IP Library Granted Patent US 12,230,958
Granted Patent B2
US 12,230,958 · App. 17/274,980 · Granted Feb 18, 2025

Systems and methods for rapidly responding to commanded power profiles

Inventors: Masoud Abbaszadeh (Clifton Park, NY); Pierino Gianni Bonanni (Loudonville, NY); Reza Ghaemi (Watervliet, NY)
Assignee: GE DIGITAL HOLDINGS LLC
H02J13/00002G05B13/041G05B13/048
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 12,230,958
App. No.
17/274,980
Granted
Feb 18, 2025
Kind
B2
Abstract

A method for controlling a distributed power system is provided, the system including an aggregator communicatively coupled to a plurality of nodes, each of the plurality of nodes including an associated load. The method includes receiving, at the aggregator, a commanded power profile from an independent service operator, the commanded power profile including a commanded power deviation for the distributed power system, calculating, using the aggregator, a score for each of the plurality of nodes based on a current operating power of each node, selecting, using the aggregator, a subset of the plurality of nodes based on the calculated scores, and commanding, using the aggregator, each node in the subset to adjust its current power by a respective predetermined amount, the predetermined amounts determined based on the commanded power deviation.

Claims (36)

1. A method for controlling a distributed power system including an aggregator communicatively coupled to a plurality of nodes, each of the plurality of nodes including an associated load, said method comprising:

receiving, at the aggregator, a commanded power profile from an independent service operator, the commanded power profile including a commanded power deviation for the distributed power system;

calculating, using the aggregator, a score for each of the plurality of nodes based on a current power of each node, the score indicating a distance between the current power for the node and a midpoint between upper and lower power limits for the node;

selecting, using the aggregator, a subset of the plurality of nodes based on the calculated scores; and

commanding, using the aggregator, each node in the subset to adjust its current power by a respective predetermined amount, the predetermined amounts determined based on the commanded power deviation.

2. The method of claim 1 , wherein calculating a score for each of the plurality of nodes comprises calculating a score based on a distance between the current power for the node and upper and lower power limits for that node.

3. The method of claim 1 , wherein selecting a subset of the plurality of nodes comprises selecting a first predetermined fraction of the overall number of nodes.

4. The method of claim 1 , wherein the respective predetermined amounts are determined such that a sum of the predetermined amounts is equal to a second predetermined fraction of the commanded power deviation.

5. The method of claim 1 , wherein the respective predetermined amounts are equal to one another.

6. The method of claim 1 , wherein receiving a commanded power profile comprises receiving the commanded power profile after a first sample time, and wherein commanding each node in the subset to adjust its current power comprises commanding each node in the subset to adjust its current power at a second sample time that is consecutive to the first sample time.

7. The method of claim 1 , wherein receiving a commanded power profile comprises receiving the commanded power profile after a first sample time, and wherein commanding each node in the subset to adjust its current power comprises commanding each node in the subset to adjust its current power immediately after the predetermined amounts have been determined.

8. The method of claim 7 , further comprising shifting a second sample time that is consecutive to the first sample time to align with a time when each node in the subset is commanded to adjust its current power.

9. A distributed power system comprising:

a plurality of nodes, each node comprising an associated load; and

an aggregator communicatively coupled to said plurality of nodes, said aggregator configured to:

receive a commanded power profile from an independent service operator, the commanded power profile including a commanded power deviation for said distributed power system;

calculate a score for each of said plurality of nodes based on a current power of each node, the score indicating a distance between the current power for the node and a midpoint between upper and lower power limits for the node;

select a subset of said plurality of nodes based on the calculated scores; and

command each node in the subset to adjust its current power by a respective predetermined amount, the predetermined amounts determined based on the commanded power deviation.

10. The distributed power system of claim 9 , wherein to calculate a score, said aggregator is configured to calculate a score based on a distance between the current power for the node and upper and lower power limits for that node.

11. The distributed power system of claim 9 , wherein to select a subset, said aggregator is configured to select a first predetermined fraction of the overall number of nodes.

12. The distributed power system of claim 9 , wherein the respective predetermined amounts are determined such that a sum of the predetermined amounts is equal to a second predetermined fraction of the commanded power deviation.

13. The distributed power system of claim 9 , wherein the respective predetermined amounts are equal to one another.

14. The distributed power system of claim 9 , wherein to receive a commanded power profile, said aggregator is configured to receive the commanded power profile after a first sample time, and wherein to command each node in the subset, said aggregator is configured to command each node in the subset to adjust its current power at a second sample time that is consecutive to the first sample time.

15. The distributed power system of claim 9 , wherein to receive a commanded power profile, said aggregator is configured to receive the commanded power profile after a first sample time, and wherein to command each node in the subset, and said aggregator is configured to command each node in the subset immediately after the predetermined amounts have been determined.

16. An aggregator for controlling a distributed power system, said aggregator communicatively coupled to a plurality of nodes each including an associated load, said aggregator comprising:

a memory device; and

a processor communicatively coupled to said memory device, said processor configured to:

receive a commanded power profile from an independent service operator, the commanded power profile including a commanded power deviation for the distributed power system;

calculate a score for each of the plurality of nodes based on a current power of each node, the score indicating a distance between the current power for the node and a midpoint between upper and lower power limits for the node;

select a subset of the plurality of nodes based on the calculated scores; and

command each node in the subset to adjust its current power by a respective predetermined amount, the predetermined amounts determined based on the commanded power deviation.

