IP Library Granted Patent US 7,253,538
Granted Patent B2
US 7,253,538 · App. 11/057,158 · Granted Aug 7, 2007

Method of supplying electric power from shore to ship and system thereof

Assignee: Japan Radio & Electric Mfg. Co., Ltd.
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 7,253,538
App. No.
11/057,158
Granted
Aug 7, 2007
Kind
B2
Abstract

A method and a system of supplying electric power from shore to a ship with generators 60, 61 , the ship being berthed in port include: a first step of synchronizing the electric power 11 from shore with electric power from the generators 60, 61 , a second step of carrying out temporary parallel operation of the electric power 11 from shore and the electric power from the generators 60, 61 after the synchronization, and a third step of shutting off the electric power from the generators 60, 61 to supply the electric power 11 from shore to the ship after the temporary parallel operation. According to the method and system, electric power supply interruption can be prevented when a shore power source is changed over to an onboard power source, and vice versa. Also, onboard control devices can be smoothly operated even on the way of changing over the power sources.

Claims (15)

1. A method of supplying electric power from shore to a ship with at least one generator, the ship being berthed in port, comprising:

a first step of synchronizing the electric power from shore with electric power from the generator,

a second step of carrying out temporary parallel operation of the electric power from shore and the electric power from the generator after the synchronizing of the first step, and

a third step of shutting off the electric power from the generator to supply the electric power from shore to the ship after the temporary parallel operation of the second step,

wherein the ship is provided with cargo-handling equipment requiring a large capacity of electric power and being usually supplied with the electric power from the generator, and a line of the electric power from shore is divided into a second line and a first line, the second line being used to supply the electric power from shore to the cargo-handling equipment, the first line being used to supply the electric power from shore to ordinary load other than the cargo-handling equipment, the method further comprising:

a first process of supplying the electric power from shore to the cargo-handling equipment by connecting the second line to the cargo-handling equipment after shutting off the electric power from the generator to the cargo-handling equipment, and

a second process of supplying the electric power from shore to the ordinary load via the first line by carrying out the first step to the third step.

2. A method of supplying electric power from shore to a ship according to claim 1 , the ship being provided with not only the cargo-handling equipment and the ordinary load but also propulsion auxiliary equipment requiring a large capacity of electric power,

wherein supply of the electric power from shore to the ordinary load of the ship via the first line is carried out by using a part or a whole of a power line for the propulsion auxiliary equipment.

3. A system for supplying electric power from shore to a ship being berthed in port, the ship being provided with not only ordinary load including onboard lighting equipment and electronic devices supplied with electric power from an onboard generator but also propulsion auxiliary equipment and cargo-handling equipment both requiring a large capacity of electric power, comprising:

an electric power-receiving switchboard receiving the electric power from shore, the electric power-receiving switchboard including circuit breakers being respectively connected to divided first and second lines for turning on and off the electric power from shore to the first and second lines;

a first switchboard operable to change over from the first line to a power line for the propulsion auxiliary equipment by using a first changeover switch;

a second switchboard operable to change over from the second line to a power line for the cargo-handling equipment by using a second changeover switch; and

switching devices including a first circuit breaker and a second circuit breaker, the first circuit breaker closing after synchronization of the electric power from the generator and the electric power from shore transmitted via the power line for the propulsion auxiliary equipment, the second circuit breaker opening to shut off the electric power from the generator to the ordinary load via a main bus bar after temporary parallel operation of the electric power from shore and the electric power from the generator.

4. A system for supplying electric power from shore to a ship according to claim 3 , wherein the switching devices are provided in an onboard main switchboard or in a switchboard located adjacent to the main switchboard.

Assignments (2)
CHANGE OF NAME Recorded Nov 17, 2011
From: JAPAN RADIO & ELECTRIC MFG. CO., LTD.
To: JRCS MFG. CO., LTD.
Reel/Frame 027244/0884 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Feb 15, 2005
From: FUJITA, MASUMI
To: JAPAN RADIO & ELECTRIC MFG. CO., LTD.
Reel/Frame 016289/0458 →
Priority Claims (1)
JP 2004-045126 · Feb 20, 2004 · national
Continuity (1)
Related Publication 20050184589A1 · Aug 25, 2005