Systems for and methods of automatically scheduling and executing in situ tests on electrical and mechanical systems

Inventors: Bruce Christopher Wootton (Alameda, CA); Rory Joseph Timar (San Francisco, CA); Colin Patrick Murphy (Oakland, CA); Francesco Borrelli (Kensington, CA); Allan Daly (Albany, CA)
Assignee: NEXTRACKER LLC
F24F11/49F24F11/30F24F11/48F24F11/52F24F11/61F24F11/63G05B23/0251G05B23/0256G05B2219/24053G05B2219/2614
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 11,933,511
App. No.
17/176,477
Granted
Mar 19, 2024
Kind
B2
Abstract

A testing platform tests an electrical and mechanical system such as an HVAC unit according to an algorithm that reduces the total testing time of the components of the system, while ensuring the safety of the system during system-wide testing. The platform uses constraints that are checked both before and during the testing to ensure that HVAC operating conditions are acceptable for starting and maintaining component tests. Preferably, the platform uses finite-state machines for each device to organize the component tests, allowing for monitoring of constraints and starting, pausing, and stopping component tests. Preferably, total test execution time is reduced by running component tests in parallel, running component tests based on loads of the components, or combinations of both.

Claims (20)

1. A method of testing an electrical and mechanical system comprising a plurality of interconnected devices, each device of the plurality of interconnected devices comprising one or more components, each of the one or more components being associated with a corresponding component test, the method comprising:

ranking the plurality of interconnected devices in order of decreasing loads on the plurality of interconnected devices;

selecting a first set of conditions that allow component tests to be executed on a first set of components of devices of the plurality of interconnected devices having higher loads before component tests are executed on a second set of components of devices of the plurality of interconnected devices having smaller loads; and

executing the component tests on the plurality of interconnected devices according to an execution schedule based on the first set of conditions.

2. The method of claim 1 , further comprising:

selecting a second set of conditions that postpone execution of the component tests on the second set of components until component tests have been executed on the first set of components;

wherein the execution schedule for executing the component tests on the plurality of interconnected devices is based on the first set of conditions and the second set of conditions.

3. The method of claim 2 , wherein the component tests are embodied in finite-state machines.

4. The method of claim 2 , further comprising:

grouping components of the plurality of interconnected devices into groups of components capable of being tested in parallel;

wherein the execution schedule for executing the component tests is further based on criteria comprising the groups of components capable of being tested in parallel.

5. The method of claim 4 , wherein the execution schedule for executing the component tests is further based on criteria comprising at least one constraint for starting execution of the component tests and at least one constraint for maintaining execution of the component tests to minimize a total execution time of the component tests.

6. The method of claim 3 , wherein the execution schedule for executing the component tests is further based on criteria comprising states of the finite-state machines.

7. The method of claim 5 , further comprising:

monitoring the states of the finite-state machines, and

in response to a change in the state of any of the finite-state machines, updating the at least one constraint for starting execution of the component tests, or updating the at least one constraint for maintaining execution of the component tests.

8. The method of claim 7 , further comprising:

detecting that one of the components is unresponsive to the corresponding component test;

placing the unresponsive component into a recovery state; and

updating the constraints to indicate that the unresponsive component is removed from the groups of components capable of being tested in parallel.

Assignments (3)
CHANGE OF NAME Recorded Jan 12, 2026
From: NEXTRACKER LLC
To: NEXTPOWER LLC
Reel/Frame 074318/0990 →
CHANGE OF NAME Recorded Apr 12, 2022
From: NEXTRACKER INC.
To: NEXTRACKER LLC
Reel/Frame 059682/0208 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Feb 16, 2021
From: WOOTTON, BRUCE CHRISTOPHER; TIMAR, RORY JOSEPH; MURPHY, COLIN PATRICK; BORRELLI, FRANCESCO; DALY, ALLAN
To: NEXTRACKER INC.
Reel/Frame 055312/0374 →
Continuity (4)
Continuation 16806522 · Mar 2, 2020
Continuation 15365758 · Nov 30, 2016
Provisional Application 62261205 · Nov 30, 2015
Related Publication 20210239340A1 · Aug 5, 2021