IP Library Granted Patent US 9,896,269
Granted Patent B2
US 9,896,269 · App. 14/702,518 · Granted Feb 20, 2018

Method of forming a subterranean gas storage vessel

Inventors: Brett Wade Williams (Tuttle, OK); Paul Joseph Jones (Houston, TX); Marcus Allen Duffy (El Reno, OK)
Assignee: Halliburton Energy Services, Inc.
B65G5/00E21B41/0057
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 9,896,269
App. No.
14/702,518
Granted
Feb 20, 2018
Kind
B2
Abstract

A method of forming a subterranean gas storage vessel is provided. A wellbore is drilled through the surface of the ground into the ground, and a casing is inserted into the wellbore, the casing having a size such that a wellbore annulus is formed between the outside surface of the casing and the wall of the wellbore. A cement sheath is then formed in the wellbore annulus, and the interior of the casing is sealed to help prevent gas from inadvertently escaping therefrom. The cemented and sealed casing can then be used as a storage vessel to store and dispense gas such as compressed natural gas (CNG).

Claims (42)

1. A method of forming a subterranean gas storage vessel, comprising:

drilling a wellbore through the surface of the ground into the ground, said wellbore having a wellbore wall;

inserting a casing into the wellbore, said casing having an interior, an outside surface, a top and a bottom end, said casing further having a size such that a wellbore annulus is formed between said outside surface of the casing and said wellbore wall when said casing is inserted into said wellbore;

pumping a settable cement composition into said interior of said casing;

pumping a settable resin composition into said interior of said casing before said settable cement composition has set, wherein said settable resin composition is pumped so as to displace said settable cement composition from said interior of said casing and into said wellbore annulus and wherein said pumping of said settable resin composition is stopped once said settable resin composition reaches a predetermined height within said casing;

allowing said settable cement composition to set so as to form a cement sheath in said wellbore annulus; and

allowing said settable resin composition to set so as to seal at least a portion of the interior of said casing to help prevent gas that is stored in said casing from inadvertently escaping from said casing.

2. The method of claim 1 , wherein said step of sealing at least a portion of the interior of said casing includes sealing said interior of said casing adjacent to said bottom end of said casing.

3. The method of claim 1 , wherein said settable cement composition includes a cement formulation and enough water to form a pumpable slurry, and said settable resin composition includes a resin formulation and enough water to form a pumpable slurry.

4. The method of claim 3 , wherein said cement formulation is selected from the group consisting of a conventional cement composition, a resin composition and a comingled cement-resin composition, and said resin formulation is selected from the group consisting of a resin composition and a comingled cement-resin composition.

5. The method of claim 4 , wherein said cement formulation is a conventional cement composition, and said resin formulation is a resin composition.

6. The method of claim 4 , wherein said cement formulation is a conventional cement composition, and said resin formulation is a comingled cement-resin composition.

7. The method of claim 4 , wherein both said cement formulation and said resin formulation are a resin composition.

8. The method of claim 4 , wherein both said cement formulation and said resin formulation are a comingled cement-resin composition.

9. The method of claim 4 , wherein said cement formulation includes a hydraulic cement.

10. The method of claim 4 , wherein said resin composition includes a hardenable epoxy resin and a hardening agent selected from the group consisting of amine based hardening agents and anhydride based hardening agents.

11. The method of claim 4 , wherein said comingled cement-resin composition includes a hydraulic cement, a hardenable epoxy resin and a hardening agent selected from the group consisting of amine based hardening agents and anhydride based hardening agents.

12. The method of claim 1 , wherein said casing has a diameter in the range of from 4.5 inches to 24.5 inches, and a wall thickness in the range of from 0.1 inches to 2 inches.

