Equipment tower having a concrete plinth

Inventors: James D. Lockwood (Boulder, CO); Matthew J. Chase (Windsor, CO); Luis E. Carbonell (Deltona, FL)
Assignees: SIEMENS GAMESA RENEWABLE ENERGY, INC.; WIND TOWER TECHNOLOGIES, LLC
E02D27/425F03D13/22Y02E10/728
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 11,072,903
App. No.
15/753,193
Granted
Jul 27, 2021
Kind
B2
Abstract

An equipment tower includes a foundation, a cast-in-place concrete plinth extending vertically from the foundation, and a tower portion extending vertically from the plinth. The equipment tower is constructed at a site having a set of tower specific parameters, and at least one dimension of the plinth is selected based on a tower specific parameter. For example, a height of the plinth may be selected to achieve a desired elevation of the topmost surface of the plinth, so that two towers having identical tower segments will have a common equipment height in spite of variations in their respective foundation elevations due to variations in local ground level. Moreover, the cast-in-place plinth may be designed to include a door opening large enough to accommodate equipment to be installed within the tower.

Claims (19)

1. A method for maintaining a target elevation of a plurality of wind turbines of a wind farm, the plurality of wind turbines comprising standardized wind turbine tower sections, the method comprising:

forming a first foundation for a first wind turbine at a first location of the wind farm;

casting a first plinth in place on the first foundation, wherein the first plinth has a height such that a standardized wind turbine tower section erected on the first plinth reaches the target elevation;

erecting the standardized wind turbine tower section on the first plinth;

forming a second foundation for a second wind turbine at a second location of the wind farm;

determining a difference between a local ground elevation at the first location and the second location;

calculating a height of a second plinth that is responsive to the difference in the local ground elevation such that a standardized wind turbine tower section erected on the second plinth reaches the target elevation;

casting the second plinth in place on the second foundation according to the calculated height; and

erecting the standardized wind turbine tower section on the second plinth.

2. The method of claim 1 , wherein the height of the second plinth is increased from a height of the first plinth based on a decrease in the local ground elevation measured between the second foundation and the first foundation.

3. The method of claim 1 , wherein the height of the second plinth is decreased from a height of the first plinth based on an increase in the local ground elevation measured between the second foundation and the first foundation.

4. The method of claim 1 , further comprising:

casting an opening within the first plinth, the opening sized to accommodate equipment scheduled for installation in the first wind turbine; and

casting an opening within the second plinth, the opening sized to accommodate equipment scheduled for installation in the second wind turbine tower.

5. The method of claim 1 , wherein the opening within the first plinth and the opening within the second plinth is a door.

6. The method of claim 5 , wherein a wall thickness of the first plinth and a wall thickness of the second plinth is selected to accommodate a door opening.

7. The method of claim 1 , further comprising:

installing equipment in the first wind turbine and the second wind turbine tower through the respective opening in the first plinth and the second plinth.

8. The method of claim 1 , wherein the first plinth is integrally casted with the first foundation and the second plinth is integrally casted with the second foundation.

Assignments (5)
CHANGE OF NAME Recorded May 2, 2018
From: SIEMENS WIND POWER, INC.
To: SIEMENS GAMESA RENEWABLE ENERGY, INC.
Reel/Frame 046065/0628 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Apr 26, 2018
From: LOCKWOOD, JAMES D.
To: WIND TOWER TECHNOLOGIES, LLC.
Reel/Frame 045646/0424 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Apr 26, 2018
From: SIEMENS ENERGY, INC.
To: SIEMENS WIND POWER, INC.
Reel/Frame 045646/0894 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Feb 16, 2018
From: CHASE, MATTHEW J.
To: WIND TOWER TECHNOLOGIES, LLC.
Reel/Frame 044952/0089 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Feb 16, 2018
From: CARBONELL, LUIS E.
To: SIEMENS ENERGY, INC.
Reel/Frame 044952/0224 →
Continuity (3)
Provisional Application 62211991 · Aug 31, 2015
Provisional Application 62211998 · Aug 31, 2015
Related Publication 20190010673A1 · Jan 10, 2019