IP Library Granted Patent US 6,874,224
Granted Patent B2
US 6,874,224 · App. 10/175,888 · Granted Apr 5, 2005

Method for manufacturing a multi-site spare three-phase transformer

Assignee: Waukesha Electric Systems, Inc.
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 6,874,224
App. No.
10/175,888
Granted
Apr 5, 2005
Kind
B2
Abstract

A three phase transformer circuit is provided that includes a supply side, wherein the supply side is selectably configurable, via the use of se of terminal boards, between a delta connection and a wye connection at a time of use and, a load side, wherein the load side is selectably configurable between a delta connection and a wye connection at the time of use. The three-phase transformer also provides for selecting an input voltage, from multiple input voltages, via the sets of terminal boards, at the time of use, and for selecting an output voltage for the supply side, from multiple output voltage, at the time of use.

Claims (8)

1. A method for manufacturing circuitry of a multi-site three-phase transformer, comprising the steps of:

dividing the circuitry into a supply side and a load side;

connecting a winding start lead from each of three sets of supply windings, individually, to a respective one of three sets of supply terminal boards for connecting the three sets of windings in one of a delta and a wye configuration;

dividing outer windings on the supply side into a top portion and a bottom portion; and

connecting supply terminal board start leads and a finish lead from each of the top portion and the bottom portion, to the respective supply terminal board for controlling a voltage output from the circuitry.

2. The method of claim 1 , further comprising extending tap leads from the outer windings.

3. The method of claim 1 , further comprising connecting each of the start leads of the top portion to a start terminal board.

4. The method of claim 3 , further comprising connecting a start lead and a finish lead of the inner windings to the start terminal board.

Assignments (3)
CHANGE OF NAME Recorded May 3, 2021
From: WAUKESHA ELECTRIC SYSTEMS, INC.
To: SPX TRANSFORMER SOLUTIONS, INC.
Reel/Frame 056122/0059 →
RE-RECORD TO CORRECT THE EXECUTION DATES FOR THE FIRST & SECOND ASSIGNORS, PREVIOUSLY RECORDED ON REEL 016812 FRAME 0186. Recorded Apr 10, 2006
From: AHUJA, RAJENDRA; NGUYEN, JOSEPH; JAFARNIA, MOSTAFA
To: WAUKESHA ELECTRIC SYSTEMS, INCORPORATED (WI CORP.)
Reel/Frame 017458/0731 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Feb 10, 2005
From: AHUJA, RAJENDRA; NGUYEN, JOSEPH; JAFARNIA, MOSTAFA
To: WAUKESHA ELECTRIC SYSTEMS, INCORPORATED
Reel/Frame 016812/0186 →
Continuity (1)
Related Publication 20030234639A1 · Dec 25, 2003