IP Library Granted Patent US 8,061,037
Granted Patent B2
US 8,061,037 · App. 11/611,445 · Granted Nov 22, 2011

Method for forming monitored concrete pilings using a pour diverter

Assignee: Smart Structures, Inc.
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,061,037
App. No.
11/611,445
Granted
Nov 22, 2011
Kind
B2
Abstract

A method for casting monitored pilings and a pour diverter used in connection with the method is provided. The method includes positioning a plurality of pile strands in a form, and then connecting a suspension assembly having at least one sensor to at least one of the pile strands so that the at least one sensor is located in a piling core area. A pour diverter, having a generally V-shaped configuration, is positioned over the suspension assembly. Concrete is poured into the form over the pour diverter so that a flow of the concrete into the form is split and flows down on either side of the suspension assembly until the at least one sensor is covered. The pour diverter is then removed to finish the casting. Preferably, provisions are provided on the pour diverter for holding or covering an antenna assembly during the pour, prior to it being placed into the concrete forming the piling.

Claims (27)

1. A method for casting a piling comprising:

positioning a plurality of pile strands in a form;

connecting a suspension assembly having a sensor that is at least one of an accelerometer or a strain gauge to at least one of the pile strands so that the at least one sensor is located in a piling core area;

positioning a pour diverter over the suspension assembly;

pouring concrete over the pour diverter, which shields the suspension assembly from a direct flow of the concrete, and into the form; and

removing the pour diverter.

2. The method of claim 1 , wherein the pour diverter splits a flow of the concrete over the suspension assembly so that the concrete fills the form with the concrete on both sides of the suspension assembly until the concrete covers the at least one sensor.

3. The method of claim 1 , further comprising completely filling the form with the concrete after removing the pour diverter.

4. The method of claim 1 , further comprising, moving the pour diverter along the piling form using a trolley assembly.

5. The method of claim 1 , wherein the pour diverter includes:

two diverter sides arranged in a generally V-shaped configuration;

a handle portion formed at a position where the two sides join one another; and

two opposing ends located between the sides, the ends including slots for receiving a portion of a antenna/radio assembly.

6. The method of claim 5 , wherein the diverter is formed by two identical formed metal parts that are welded to one another.

7. The method of claim 5 , wherein the pour diverter defines a hollow cavity thereunder.

8. The method of claim 5 , wherein the handle portion is formed by a slot in a top portion of the two diverter sides.

9. A method for casting a piling comprising:

positioning a plurality of pile strands in a form;

connecting a suspension assembly having a sensor that is at least one of an accelerometer or a strain gauge to at least one of the pile strands so that the at least one sensor is located in a piling core area;

positioning a pour diverter over the suspension assembly;

connecting an antenna assembly to the one or more sensors;

connecting the antenna assembly to or covering the antenna assembly with the pour diverter above a level of the concrete to be poured;

pouring concrete into the form;

removing the pour diverter; and

after the concrete is poured and the diverter is removed, positioning the antenna assembly in the form so that the antenna assembly is generally flush with a surface of the piling.

10. The method of claim 9 , further comprising shielding at least one of wires, cables or connectors under the pour diverter.

11. The method of claim 9 , further comprising coating an outside of the antenna assembly that is placed in the concrete with an epoxy coating.

Assignments (2)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Feb 11, 2016
From: SMART STRUCTURES, INC.
To: SMART INFRASTRUCTURE, LLC
Reel/Frame 037714/0454 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Feb 27, 2007
From: HECHT, KURT
To: SMART STRUCTURES, INC.
Reel/Frame 018938/0066 →