Systems and methods for virtual commissioning of building management systems

Inventors: Xin Zhang (Hartland, WI); Bryan A. Register (Brookfield, WI); Matthew P. Kaiser (Milwaukee, WI); Gregory T. Reichl (Kaukana, WI)
Assignee: Johnson Controls Tyco IP Holdings LLP
G05B19/042G06F8/61G05B2219/25011G05B2219/2614
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 11,971,692
App. No.
18/199,261
Granted
Apr 30, 2024
Kind
B2
Abstract

A system for virtual commissioning of a building management system includes one or more memory devices configured to store instructions that, when executed by one or more processors, cause the one or more processors to: receive, at a virtual server, product installation data from a building management system controller installed at a building site via a first connection, the product installation data corresponding to a product installation at the building site; receive, commissioning data from the remote commissioning system via a second connection; configure one or more products installed at the building site to be controlled by the virtual building management system on the virtual server; and selectively transfer control of the one or more products installed at the building site from the virtual building management system hosted at on the virtual server to the building management system controller installed at the building site.

Claims (26)

1. A method for virtually commissioning a building management system comprising:

installing a virtual building management system on a virtual server, wherein the virtual server is communicatively connected to a building management system controller installed at a building site;

receiving, at the virtual server, product installation data, wherein the product installation data corresponds to one or more products at the building site;

configuring the one or more products installed at the building site to be controlled by the virtual building management system on the virtual server; and

selectively transferring control of the one or more products installed at the building site from the virtual building management system hosted by the virtual server to the building management system controller installed at the building site and from the building management system controller at the building site to the virtual building management system hosted on the virtual server.

2. The method of claim 1 , further comprising:

receiving, at the virtual server, the product installation data from the building management system controller installed at the building site a first connection, wherein the product installation data corresponds to a product installation at the building site, wherein the product installation data from the building management system comprises configuration, status, state, connectivity, self-test, and operational data of one or more building equipment products installed at the building site.

3. The method of claim 2 , wherein the product installation data from the building management system is provided to the virtual server on a real time or near real time basis.

4. The method of claim 2 , further comprising:

receiving, at the virtual server, commissioning data from a remote commissioning system via a second connection, wherein the commissioning data from the remote commissioning system comprises one or more of a configuration, an application, a command, a test procedure, a control strategy, a validation procedure, and operational instruction.

5. The method of claim 2 , wherein the first connection is a secure connection.

6. The method of claim 2 , wherein the first connection is a virtual private network connection.

7. The method of claim 2 , wherein the building management system controller is configured with a network automation engine.

8. The method of claim 1 , wherein the selectively transferring control of the one or more products installed at the building site comprises retaining control of the one or more products installed at the building site by the virtual building management system on the virtual server.

9. The method of claim 1 , wherein the selectively transferring control of the one or more products installed at the building site comprises replication of the virtual building management system on a building site server.

10. A system for virtual commissioning of a building management system, the system comprising one or more memory devices configured to store instructions that, when executed by one or more processors, cause the one or more processors to:

receive, at a virtual server, product installation data from a building management system controller installed at a building site via a first connection, wherein the product installation data corresponds to a product installation comprising one or more products at the building site;

configure the one or more products installed at the building site to be controlled by a virtual building management system on the virtual server; and

selectively transfer control of the one or more products installed at the building site from the virtual building management system hosted on the virtual server to the building management system controller installed at the building site and from the building management system controller at the building site to the virtual building management system hosted on the virtual server.

11. The system of claim 10 , wherein the product installation data from the building management system at the building site comprises identification, configuration, status, state, connectivity, self-test, and operational data for one or more building systems.

12. The system of claim 10 , wherein the product installation data from the building management system at the building site is provided to the virtual server on a real time or near real time basis.

13. The system of claim 10 , where in the instructions are configured to receive, at the virtual server, commissioning data from a remote commissioning system, wherein the commissioning data from the remote commissioning system comprises one or more of a configuration, an application, a command, a test procedure, a control strategy, a validation procedure, and operational instruction.

14. The system of claim 10 , wherein the first connection is secure connection or a virtual private network connection.

15. The system of claim 10 , wherein the building management system controller is configured with a network automation engine.

16. The system of claim 10 , wherein the selectively transfer control of the one or more products installed at the building site comprises retaining control of the one or more products installed at the building site by the virtual building management system on the virtual server.

17. The system of claim 10 , wherein selectively transferring control of the one or more products installed at the building site comprises replication of the virtual building management system on a building site server.

Assignments (3)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Mar 19, 2024
From: ZHANG, XIN; REGISTER, BRYAN A; KAISER, MATTHEW P.; REICHL, GREGORY T.
To: JOHNSON CONTROLS TECHNOLOGY COMPANY
Reel/Frame 066822/0626 →
NUNC PRO TUNC ASSIGNMENT Recorded Mar 19, 2024
From: JOHNSON CONTROLS TECHNOLOGY COMPANY
To: JOHNSON CONTROLS TYCO IP HOLDINGS LLP
Reel/Frame 066822/0810 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Mar 18, 2024
From: JOHNSON CONTROLS TYCO IP HOLDINGS LLP
To: TYCO FIRE & SECURITY GMBH
Reel/Frame 066957/0796 →