IP Library Granted Patent US 9,052,353
Granted Patent B2
US 9,052,353 · App. 14/055,598 · Granted Jun 9, 2015

Method for locating short circuit in an overhead power transmission line by unsynchronized measurements at both ends thereof

Inventors: Alexandr Nikandrovich Visyaschev (Irkutsk, RU); Eduard Ruslanovich Plenkov (Irkutsk, RU); Stepan Georgievich Tiguntsev (Irkutsk, RU)
Assignee: FEDERALNOYE GOSUDARSTVENNOYE BUDZHETNOYE OBRAZOVATELNOYE UCHREZHDENIE VYSSHEGO OBRAZOVANIYA “IRKUTSKI NATSIONALNY ISSLEDOVATELSKI TEHNICHESKI UNIVERSITET” (FGBOU VO “IRNITU”)
G01R31/085G01R31/088G01R15/26
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 9,052,353
App. No.
14/055,598
Granted
Jun 9, 2015
Kind
B2
Abstract

The claimed invention relates to the power industry and can be used for locating short circuits in power transmission lines by measuring the instantaneous current and voltage values when unsynchronized measurements are taken at both ends of the line. It is a technological object of the invention to improve the accuracy of damage location. The technical result of the invention is achieved by accurately synchronizing the current and voltage values measured at the ends of the line and unsynchronized in time on measurement. Synchronization is effected by aligning the oscillograms at both ends of the line with the short circuit start section.

Claims (56)

1. A method for locating a short circuit point in an overhead power transmission line by taking unsynchronized measurements at both ends thereof, said line having a length l, a real resistance R, and an inductive resistance X L and connecting two supply systems, said method comprising measuring the phase currents and voltages unsynchronized in time at both ends of the line during a short circuit; identifying the damaged phases; and determining the relative distance n to the short circuit point at the end of the line marked by ′ from the formula l′=n*l, where l′ represents when a short circuit occurs in the line; wherein the instantaneous values of phase currents (i′ A ,i′ B ,i′ C ) and (i″ A ,i″ B ,i″ C ) and voltages (u′ A ,u′ B ,u′ C ) and (u″ A ,u″ B ,i″ C ) are measured at both ends of the line (′ designates one end of the line and ″ marks the other end of the line) during a short circuit; oscillograms are constructed for currents and voltages; the oscillograms at both ends of the line are aligned in the short circuit start section; a section in the oscillograms of damaged phase current and voltage is chosen within the interval of two to ten periods from the start of the short circuit; the instantaneous values of currents i′ and i″ and voltages u′ and u″ are read off in the section and at neighboring points; time-specific current derivatives di′/dt and di″/dt are calculated; and the relative distance n to the short circuit point is determined from the formula:

n

=

(

u

-

u

)

+

R

·

i

+

X

L

·

i

t

R

·

(

i

+

i

)

+

X

L

·

(

i

t

+

i

t

)

,

wherein:

u′ and u″ are instantaneous voltage values obtained in the section of the damaged phase voltage oscillograms at one and the other ends of the line (V);

i′ and i″ are instantaneous current values obtained in the section of the damaged phase current oscillograms at one and the other ends of the line (A);

di′/dt and d″/dt are time-specific current derivatives (A/C); and

R and X L are the real and inductive phase resistances of the line (Ohms).

Assignments (2)
CHANGE OF NAME Recorded Apr 28, 2015
From: FEDERALNOYE GOSUDARSTVENNOYE BUDZHETNOYE OBRAZOVATELNOYE UCHREZHDENIE VYSSHEGO PROFESSIONALNOGO OBRAZOVANIYA "IRKUTSKI GOSUDARSTVENNY TEHNICHESKI UNIVERSITET" (FGBOU VPO "IRGTU")
To: FEDERALNOYE GOSUDARSTVENNOYE BUDZHETNOYE OBRAZOVATELNOYE UCHREZHDENIE VYSSHEGO OBRAZOVANIYA "IRKUTSKI NATSIONALNY ISSLEDOVATELSKI TEHNICHESKI UNIVERSITET" (FGBOU VO "IRNITU")
Reel/Frame 035523/0621 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Oct 16, 2013
From: VISYASCHEV, ALEXANDR NIKANDROVICH; PLENKOV, EDUARD RUSLANOVICH; TIGUNTSEV, STEPAN GEORGIEVICH
To: FEDERALNOYE GOSUDARSTVENNOYE BUDZHETNOYE OBRAZOVATELNOYE UCHREZHDENIE VYSSHEGO PROFESSIONALNOGO OBRAZOVANIYA "IRKUTSKI GOSUDARSTVENNY TEHNICHESKI UNIVERSITET" (FGBOU VPO "IRGTU")
Reel/Frame 031485/0109 →
Priority Claims (1)
RU 2012145289 · Oct 24, 2012 · national
Continuity (1)
Related Publication 20140111219A1 · Apr 24, 2014