A method of pumping DEF (diesel exhaust fluid) in a diesel emissions control system. The method includes pumping DEF from an auxiliary DEF tank to an onboard DEF tank. The DEF is pumped from the auxiliary DEF tank to the onboard DEF tank. The fluid pathway is purged with air after pumping the DEF from the auxiliary DEF tank to the onboard DEF tank. The air is pumped (1) through the fluid pathway from the auxiliary DEF tank, or (2) into the auxiliary DEF tank.
1 . A method of pumping DEF fluid from an auxiliary DEF tank into an onboard DEF tank through a DEF line, the method comprising:
determining that the amount of DEF in the onboard DEF tank is at or below a lower threshold value;
activating a pump to pump DEF from the auxiliary DEF tank through a DEF line into the onboard DEF tank;
determining that the amount of DEF in the onboard DEF tank is at or above an upper threshold; and
activating the pump to pump DEF from the DEF line into the auxiliary DEF tank.
2 . The method of claim 1 , further comprising determining that an engine is running.
3 . The method of claim 1 , wherein activating the pump to pump DEF from the DEF line into the auxiliary DEF tank comprises purging DEF from the DEF line in a diesel emissions control system.
4 . The method of claim 1 , wherein the upper threshold is 70% of the volume of the onboard DEF tank.
5 . The method of claim 1 , wherein the pump is a reversible peristaltic pump.
6 . The method of claim 5 , wherein activating the pump to pump DEF from the DEF line into the auxiliary DEF tank further comprises reversing the direction of the pump.
7 . A method of pumping DEF fluid from an auxiliary DEF tank into an onboard DEF tank, the method comprising:
determining that the amount of DEF in the onboard DEF tank is at or below a lower threshold value;
activating a pump to perform a first pumping sequence comprising pumping from the auxiliary DEF tank toward the onboard DEF tank for a predetermined time interval; and
activating the pump to perform a second pumping sequence, the second pumping sequence comprising pumping air from the onboard DEF tank into the auxiliary DEF tank.
8 . The method of claim 7 , wherein the predetermined time interval is greater than the amount of time required to fill the onboard DEF tank to an upper threshold value from the lower threshold value.
9 . The method of claim 8 , further comprising interrupting the first pumping sequence when the amount of DEF in the onboard DEF tank is determined to reach the upper threshold value.
10 . The method of claim 7 , wherein the predetermined time interval is less than or equal to the amount of time required to fill the onboard DEF tank from the lower threshold value.
11 . The method of claim 7 , wherein the predetermined time interval is comprised of a first time interval and a second time interval, the first time interval being the amount of time required to fill the onboard DEF tank to an upper threshold value from the lower threshold value; the second time interval being equal to or greater than the amount of time required to purge DEF from a fluid pathway between the pump and the auxiliary DEF tank.
12 . The method of claim 7 , wherein the pump is a reversible peristaltic pump.
13 . The method of claim 7 , wherein activating the pump to perform the second pumping sequence comprises reversing the direction of the pump.
14 . A method of pumping DEF fluid from an auxiliary DEF tank into an onboard DEF tank, the method comprising:
determining that the amount of DEF in the onboard DEF tank is at or below a lower threshold value;
activating a pump to perform a first pumping sequence comprising pumping from the auxiliary DEF tank toward the onboard DEF tank for a predetermined time interval;
wherein the predetermined time interval is at least the amount of time required to fill the onboard DEF tank to an upper threshold value from the lower threshold value; and
interrupting the first pumping sequence when the amount of DEF in the onboard DEF tank is determined to reach the upper threshold value.
15 . The method of claim 14 , wherein the predetermined time interval is greater than the amount of time required to fill the onboard DEF tank to the upper threshold value from the lower threshold value.
16 . The method of claim 14 , further comprising activating the pump to perform a second pumping sequence, the second pumping sequence comprising pumping air from the onboard DEF tank into the auxiliary DEF tank.
17 . A method of pumping DEF fluid from an auxiliary DEF tank into an onboard DEF tank, the method comprising:
determining that the amount of DEF in the onboard DEF tank is at or below a lower threshold value;
activating a pump to perform a first pumping sequence comprising pumping from the auxiliary DEF tank toward the onboard DEF tank for a predetermined time interval;
wherein the predetermined time interval is at least the amount of time required to fill the onboard DEF tank to an upper threshold value from the lower threshold value; and
activating the pump to perform a second pumping sequence comprising pumping air through at least a portion of a fluid pathway between the auxiliary DEF tank and the pump.
18 . The method of claim 17 , wherein the second pumping sequence comprises pumping air from the onboard DEF tank into the auxiliary DEF tank.
19 . A method of pumping DEF fluid from an auxiliary DEF tank into an onboard DEF tank, the method comprising:
determining that the amount of DEF in the onboard DEF tank is at or below a lower threshold value;
activating a pump to perform a first pumping sequence comprising pumping from the auxiliary DEF tank toward the onboard DEF tank;
determining that the auxiliary DEF tank is empty, wherein determining that the auxiliary DEF tank is empty comprises:
measuring a fluid level in the onboard DEF tank over a predetermined amount of time, wherein the predetermined amount of time is at least the amount of time required to purge DEF from a fluid pathway between the pump and the auxiliary DEF tank; and
stopping the pump.
20 . The method of claim 19 , further comprising interrupting the first pumping sequence when the amount of DEF in the onboard DEF tank is determined to reach an upper threshold value.