METHOD AND ARRANGEMENT FOR COUPLING A FOUNDATION STRUCTURE AND A VERTICAL PRECAST STRUCTURE

Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US None
App. No.
18/584,823
Abstract

A connection assembly mechanism includes a threaded connector, a hollow box section member, a set of elongated connectors, and a connection mechanism. The threaded connector is embedded in a foundation structure. The hollow box section member having a base including a threaded cavity receives the threaded connector and is flush mounted with an internal bottom edge of a vertical precast structure. The set of elongated connectors, positioned at opposite vertical sides of the hollow box section member, is embedded within the vertical precast structure. The connection mechanism coupling the hollow box section member and the threaded connector, thereby couples the vertical precast structure and the foundation structure.

Claims (30)

1 . A connection assembly mechanism comprising:

a threaded connector configured for embedding in a foundation structure;

a hollow box section member having a base including a threaded cavity configured for receiving the threaded connector, the hollow box section member configured for flush mounting with an internal bottom edge of a vertical precast structure;

a set of elongated connectors positioned at opposite vertical sides of the hollow box section member, wherein each of the elongated connectors is configured for embedding within the vertical precast structure; and

a connection mechanism configured for coupling the hollow box section member and the threaded connector, thereby coupling the vertical precast structure and the foundation structure.

2 . The connection assembly mechanism according to claim 1 , wherein the connection mechanism corresponds to a mechanical fastener.

3 . The connection assembly mechanism according to claim 1 , further comprising a plate member configured for distributing a load under the mechanical fastener when the vertical precast structure is affixed with the foundation structure at a construction site,

wherein the plate member includes a cavity configured for receiving the threaded connector.

4 . The connection assembly mechanism according to claim 1 , wherein the hollow box section member is further configured for flush-mounting with the internal bottom edge of the vertical precast structure such that the hollow box section member is accessible for the coupling with the threaded connector from an internal side of the vertical precast structure.

5 . The connection assembly mechanism according to claim 1 , wherein the threaded connector corresponds to a cast-in-place anchor bolt.

6 . The connection assembly mechanism according to claim 1 , wherein the threaded connector corresponds to a post-installed anchor bolt set onto anchoring adhesive.

7 . The connection assembly mechanism according to claim 1 , wherein the foundation structure corresponds to a monolithic cast-in-place foundation structure.

8 . The connection assembly mechanism according to claim 1 , further comprising a sealant sealing a gap between the hollow box section member flush-mounted with the internal bottom edge of the vertical precast structure and a top surface of the foundation structure.

9 . A connection method, comprising:

embedding a threaded connector in a foundation structure;

flush-mounting a hollow box section member with an internal bottom edge of a vertical precast structure,

wherein a set of elongated connectors, positioned at opposite vertical sides of the hollow box section member, is embedded within the vertical precast structure;

receiving the threaded connector through a threaded cavity at a base of the hollow box section member; and

coupling the hollow box section member and the threaded connector using a connection mechanism, thereby coupling the vertical precast structure with the foundation structure.

10 . The connection method according to claim 9 , further comprising determining a type, quantity, and size of a connection assembly mechanism for coupling the foundation structure and the vertical precast structure based on a first set of parameters associated with the connection assembly mechanism and a second set of parameters associated with at least one of the foundation structure and the vertical precast structure.

11 . The connection method according to claim 10 , wherein the first set of parameters includes material specifications of the connection assembly mechanism.

12 . The connection method according to claim 11 , wherein the material specifications of the connection assembly mechanism correspond to at least tensile strength and hardness of the connection assembly mechanism.

13 . The connection method according to claim 10 , wherein the second set of parameters includes at least one of a location, an orientation, and a weight of at least one of the foundation structure and the vertical precast structure and environmental conditions.

14 . The connection method according to claim 9 , wherein the hollow box section member and the threaded connector are mechanically coupled using a mechanical fastener for coupling the vertical precast structure with the foundation structure at a construction site.

15 . The connection method according to claim 14 , further comprising distributing a load under the mechanical fastener using a plate member when the vertical precast structure is affixed with the foundation structure at the construction site.

16 . The connection method according to claim 9 , wherein the hollow box section member is flush-mounted with the internal bottom edge of the vertical precast structure such that the hollow box section member is accessible for the mechanical coupling with the foundation structure from an internal side of the vertical precast structure.

17 . The connection method according to claim 9 , wherein the threaded connector corresponds to a cast-in-place anchor bolt.

18 . The connection method according to claim 9 , wherein the threaded connector corresponds to post-installed anchor bolt set onto anchoring adhesive.

19 . The connection method according to claim 9 , wherein the foundation structure corresponds to a monolithic cast-in-place foundation structure.

20 . The connection method according to claim 9 , further comprising scaling a gap between the hollow box section member flush-mounted with an internal bottom edge of the vertical precast structure and a top surface of the foundation structure with a scalant.

Assignments (6)
CORRECTIVE ASSIGNMENT TO CORRECT THE US18/615,986 WAS INCORRECTLY IDENTIFIED AS US18/615,896 ON THE ORIGINAL SECURITY AGREEMENT AND ON THE USPTO COVER PAGE. PREVIOUSLY RECORDED ON REEL 67418 FRAME 492. ASSIGNOR(S) HEREBY CONFIRMS THE SECURITY INTEREST. Recorded Jan 15, 2026
From: ONX, INC.
To: ODYSSEY REINSURANCE COMPANY
Reel/Frame 075354/0646 →
CORRECTIVE ASSIGNMENT TO CORRECT THE APPLICATION NUMBER PREVIOUSLY RECORDED AT REEL: 67309 FRAME: 719. ASSIGNOR(S) HEREBY CONFIRMS THE ASSIGNMENT . Recorded Dec 10, 2025
From: ONX, INC.
To: ALTER DOMUS (US) LLC
Reel/Frame 074974/0237 →
SECURITY INTEREST Recorded May 15, 2024
From: ONX, INC.
To: ODYSSEY REINSURANCE COMPANY
Reel/Frame 067418/0492 →
NOTICE OF GRANT OF SECURITY INTEREST IN PATENTS Recorded May 3, 2024
From: ONX, INC.
To: ALTER DOMUS (US) LLC
Reel/Frame 067309/0719 →
SECURITY INTEREST Recorded May 3, 2024
From: ONX, INC.
To: MRB ENTERPRISES LLC
Reel/Frame 067313/0747 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded May 2, 2024
From: MAHENDRAN, THULASILINGAM; RAJENDRAN, PRATHEEP KUMAR; AGCAOILI, MC GIL DOMINGO
To: ONX, INC.
Reel/Frame 067298/0690 →