IP Library Granted Patent US 8,820,677
Granted Patent B2
US 8,820,677 · App. 13/163,680 · Granted Sep 2, 2014

Aircraft power systems and methods

Inventors: Kaushik Rajashekara (Carmel, IN); George A. Pontones (Indianapolis, IN)
B64D41/00H01M2250/20H02J1/10B64D2041/005Y02T90/36B64D2221/00H02J9/066H02J3/387Y02T50/54Y02T90/32
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,820,677
App. No.
13/163,680
Granted
Sep 2, 2014
Kind
B2
Abstract

One embodiment of the present application is directed to a unique method for powering one or more critical loads in an aircraft. Another embodiment is a unique apparatus for powering one or more critical loads upon failure of one or more engines. Other embodiments include unique methods, systems, devices, and apparatus' for powering power loads in an aircraft. Further embodiments, forms, features, aspects, benefits, and advantages of the present application shall become apparent from the description and figures provided herewith.

Claims (32)

1. A method, comprising:

monitoring an operating condition of an engine of an aircraft;

starting an emergency power generator when the operating condition indicates a failure of the engine to provide sufficient power for critical loads; and

powering only the critical loads in the aircraft using power from a fuel cell and the emergency power generator, wherein the critical loads are loads that are critical to flight safety and loads that are critical to passenger health;

wherein powering only the critical loads comprises:

converting a first AC power from the emergency power generator to a first DC power at a predefined voltage with a first rectifier;

converting a second DC power from the fuel cell to a third DC power at the predefined voltage with a first DC-DC converter;

transferring the first DC power from the emergency power generator and the third DC power from the fuel cell through a DC bus;

transferring a portion of the DC power from the DC bus to a second DC-DC converter;

delivering a fourth DC power from the second DC-DC converter to a critical DC load;

transferring a portion of the DC power from the DC bus to a DC-AC inverter; and

delivering a second AC power from the DC-AC inverter to a critical AC load.

2. The method of claim 1 , further comprising:

maintaining the fuel cell in a standby mode during non-emergency aircraft operations;

powering the critical loads with the fuel cell until a power output of the emergency power generator is sufficient to power the critical loads; and

powering at least some of the critical loads with the emergency power generator once the power output of the emergency power generator is sufficient to power the critical loads.

3. The method of claim 2 , further comprising:

powering the critical loads using power from only the emergency power generator once the power output of the emergency power generator is sufficient to power the critical loads.

4. The method of claim 2 , further comprising:

powering other aircraft electrical loads using power from the fuel cell while the emergency power generator powers the critical loads.

5. The method of claim 1 , further comprising:

powering the critical loads with the fuel cell and with the emergency power generator until a power output of the emergency power generator is sufficient to power the critical loads alone.

6. The method of claim 1 , further comprising powering at least one critical load using the fuel cell while the aircraft is operating in a normal condition.

7. The method of claim 1 , further comprising:

powering only the critical loads with the fuel cell until the emergency power generator is capable of powering the critical loads, then powering other loads with the fuel cell.

8. The method of claim 1 , wherein the aircraft includes more than one engine and the operating condition indicates a failure of all of the engines.

9. The method of claim 1 , wherein the aircraft includes more than one engine and the operating condition indicates a failure of one of the engines.

10. The method of claim 1 , further comprising:

powering the critical loads with the emergency power generator, the fuel cell, and a battery.

11. The method of claim 1 , wherein the starting of the emergency power generator includes deploying at least one of a ram air turbine and an air driven generator.

12. The method of claim 1 , further comprising storing excess energy from at least one of the fuel cell and the emergency power generator energy in a storage device when the power output of the fuel cell and emergency power generator exceed the power required to meet the critical loads.

13. The method of claim 1 , wherein the critical loads are one or more of flight control systems, flight control surface positioning systems, communication, navigation and hazard detection/avoidance systems, other avionic systems, landing gear systems and environmental control systems.

Assignments (1)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Aug 5, 2011
From: RAJASHEKARA, KAUSHIK; PONTONES, GEORGE
To: ROLLS-ROYCE CORPORATION
Reel/Frame 026705/0748 →
Continuity (1)
Related Publication 20120318914A1 · Dec 20, 2012