13. A method of forming a subterranean gas storage vessel and using the subterranean gas storage vessel to store compressed natural gas, comprising:

drilling a wellbore through the surface of the ground into the ground, said wellbore having a wellbore wall;

inserting a casing into the wellbore, said casing having an interior, an outside surface, a top and a bottom end, said casing further having a size such that a wellbore annulus is formed between said casing and said wellbore wall when said casing is inserted into said wellbore;

pumping a settable cement composition into said interior of said casing, forming a said settable cement composition including a cement formulation and enough water to form a pumpable slurry, said cement formulation being selected from the group consisting of a conventional cement composition, a resin composition and a comingled cement-resin composition;

pumping a settable resin composition into said interior of said casing before said settable cement composition has set, wherein said settable resin composition is pumped so as to displace said settable cement composition from said interior of said casing and into said wellbore annulus and wherein said pumping of said settable resin composition is stopped once said settable resin composition reaches a predetermined height within said casing;

allowing said settable cement composition to set so as to form a cement sheath in said wellbore annulus;

allowing said settable resin composition to set so as to seal at least a portion of the interior of said casing adjacent to said bottom end of said casing to help prevent gas that is stored in said casing from inadvertently escaping from said casing, said settable resin composition including a resin formulation and enough water to form a pumpable slurry, said resin formulation being selected from the group consisting of a resin composition and a comingled cement-resin composition;

injecting natural gas into said casing in a manner such that said natural gas is pressurized in said casing to a pressure of at least 100 psi; and

storing compressed natural gas in said casing.

14. The method of claim 13 , wherein said settable cement composition is a cement composition, and said settable resin composition is selected from the group consisting of a resin composition and a comingled cement-resin composition.

15. The method of claim 13 , wherein said settable cement composition is a cement composition, and said settable resin composition is a resin composition.

16. A method of forming a subterranean gas storage vessel and using the subterranean gas storage vessel to store compressed natural gas and dispense natural gas, comprising:

drilling a wellbore through the surface of the ground into the ground, said wellbore having a wellbore wall;

inserting a casing into the wellbore, said casing having an interior, an outside surface, a top and a bottom end, said casing further having a size such that a wellbore annulus is formed between said casing and said wellbore wall when said casing is inserted into said wellbore;

pumping a settable cement composition into said interior of said casing, said settable cement composition including a cement formulation and enough water to form a pumpable slurry, said cement formulation being selected from the group consisting of a conventional cement composition, a resin composition and a comingled cement-resin composition;

pumping a settable resin composition into said interior of said casing before said settable cement composition has set, wherein said settable resin composition is pumped so as to displace said settable cement composition from said interior of said casing and into said wellbore annulus and wherein said pumping of said settable resin composition is stopped once said settable resin composition reaches a predetermined height within said casing;

allowing said settable cement composition to set so as to form a cement sheath in said wellbore annulus;

allowing said settable resin composition to set so as to seal at least a portion of the interior of said casing adjacent to said bottom end of said casing to help prevent gas that is stored in said casing from inadvertently escaping from said casing, said settable resin composition including a resin formulation and enough water to form a pumpable slurry, said resin formulation being selected from the group consisting of a resin composition and a comingled cement-resin composition;

injecting natural gas into said casing in a manner such that said natural gas is pressurized in said casing to a pressure of at least 100 psi;

storing compressed natural gas in said casing; and

withdrawing natural gas from said casing as needed.

17. The method of claim 16 , wherein said settable cement composition is a cement composition, and said settable resin composition is selected from the group consisting of a resin composition and a comingled cement-resin composition.

18. The method of claim 16 wherein said settable cement composition comprises components and further comprising mixing the components of said settable cement composition and said settable resin composition using mixing equipment.

19. The method of claim 16 wherein said settable cement composition is placed in said wellbore annulus using one or more pumps.

Assignments (1)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded May 14, 2015
From: WILLIAMS, BRETT WADE; JONES, PAUL JOSEPH; DUFFY, MARCUS ALLEN
To: HALLIBURTON ENERGY SERVICES, INC.
Reel/Frame 035637/0592 →
Continuity (1)
Related Publication 20160318710A1 · Nov 3, 2016