17. The aggregator of claim 16 , wherein to calculate a score, said processor is configured to calculate a score based on a distance between the current power for the node and upper and lower power limits for that node.

18. The aggregator of claim 16 , wherein to select a subset, said processor is configured to select a first predetermined fraction of the overall number of nodes.

19. The aggregator of claim 16 , wherein the respective predetermined amounts are determined such that a sum of the predetermined amounts is equal to a second predetermined fraction of the commanded power deviation.

20. The aggregator of claim 16 , wherein to receive a commanded power profile, said processor is configured to receive the commanded power profile after a first sample time, and wherein to command each node in the subset, said processor is configured to command each node in the subset immediately after the respective predetermined amounts have been determined.

Assignments (3)
CONFIRMATORY LICENSE Recorded Feb 29, 2024
From: GENERAL ELECTRIC GLOBAL RESEARCH
To: US DEPARTMENT OF ENERGY
Reel/Frame 066602/0176 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Nov 17, 2023
From: GENERAL ELECTRIC COMPANY
To: GE DIGITAL HOLDINGS LLC
Reel/Frame 065612/0085 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Mar 12, 2021
From: ABBASZADEH, MASOUD; BONANNI, PIERINO GIANNI; GHAEMI, REZA
To: GENERAL ELECTRIC COMPANY
Reel/Frame 055571/0732 →
Continuity (1)
Related Publication 20220037916A1 · Feb 3, 2022
References Cited (35)
US 7333880B2 · Brewster et al. · 2008 [cited by applicant]
US 8260468B2 · Ippolito · 2012 [cited by examiner]
US 8674541B2 · Peitzke et al. · 2014 [cited by applicant]
US 8818889B2 · Papavasiliou · 2014 [cited by examiner]
US 9008852B2 · Forbes, Jr. · 2015 [cited by applicant]
US 9411329B2 · Greene et al. · 2016 [cited by applicant]
US 9733623B2 · Yang et al. · 2017 [cited by applicant]
US 10461540B2 · Ghaemi et al. · 2019 [cited by applicant]
US 20070276547A1 · Miller · 2007 [cited by examiner]
US 20110231320A1 · Irving · 2011 [cited by applicant]
US 20140018969A1 · Forbes, Jr. · 2014 [cited by examiner]
US 20140277808A1 · Irisarri et al. · 2014 [cited by applicant]
US 20140280899A1 · Brewster, Jr. · 2014 [cited by examiner]
US 20150012146A1 · Cherian et al. · 2015 [cited by applicant]
US 20150295405A1 · Black et al. · 2015 [cited by applicant]
US 20160056628A1 · Burstall · 2016 [cited by examiner]
US 20160347195A1 · Bridges et al. · 2016 [cited by applicant]
US 20190173282A1 · Lelusz · 2019 [cited by examiner]
CN 102437653B · 2015 [cited by applicant]
EP 2369538A1 · 2011 [cited by applicant]
EP 3376630A1 · 2018 [cited by applicant]
WO 2016027041A1 · 2016 [cited by applicant]
WO 2016172348A1 · 2016 [cited by applicant]
Brooks et al., “Demand Dispatch”, IEEE Power and Energy Magazinec, vol. 8, Issue: 3, pp. 20-29, May-Jun. 2010. [cited by applicant]
Li et al., “Control of three-phase grid-connected microgrids using artificial neural networks”, 2015 7th International Joint Conference on Computational Intelligence (IJCCI), pp. 58-69, Lisbon, 2015. [cited by applicant]
U.S. Appl. No. 15/462,136, filed Mar. 17, 2017, entitled Scalable Flexibility Control of Distributed Loads in a Power Grid. [cited by applicant]
Ferrarini, et al., “A Distributed Model Predictive Control approach for the integration of flexible loads, storage and renewables,” 2014 IEEE 23rd International Symposium on Industrial Electronics (ISIE), 6 pages. [cited by applicant]
Babar, et al., “The conception of the aggregator in demand side management for domestic consumers,” International Journal of Smart Grid and Clean Energy, vol. 2, No. 3, Oct. 2013, 5 pages. [cited by applicant]
Halvgaard, et al., “Thermal Storage Power Balancing with Model Predictive Control,” 2013 European Control Conference (ECC) Jul. 17-19, 2013, Zurich, Switzerland, 6 pages. [cited by applicant]
Ghaemi, et al., “Scalable Optimal Flexibility Control of Distributed Loads in Power Grid,” Last Accessed: May 2, 2017, 7 pages. [cited by applicant]
Extended European Search Report, dated Jul. 2, 2018, for related EP patent application No. EP 18151437.3. [cited by applicant]
Oukarakis E., et al., “Investigation of Maximum Possible OPF Problem Decomposition Degree for Decentralized Energy Markets,” IEEE Transactions on Power Systems, IEEE Service Center, Piscataway, NJ, US, vol. 30, No. 5, S… [cited by applicant]
Motto, et al., “On Walrasian Equilibrium for Pool-Based Electricity Markets,” IEEE Transactions on Power Systems, vol. 17, No. 3, Aug. 1, 2002, pp. 774-781. [cited by applicant]
Xu, et al., “Operation Strategies of the Load Aggregator with Electric Energy Storage,” 2012 IEEE International Conference on Power System Technology (POWERCON), 6 pages. [cited by applicant]
International Search Report and Written Opinion, dated Nov. 12, 2018, for PCT/US/2020/0050903 (16 pgs.). [cited by applicant]