IP Library › Granted Patent US 10,425,280
Granted Patent B2
US 10,425,280 · App. 15/785,793 · Granted Sep 24, 2019

Method for determining optimal laying arrangement of infrastructure link

Inventors: Moshe Zukerman (Kowloon, HK); Zengfu Wang (Shaanxi, CN); Qing Wang (Kowloon, HK); Yu Wang (Kowloon, HK); Gang Wang (Kowloon, HK); William Moran (Balwyn, AU); Felipe Cucker (Kowloon, HK); Jun Guo (Guangdong, CN); Elias Tahchi (Quarry Bay, HK)
Assignee: City University of Hong Kong
H04L41/0836G06Q10/06313G06Q50/08H04L41/0826H04L41/145H04L45/124
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 10,425,280
App. No.
15/785,793
Granted
Sep 24, 2019
Kind
B2
Abstract

A method for determining an optimal laying arrangement of a new infrastructure link for connection from a new site to an existing infrastructure network includes modeling a terrain of a region around and at the new site and the existing infrastructure network near the new site; modeling each factor affecting the laying arrangement as a respective cost function; applying a respective weighting to each of the cost function to determine a life-cycle cost function; and determining, based on the determined life-cycle cost function, an optimized laying arrangement with minimal life-cycle cost from the new site to a connection point in the existing infrastructure network.

Claims (130)

1. A method for determining an optimal laying arrangement of a new infrastructure link for connection from a new site to an existing infrastructure network, comprising:

modeling a terrain of a region around and at the new site and the existing infrastructure network near the new site;

modeling each factor affecting the laying arrangement as a respective cost function;

applying a respective weighting to each of the cost function to determine a life-cycle cost function; and

determining, based on the determined life-cycle cost function, an optimized laying arrangement with minimal life-cycle cost from the new site to a connection point in the existing infrastructure network, wherein the determination of the optimized laying arrangement comprises solving the following optimization equation:

min

γ

⁢

⁢

(

γ

)

=

min

γ

⁢

∫

0

l

⁡

(

γ

)

⁢

h

⁡

(

X

⁡

(

s

)

)

⁢

ds

such that γ(A)=X A ; and γ(B)=X B ;

where H(γ) is a total life-cycle cost for an infrastructure link, A and B denote two end points of the new infrastructure link, with B being an existing infrastructure link γ i , i=1, 2, . . . , n, given γ 1 , γ 2 , . . . , γ n .

2. The method of claim 1 , wherein the modeling of the terrain comprises modeling the terrain as a closed 2D triangulated manifold.

3. The method of claim 1 , wherein the new infrastructure link comprises a new cable and the existing infrastructure network comprises an existing cable network.

4. The method of claim 3 , wherein the connection point is a branching unit of an existing cable or a cable landing station of the existing cable network.

5. The method of claim 3 , wherein the new cable comprises a telecommunication cable and the existing cable network comprises an existing telecommunication cable network.

6. The method of claim 3 , wherein the new cable comprises a submarine cable and the existing cable network comprises a submarine cable network.

7. The method of claim 1 , wherein the plurality of factor includes environmental factors and human factors.

8. The method of claim 1 , wherein the optimized laying arrangement comprises the optimized laying route.

9. The method of claim 1 , further comprising displaying the optimized laying arrangement on a model of the terrain.

10. The method of claim 1 , further comprising:

transforming the optimization equation using Eikonal equation; and

applying fast marching method to solve the transformed equation for determination of the optimized laying arrangement.

11. A non-transitory computer readable medium for storing computer instructions that, when executed by one or more processors, causes the one or more processors to perform a method for determining an optimal laying arrangement of a new infrastructure link for connection from a new site to an existing infrastructure network, comprising:

modeling a terrain of a region around and at the new site and the existing infrastructure network near the new site;

modeling each factor affecting the laying arrangement as a respective cost function;

applying a respective weighting to each of the cost function to determine a life-cycle cost function; and

determining, based on the determined life-cycle cost function, an optimized laying arrangement with minimal life-cycle cost from the new site to a connection point in the existing infrastructure network, wherein the determination of the optimized laying arrangement comprises solving the following optimization equation:

min

γ

⁢

⁢

(

γ

)

=

min

γ

⁢

∫

0

l

⁡

(

γ

)

⁢

h

⁡

(

X

⁡

(

s

)

)

⁢

ds

such that γ(A)=X A ; and γ(B)=X B ;

where H(γ) is a total life-cycle cost for an infrastructure link, A and B denote two end points of the new infrastructure link, with B being an existing infrastructure link γ i =1, 2, . . . , n, given γ 1 , γ 2 , . . . , γ n .

12. The non-transitory computer readable medium of claim 11 , wherein the modeling of the terrain comprises modeling the terrain as a closed 2D triangulated manifold.

13. The non-transitory computer readable medium of claim 11 , wherein the new infrastructure link comprises a new cable and the existing infrastructure network comprises an existing cable network.

14. The non-transitory computer readable medium of claim 13 , wherein the connection point is a branching unit of an existing cable or a cable landing station of the existing cable network.

15. The non-transitory computer readable medium of claim 13 , wherein the new cable comprises a telecommunication cable and the existing cable network comprises an existing telecommunication cable network.

16. The non-transitory computer readable medium of claim 13 , wherein the new cable comprises a submarine cable and the existing cable network comprises a submarine cable network.

17. The non-transitory computer readable medium of claim 11 , wherein the plurality of factor includes environmental factors and human factors.

18. The non-transitory computer readable medium of claim 11 , wherein the optimized laying arrangement comprises the optimized laying route.

19. A system for determining an optimal laying arrangement of a new infrastructure link for connection from a new site to an existing infrastructure network, the system comprising one or more processors configured to:

model a terrain of a region around and at the new site and the existing infrastructure network near the new site;

model each factor affecting the laying arrangement as a respective cost function;

apply a respective weighting to each of the cost function to determine a life-cycle cost function; and

determine, based on the determined life-cycle cost function, an optimized laying arrangement with minimal life-cycle cost from the new site to a connection point in the existing infrastructure network;

wherein the determination of the optimized laying arrangement comprises solving the following optimization equation:

min

γ

⁢

⁢

(

γ

)

=

min

γ

⁢

∫

0

l

⁡

(

γ

)

⁢

h

⁡

(

X

⁡

(

s

)

)

⁢

ds

such that γ(A)=X A ; and γ(B)=X B ;

where is a total life-cycle cost for an infrastructure link, A and B denote two end points of the new infrastructure link, with B being an existing infrastructure link γ i , i=1, 2, . . . , n, given γ 1 , γ 2 , . . . , γ n .

Assignments (1)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Mar 26, 2018
From: ZUKERMAN, MOSHE; WANG, QING; WANG, YU; CUCKER, FELIPE; WANG, ZENGFU; WANG, GANG; MORAN, WILLIAM; GUO, JUN; TAHCHI, ELIAS
To: CITY UNIVERSITY OF HONG KONG
Reel/Frame 045350/0585 →
Continuity (1)
Related Publication 20190116090A1 · Apr 18, 2019
Cited By (2)
US 12,250,123 US 12,587,465