IP Library Granted Patent US 8,518,586
Granted Patent B2
US 8,518,586 · App. 12/998,737 · Granted Aug 27, 2013

Preventing air intrusion into hydrogen-stabilized fuel cells during shutdown

Inventor: Michael L. Perry (Glastonbury, CT)
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,518,586
App. No.
12/998,737
Granted
Aug 27, 2013
Kind
B2
Abstract

During a process of shutting down a fuel cell power plant ( 11 ) the exits ( 28 ) of the anodes ( 14 ) are vented ( 76 - 77 ) under liquid ( 57 ). The liquid may be that of a coolant accumulator ( 57 ) of a fuel cell stack ( 12 ) cooled by conduction and convection of sensible heat into liquid coolant (FIG. 1 ) or evaporatively cooled (FIG. 4 ). The vent ( 77 ) may be under liquid all of the time (FIGS. 1, 3 and 4 ) or only after the stack has been drained of coolant (FIG. 2 ). The vent ( 77 ) may be the only vent for the anode exits (FIG. 3 ), or there may also be a purge vent valve ( 31 ) (FIGS. 1 and 4 ).

Claims (16)

1. A method comprising:

(a) stabilizing hydrogen in the anodes ( 17 ) and cathodes ( 13 ) of a stack ( 12 ) of fuel cells by providing hydrogen to inlets ( 25 ) of the fuel cell anodes ( 14 ) while supply of fresh air to the inlets ( 42 ) of the cathodes ( 12 ) is blocked by the closure an air inlet valve ( 38 );

characterized by:

(b) venting ( 30 , 76 - 77 ) exits ( 28 ) of the anodes into liquid of an accumulator ( 57 ).

2. A method according to claim 1 further characterized by step (a) including recycling ( 46 , 49 - 51 ) cathode exhaust from exits ( 45 ) of the cathodes to the inlet of an air blower ( 40 ) connected to inlets ( 42 ) of the cathodes.

3. A method according to claim 1 further characterized in that said steps (a) and (b) are performed while fuel is being recycled from the anode exits ( 60 ) to the anode inlets ( 25 ).

4. A method according to claim 1 further characterized in that said steps (a) and (b) are performed while a fuel purge valve ( 31 ) is closed.

5. A method according to claim 1 further characterized in that said steps (a) and (b) are performed while a cathode exhaust valve ( 47 ) is closed.

6. A fuel cell power plant ( 11 ) comprising:

a stack ( 12 ) of fuel cells, each fuel cell having fuel reactant gas flow fields ( 14 ) with inlets ( 25 ) and outlets ( 28 );

characterized by:

said outlets ( 28 ) being vented into liquid of an accumulator ( 57 ).

7. A fuel cell power plant according to claim 6 further characterized in that said outlets ( 28 ) are vented by a conduit ( 76 , 77 ) which extends only part way ( FIG. 2 ) into the accumulator ( 57 ) so that they are vented into liquid of the accumulator ( 57 ) only when coolant in the fuel cells of the stack has been drained into the accumulator.

8. A fuel cell power plant ( 11 ) according to claim 6 further characterized in that said outlets ( 28 ) are vented by a conduit ( 76 , 77 ) which extends to the bottom ( FIGS. 1 , 3 and 4 ) of the accumulator ( 57 ) so that they are vented into liquid of the accumulator ( 57 ) at all times.

9. A fuel cell power plant ( 11 ) according to claim 6 further characterized in that said outlets ( 28 ) are also selectively vented through a purge valve ( 31 ).

10. A fuel cell power plant ( 11 ) according to claim 6 further characterized in that said outlets ( 28 ) are vented into liquid of the accumulator ( 57 ) through conduits ( 76 , 77 ) having a flow control valve ( 78 ) disposed between them.

Assignments (5)
CORRECTIVE ASSIGNMENT TO CORRECT ASSIGNEE ADDRESS PREVIOUSLY RECORDED AT REEL 035716, FRAME 0253. ASSIGNOR(S) HEREBY CONFIRMS THE ASSIGNMENT. Recorded Aug 24, 2015
From: BALLARD POWER SYSTEMS INC.
To: AUDI AG
Reel/Frame 036448/0093 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded May 18, 2015
From: BALLARD POWER SYSTEMS INC.
To: AUDI AG
Reel/Frame 035716/0253 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded May 30, 2014
From: UNITED TECHNOLOGIES CORPORATION
To: BALLARD POWER SYSTEMS INC.
Reel/Frame 033070/0235 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Aug 19, 2013
From: UTC POWER CORPORATION
To: UNITED TECHNOLOGIES CORPORATION
Reel/Frame 031033/0325 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded May 25, 2011
From: PERRY, MICHAEL L.
To: UTC POWER CORPORATION
Reel/Frame 026421/0526 →
Continuity (1)
Related Publication 20110223495A1 · Sep 15, 2011