IP Library Granted Patent US 10,209,006
Granted Patent B2
US 10,209,006 · App. 15/119,429 · Granted Feb 19, 2019

Fluidized calciner

Inventors: Junzhu Wang (Naka, JP); Yoshinori Takayama (Naka, JP)
Assignee: MITSUBISHI MATERIALS CORPORATION
F27B7/2033C04B7/45F27B7/38F27D17/004
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 10,209,006
App. No.
15/119,429
Granted
Feb 19, 2019
Kind
B2
Abstract

The present invention provides a fluidized calciner which can perform sufficient calcination by reducing a rate of unburned fuel at an outlet of the fluidized calciner while preventing occlusion in a preheater. In the present invention, plural pulverized coal blowing lines ( 3 ), raw material chute ( 4 ) of cement raw material, and first to fourth air introduction pipes ( 5 a to 5 d ) are connected to a bottom side wall of a tubular furnace body ( 2 ) whose upper end portion is closed by a top plate ( 2 b ); a fluidizing air blowing port ( 2 a ) adapted to blow in fluidizing air is disposed at a bottom of the furnace body ( 2 ); an exhaust gas duct ( 6 ) is connected to a top side wall of the furnace body located above the first and/or second air introduction pipes ( 5 a, 5 b ) by being spaced away from the top plate ( 2 b ); and blowing ports ( 3 a ) of the pulverized coal blowing lines are disposed below suction ports of respective air introduction pipes ( 5 a to 5 d ) but above the fluidizing air blowing port ( 2 a ), and at least one of the blowing ports ( 3 a ) is placed below the third or fourth air introduction pipe ( 5 c or 5 d ).

Claims (9)

1. A fluidized calciner, wherein:

a plurality of pulverized coal blowing lines adapted to blow fuel into a furnace body cylindrical in shape, a raw material chute adapted to load cement raw material into the furnace body, and first to fourth air introduction pipes placed sequentially at intervals and adapted to provide introduced air into the furnace body are connected to a bottom side wall of the furnace body whose axis direction corresponds to an up-down direction and whose upper end portion is closed by a top plate;

a fluidizing air blowing port adapted to blow fluidizing air into the furnace body is disposed at a bottom of the furnace body;

an exhaust duct adapted to cause combustion gas in the furnace body containing cement raw material to flow out is connected to a top side wall of the furnace body located above the first and/or second air introduction pipes by being spaced away from the top plate;

blowing ports of the pulverized coal blowing lines are disposed below suction ports of the respective air introduction pipes but above the fluidizing air blowing port; and

one of the blowing ports is placed below the third or fourth air introduction pipe.

2. The fluidized calciner according to claim 1 , wherein the blowing ports of the pulverized coal blowing lines are disposed at two locations.

3. The fluidized calciner according to claim 1 , wherein the raw material chute is placed next to the first air introduction pipe and the blowing ports are placed below the third air introduction pipe opposed to the first air introduction pipe in a radial direction.

4. The fluidized calciner according to claim 2 , wherein the raw material chute is placed next to the first air introduction pipe and the blowing ports are placed below the third air introduction pipe opposed to the first air introduction pipe in a radial direction.

Assignments (3)
COMPANY SPLIT Recorded Oct 7, 2022
From: MITSUBISHI MATERIALS CORPORATION
To: MITSUBISHI UBE CEMENT CORPORATION
Reel/Frame 061766/0082 →
CORPORATE ADDRESS CHANGE Recorded Feb 23, 2022
From: MITSUBISHI MATERIALS CORPORATION
To: MITSUBISHI MATERIALS CORPORATION
Reel/Frame 059219/0869 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Aug 17, 2016
From: WANG, JUNZHU; TAKAYAMA, YOSHINORI
To: MITSUBISHI MATERIALS CORPORATION
Reel/Frame 039463/0416 →
Priority Claims (1)
JP 2014-038119 · Feb 28, 2014 · national
Continuity (1)
Related Publication 20170219287A1 · Aug 3, 2017