IP Library Granted Patent US 8,931,249
Granted Patent B2
US 8,931,249 · App. 13/616,841 · Granted Jan 13, 2015

Spinning machine and method for interrupting yarn production on a spinning machine

Inventors: Adalbert Stephan (Beilngries, DE); Gernot Schäffler (Wäschenbeuren, DE); Evzen Pilar (Litomysl, CZ); Martin Novak (Usti nad Orlici, CZ); Vítezslav Kubes (Usti nad Orlici, CZ); Josef Ludvícek (Usti nad Orlici, CZ); Vladimir Krycner (Usti nad Orlici, CZ)
Assignee: Rieter Ingolstadt GmbH
D01H13/14
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,931,249
App. No.
13/616,841
Granted
Jan 13, 2015
Kind
B2
Abstract

A method interrupts yarn production on a spinning machine having at least one spinning point having an inlet for a fiber material and an outlet for the yarn made from the fiber material, and wherein the spinning machine comprises a delivery device for feeding the fiber material into the spinning point, a take-off device for drawing off the yarn out of the spinning point, a winding device for winding up the produced yarn, and a yarn monitoring unit for monitoring at least one yarn parameter. Yarn production is interrupted upon detecting a defined deviation of the monitored yarn parameter from a target value, upon changing bobbins at the winding device, and/or prior to switching off the spinning machine. The feed speeds of the delivery device, the take-off device, and the winding device are gradually reduced to a stop in order to interrupt the yarn production, wherein the reducing takes place such that the end of the produced yarn is located between the outlet of the spinning point and the winding device after the reducing is completed.

Claims (29)

1. A method for interrupting yarn production on a spinning machine, wherein the spinning machine includes:

a spinning point having an inlet for a fiber material and an outlet for yarn made from the fiber material;

a delivery device for feeding the fiber material to the spinning point;

a take-off device for drawing off the yarn out of the spinning point;

a winding device for winding up the produced yarn; and

a yarn monitoring unit of monitoring a yarn parameter,

the method comprising:

interrupting yarn production upon any one of detection of a defined deviation of the yarn parameter by the yarn monitoring unit from a target value, upon changing bobbins at the winding device, or prior to switching off the spinning machine;

for yarn interruption, gradually reducing the feed speeds of the delivery device, the take-off device, and the winding device to a stop, wherein the reduction of feed speeds is controlled so that an end of the produced yarn is located between the outlet of the spinning point and the winding device after the speed reduction is complete.

2. The method as in claim 1 , wherein the delivery device includes a delivery roller pair, and the take-off device includes a take-off roller pair.

3. The method as in claim 1 , wherein the end of the produced yarn is located between the outlet of the spinning point and the take-off device after the speed reduction is complete.

4. The method as in claim 1 , wherein the feed speeds are first reduced to defined levels at which yarn production is not possible in the spinning point, and thereafter the take-off device and the winding device are then run at their respective defined level speeds until the end of the produced yarn is located at a defined position between the outlet of the spinning point and the winding device.

5. The method as in claim 1 , wherein the feed speeds are reduced continuously to a stop.

6. The method as in claim 1 , wherein the yarn is fixed in position by a yarn storage device after the reduction of the feed speeds is complete.

7. The method as in claim 1 , wherein the yarn is fixed in position by the take-off device after the reduction of the feed speeds is complete.

8. The method as in claim 1 , wherein the end of the produced yarn is captured by a robot after interruption of yarn production, fed back to the spinning point, and connected to the fiber material during a piecing process.

9. The method as in claim 8 , wherein the end of the produced yarn is captured by the robot between the outlet of the spinning point and the winding device.

10. The method as in claim 8 , wherein the piecing process takes place outside of the spinning point between the delivery device and a drawing unit.

11. The method as in claim 8 , wherein a yarn segment produced during reduction of the feed speeds is removed prior to the piecing process.

12. The method as in claim 1 , wherein position of the end of the produced yarn is determined by a sensor.

13. The method as in claim 12 , wherein reduction of the feed speeds is controlled as a function of a signal from the sensor that determines the end of the produced yarn.

14. The method as in claim 1 , wherein reduction of the feed speeds is controlled as a function of a chemical or physical property of the fiber material.

15. A spinning machine, comprising:

a spinning point having an inlet for a fiber material and an outlet for yarn made from the fiber material;

a delivery device for feeding the fiber material to the spinning point;

a take-off device for drawing off the yarn out of the spinning point;

a winding device for winding up the produced yarn;

a yarn monitoring unit of monitoring a yarn parameter; and

wherein the spinning machine is configured for interruption of yarn production in accordance with the method of claim 1 .

Assignments (2)
MERGER Recorded Feb 5, 2025
From: RIETER INGOLSTADT GMBH
To: SPINDELFABRIK SUESSEN GMBH
Reel/Frame 070114/0612 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Nov 28, 2012
From: STEPHAN, ADALBERT; SCHAFFLER, GERNOT; PILAR, EVZEN; NOVAK, MARTIN; KUBES, VITEZSLAV; LUDVICEK, JOSEF; KRYCNER, VLADIMIR
To: RIETER INGOLSTADT GMBH
Reel/Frame 029364/0641 →
Priority Claims (1)
DE 10 2001 053 811 · Sep 21, 2011 · national
Continuity (1)
Related Publication 20130067878A1 · Mar 21, 2013