IP Library Granted Patent US 11,802,460
Granted Patent B2
US 11,802,460 · App. 17/505,127 · Granted Oct 31, 2023

Station keeping and emergency disconnecting capability for a vessel connected to a subsea wellhead in shallow water

Inventors: Craig Mccormick (Tomball, TX); Scott Reynolds (Houston, TX); Darrel Pelley (Houston, TX)
Assignee: TRANSOCEAN SEDCO FOREX VENTURES LIMITED
E21B33/063E21B33/038E21B33/0355E21B33/064E21B47/001
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 11,802,460
App. No.
17/505,127
Granted
Oct 31, 2023
Kind
B2
Abstract

In some embodiments, a method for executing an emergency disconnect sequence in shallow water depth includes unlatching a lower marine riser package (LMRP) of a blowout preventer (BOP) from a lower stack of the BOP. The BOP defines a wellbore fluidically coupled to the subsea wellhead. A tubular is disposed within the wellbore. The method further includes shearing the tubular and sealing the wellbore. In response to an indication that a vessel operably coupled to the BOP has failed to keep station, an unlatch sequence and a shear and seal sequence are initiated, such that each sequence occurs at least partially simultaneously. The unlatch sequence includes disconnecting the LMRP from the lower stack, and the shear and seal sequence includes activating the lower stack to shear the tubular in less than about one second and seal the wellbore.

Claims (56)

1. A method for executing an emergency disconnect sequence in shallow water depth including (1) unlatching a lower marine riser package (LMRP) of a blowout preventer (BOP) from a lower stack of the BOP, the BOP (a) defining a wellbore fluidically coupled to the subsea wellhead, and (b) having a tubular disposed within the wellbore, and (2) shearing the tubular and sealing the wellbore, the method comprising:

in response to an indication that a vessel operably coupled to the BOP has failed to keep station, initiating, using a control system disposed at the lower stack of the BOP and not the LMRP, both (1) an unlatch sequence, and (2) a shear and seal sequence,

the unlatch sequence including disconnecting the LMRP from the lower stack,

the shear and seal sequence including activating the lower stack to shear the tubular and seal the wellbore, wherein following initiation of the unlatch sequence and the shear and seal sequence, the unlatch sequence and the shear and seal sequence are controlled independent of all components of any offshore drilling platform and independent of all components of any vessel.

2. The method of claim 1 , wherein the unlatch sequence includes retracting at least one of a stinger or a stab.

3. The method of claim 1 , wherein the activating the BOP includes:

(1) sealing the wellbore within the BOP and external to the tubular, and (2) shearing the tubular using chemical energy stored subsea.

4. The method of claim 1 , wherein the activating the BOP includes activating a hydraulically-actuated shear blind ram to seal the wellbore using hydraulic energy (1) stored subsea and (2) that was pressurized using a pump mounted to the lower stack.

5. The method of claim 1 , wherein the LMRP has a mandrel and the lower stack has a connector removably coupled to the mandrel, and wherein the mandrel is a male component and the connector is a female component.

6. The method of claim 1 , wherein the shallow water depth is less than 1,000 feet.

7. The method of claim 1 , wherein the shallow water depth is less than 450 feet.

8. The method of claim 1 , wherein:

the activating the lower stack to shear the tubular includes using pyrotechnics to shear the tubular, the activating the lower stack includes closing a shear blind ram to seal the wellbore, and

the unlatch sequence includes initiating retraction of at least one of a stinger or a stab before the closing the shear blind ram to seal the wellbore is complete.

9. The method of claim 1 , wherein the activating the BOP includes:

(1) sealing the wellbore within the BOP and external to the tubular, and (2) shearing the tubular using pyrotechnics.

10. The method of claim 1 , wherein:

the activating the lower stack to shear the tubular includes using hydraulic power from a pyrotechnic accumulator to shear the tubular,

the activating the lower stack includes closing a shear blind ram to seal the wellbore, and

the unlatch sequence includes initiating retraction of at least one of a stinger or a stab before the closing the shear blind ram to seal the wellbore is complete.

11. The method of claim 1 , wherein the activating the BOP includes:

sealing the wellbore using a pyrotechnic accumulator coupled to the lower stack and configured to provide power to the shear blind ram to seal the wellbore.

12. The method of claim 1 , wherein the emergency disconnect sequence is completed in less than about 30 seconds.

13. The method of claim 1 , wherein the emergency disconnect sequence is completed in less than about 15 seconds.

14. The method of claim 1 , wherein the emergency disconnect sequence is completed in less than about 10 seconds.

15. A method for executing an emergency disconnect sequence in shallow water depth including (1) disconnecting an annular blowout preventer (BOP) from a mandrel of a LMRP to which it is coupled via a frangible fastener, the mandrel being latched to a connector of a lower stack of the BOP, the BOP (a) defining a wellbore fluidically coupled to a subsea wellhead, and (b) having a tubular disposed within the wellbore, and (2) shearing the tubular and sealing the wellbore, the method comprising:

in response to an indication that a vessel operably coupled to the BOP needs to disconnect from the subsea wellhead, initiating both (1) a disconnect sequence, and (2) a shear and seal sequence, such that the disconnect sequence is completed before the shear and seal sequence is completed,

the disconnect sequence including causing the frangible fastener to fracture such that the annular BOP is decoupled from the mandrel of the LMRP,

the shear and seal sequence including activating a shear ram of the lower stack to shear the tubular in less than about one second and seal the wellbore,

wherein the sealing the wellbore includes activating a shear blind ram of the lower stack to seal the wellbore such that the wellbore is sealed after the activating the shear ram and after the causing the frangible fastener to fracture.

