Heat source system and control method thereof

Inventors: Minoru Matsuo (Tokyo, JP); Takeshi Fuchimoto (Tokyo, JP)
Assignee: MITSUBISHI HEAVY INDUSTRIES THERMAL SYSTEMS, LTD.
F25B49/022F25B13/00F25B25/005F25B30/02F25B49/00F25B2400/06F25B2500/05F25B2600/026F25B2600/0253F25B2700/21161F25B2700/21171Y02B30/741
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 10,697,680
App. No.
14/431,677
Granted
Jun 30, 2020
Kind
B2
Abstract

A heat source system that optimizes a load on compressors in multiple heat source machines with respective independent refrigeration cycles that are situated in series. This is accomplished by using an information acquisition unit that acquires measurement values of operation frequencies of compressors from the respective heat source machines, a load distribution change unit that changes a load distribution currently assigned to each of the heat source machines, and a temperature setting unit that sets the hot/chilled water outlet temperatures of respective heat source machines.

Claims (18)

1. A heat source system constituted by connecting multiple heat source machines with respective independent refrigeration cycles in series, comprising:

a processor configured to perform the functions of:

an information acquisition unit that acquires, from the heat source machines on which a load is equally distributed, values of any one of an operation frequency of a compressor, current consumption of the compressor, power consumption of the compressor and torque of the compressor, each of which relates to an operation state;

a load distribution change unit that calculates an average value of the values acquired by the information acquisition unit and changes a load distribution currently assigned equally to each of the heat source machines such that the operation state in each of the heat source machines approaches the average value; and

a temperature setting unit that sets a hot/chilled water outlet temperature of each of the heat source machines according to the changed load distribution.

2. The heat source system according to claim 1 , wherein

the information acquisition unit further acquires operation integration time of each of compressors in the heat source machines; and

the load distribution change unit sets weighting coefficients based on the operation integration time of each of the compressors and changes the load distribution of each of the heat source machines using the weighting coefficients.

3. The heat source system according to claim 1 , wherein the load distribution change unit

compares the average value with the values of the heat source machines acquired by the information acquisition unit; and

increases the currently assigned load distribution for the heat source machine whose value is smaller than the average value, and decreases the currently assigned load distribution for the heat source machine whose value is larger than the average value.

4. The heat source system according to claim 1 , further comprising a storage unit that when the load distribution is changed by the load distribution change unit, stores, as information about load distribution, load distribution information in which a one or more of the operating heat source machines, identification information on the heat source machines as operating targets and the changed load distribution of each of the heat source machines are associated with one another,

wherein, at activation or at a change in the number of the operating heat source machines, the temperature setting unit sets a hot/chilled water outlet temperature of each of the heat source machines as the operating targets, based on the load distribution information stored in the storage unit.

5. A control method of a heat source system constituted by connecting multiple heat source machines with respective independent refrigeration cycles in series, comprising the steps of:

acquiring, from the heat source machines on which a load is equally distributed, values of any one of an operation frequency of a compressor, current consumption of the compressor, power consumption of the compressor and torque of the compressor, each of which relates to an operation state;

calculating an average value of the values acquired;

changing a load distribution currently assigned equally to each of the heat source machines such that the operation state in each of the heat source machines approaches the average value; and

setting a hot/chilled water outlet temperature of each of the heat source machines according to the changed load distribution.

Assignments (2)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Aug 1, 2017
From: MITSUBISHI HEAVY INDUSTRIES, LTD.
To: MITSUBISHI HEAVY INDUSTRIES THERMAL SYSTEMS, LTD.
Reel/Frame 043152/0511 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jul 2, 2015
From: MATSUO, MINORU; FUCHIMOTO, TAKESHI
To: MITSUBISHI HEAVY INDUSTRIES, LTD.
Reel/Frame 035974/0188 →
Priority Claims (1)
JP 2012-214504 · Sep 27, 2012 · national
Continuity (1)
Related Publication 20150241100A1 · Aug 27, 2015