Monitoring system for concrete pilings and method of installation

Inventors: Kurt Hecht (Buckingham, PA); Richard Hecht (Tewksbury, MA)
Assignee: Smart Structures, Inc.
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,596,136
App. No.
13/346,233
Granted
Dec 3, 2013
Kind
B2
Abstract

A system for tracking and monitoring data related to the manufacture, installation and/or life cycle of concrete structures, such as pilings, as well as related system components and methods for tracking, storing and accessing such data is provided. The system utilizes an embeddable antenna assembly as well as a sensor package that are installed in the concrete structure form before casting. The antenna provides wireless communication of the data from the structure. On board memory is also provided to store structure related data with the structure. A system for tracking a pile during driving is also provided, and life cycle monitoring is also provided.

Claims (33)

1. A monitored piling adapted for connection to a networked monitoring node, comprising:

a plurality of reinforcements located in cast concrete;

a sensor package located in the concrete near a tip of the piling;

a transmitter near a top of the piling, the sensor package being connected to the transmitter via a wire or cable;

a tube extending at least partially between the sensor package and the transmitter near the top of the piling, the tube having an excess wire or cable reservoir, and the wire or cable extending through the tube;

an excess of the wire or cable in the reservoir that is adapted to be drawn up from the reservoir upon cutting off the top of the piling which includes the transmitter and cutting through the tube and the wire or cable; and

the excess of the wire or cable being adapted to be drawn from the reservoir to allow an external connection to the sensor.

2. The monitored piling of claim 1 , further comprising conditioning electronics associated with the sensor package located at the piling tip that store sensor details and calibration information for the sensor package.

3. The monitored piling of claim 1 , further comprising:

a monitoring node adapted to automatically identify a plurality of gauges with uniquely identified gauge types.

4. The monitored piling of claim 3 , further comprising:

the monitoring node being adapted to self configure based on the gauges identified.

5. A monitoring system for the monitored piling of claim 4 , further comprising:

the monitoring nodes of a plurality of the monitored pilings being connected to a larger network or network gateway that collects data from the gauges.

6. The monitoring system of claim 5 , further comprising additional concrete structures with encapsulated sensors that are connected with additional network nodes.

7. The monitoring system of claim 6 , wherein the larger network or network gateway is self-configuring for all of the connected monitored piling nodes in the pilings and the additional concrete structures.

8. The monitoring system of claim 7 , further comprising a remote central repository for data from the sensors.

9. A structure or foundation including a monitoring system, comprising:

a monitored piling having a plurality of reinforcements located in cast concrete, a sensor package located in the concrete near a tip of the piling, a transmitter near a top of the piling, the sensor package being connected to the transmitter via a wire or cable, a tube extending near the top of the piling and holding an excess of wire or cable that extends through the tube, the excess of the wire or cable is adapted to be drawn from the tube upon cutting off the top of the piling which includes the transmitter and cutting through the tube and the wire or cable, and the excess of the wire or cable being adapted to be drawn out to allow an external connection to the sensor;

a networked monitoring node located in a capping structure or located in proximity to the piling connected to the wire or cable; and

a network that provides power and a connection for data transfer.

10. The structure or foundation including the monitoring system of claim 9 , further comprising additional concrete structures with encapsulated sensors that are connected with additional network nodes.

11. The structure or foundation including the monitoring system of claim 9 , wherein the nodes are interfaced using a network protocol.

12. The structure or foundation including the monitoring system of claim 11 , the nodes are arranged in a peer-to-peer configuration.

13. The structure or foundation including the monitoring system of claim 9 , further comprising a remote data storage repository configured to store all uploaded telemetry information from long term monitoring of the piling.

14. The structure or foundation including the monitoring system of claim 9 , further comprising sensors for monitoring additional structures located on the cap, nodes connected to the sensors, with the nodes having self-adapting network capabilities.

15. The structure or foundation including the monitoring system of claim 9 , further comprising a telemetry uplink adapted to provide data from a partially or completely integrated structure.

16. The structure or foundation including the monitoring system of claim 9 , wherein the nodes are interfaced using a network protocol.

17. A structure or foundation including a monitoring system, comprising:

a concrete structure having a plurality of reinforcements located in cast concrete, a sensor package located in the concrete structure, a transmitter connected to the concrete structure, the sensor package being connected to the transmitter via a wire or cable, a tube extending through at least a part of the concrete structure and holding an excess of wire or cable that extends through the tube, the excess of the wire or cable is adapted to be drawn from the tube upon cutting through the tube and the wire or cable, and the excess of the wire or cable being adapted to be drawn out to allow an external connection to the sensor;

a networked monitoring node located on or in proximity to the concrete structure that is connected to the wire or cable; and

a network that provides power and a connection for data transfer.

18. The structure or foundation including the monitoring system of claim 17 , further comprising additional concrete structures with encapsulated sensors that are connected with additional network nodes.

Assignments (3)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Feb 11, 2016
From: SMART STRUCTURES, INC.
To: SMART INFRASTRUCTURE, LLC
Reel/Frame 037714/0454 →
CORRECTIVE ASSIGNMENT TO CORRECT THE ASSIGNEE NAME PREVIOUSLY RECORDED ON REEL 027502 FRAME 0347. ASSIGNOR(S) HEREBY CONFIRMS THE ASSIGNMENT OF ENTIRE INTEREST. Recorded Jan 12, 2012
From: HECHT, KURT; HECHT, RICHARD
To: SMART STRUCTURES, INC.
Reel/Frame 027522/0541 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jan 9, 2012
From: HECHT, KURT; HECHT, RICHARD
To: SMART STRUCUTRES, INC.
Reel/Frame 027502/0347 →
Continuity (6)
Continuation 12637863 · Dec 15, 2009
Division 11188492 · Jul 25, 2005
Provisional Application 60685807 · May 31, 2005
Provisional Application 60642585 · Jan 10, 2005
Provisional Application 60590955 · Jul 23, 2004
Related Publication 20120107056A1 · May 3, 2012