16. The method of claim 15 , wherein the activating the shear ram to shear the tubular and the causing the frangible fastener to fracture occur substantially simultaneously.

17. The method of claim 15 , wherein the initiating includes using a control system disposed at the lower stack of the BOP and not the LMRP, and following initiation of the unlatch sequence and the shear and seal sequence, the unlatch sequence and the shear and seal sequence are controlled independent of all components of any offshore drilling platform or vessel, other than the BOP.

18. The method of claim 15 , wherein the indication is based on at least one of a riser angle, data from a global positioning system, a bending moment associated with the riser, a tensioner stroke, or a telescopic joint.

19. The method of claim 15 , wherein the indication is based on detecting that the vessel has failed to keep station.

20. The method of claim 15 , wherein the shearing the tubular includes using hydraulic power from a pyrotechnic accumulator to power the shear ram.

21. The method of claim 15 , wherein the sealing the wellbore includes using hydraulic power from a pyrotechnic accumulator to power the shear ram.

22. The method of claim 15 , wherein the emergency disconnect sequence is completed in less than about 30 seconds.

23. The method of claim 15 , wherein the emergency disconnect sequence is completed in less than about 15 seconds.

24. The method of claim 15 , wherein the emergency disconnect sequence is completed in less than about 10 seconds.

25. The method of claim 15 , wherein the emergency disconnect sequence is completed in less than about 30 seconds.

26. The method of claim 15 , wherein the emergency disconnect sequence is completed in less than about 15 seconds.

27. The method of claim 15 , wherein the emergency disconnect sequence is completed in less than about 10 seconds.

28. A blow-out preventer (BOP) system, comprising:

a lower marine riser package (LMRP), and a lower stack coupled to the LMRP, a control system configured to send a signal to initiate a both (1) an unlatch sequence, and (2) a shear and seal sequence,

the unlatch sequence including disconnecting the LMRP from the lower stack,

the shear and seal sequence including activating a ram to shear a tubular disposed within a wellbore of the BOP and activating the ram or a second ram to seal the wellbore,

wherein the LMRP has a mandrel and the lower stack has a connector removably coupled to the mandrel, and wherein the disconnecting includes transferring energy from a connector to a mandrel to unlatch the LMRP from the lower stack.

29. The BOP system of claim 28 , wherein the shear and seal sequence includes using at least one of pyrotechnics, hydraulics, chemical energy, or electrical energy to at least one of shear the tubular or seal the wellbore.

30. The BOP system of claim 28 , wherein the initiating includes using a control system disposed at the lower stack of the BOP and not the LMRP, and following initiation of the unlatch sequence and the shear and seal sequence, the unlatch sequence and the shear and seal sequence are controlled independent of all components of any offshore drilling platform and independent of all components of any vessel.

31. The BOP system of claim 28 , further comprising:

a subsea pumping station coupled to the lower stack and configured to provide hydraulic power to the ram or to the second ram to seal the wellbore.

32. The BOP system of claim 28 , wherein the shear and seal sequence includes activating the ram to shear the tubular using battery-powered hydraulics and activating the ram or the second ram to seal the wellbore using battery-powered hydraulics.

33. The BOP system of claim 28 , wherein the shear and seal sequence includes activating the ram or the second ram to pyrotechnically shear the tubular.

34. The BOP system of claim 28 , wherein the shear and seal sequence includes activating the ram or the second ram to pyrotechnically seal the wellbore.

35. The BOP system of claim 28 , wherein the shear and seal sequence includes powering the ram or the second ram by a pyrotechnic accumulator to shear the tubular.

36. The BOP system of claim 28 , wherein the shear and seal sequence includes powering the ram or the second ram by a pyrotechnic accumulator to seal the wellbore.

Assignments (2)
CHANGE OF ADDRESS Recorded Dec 20, 2024
From: TRANSOCEAN SEDCO FOREX VENTURES LIMITED
To: TRANSOCEAN SEDCO FOREX VENTURES LIMITED
Reel/Frame 069868/0658 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Oct 20, 2021
From: MCCORMICK, CRAIG; REYNOLDS, SCOTT; PELLEY, DARREL
To: TRANSOCEAN SEDCO FOREX VENTURES LIMITED
Reel/Frame 057843/0372 →
Continuity (4)
Continuation 16857510 · Apr 24, 2020
Continuation PCTUS2020029241 · Apr 22, 2020
Provisional Application 62839205 · Apr 26, 2019
Related Publication 20220251920A1 · Aug 11, 2022