IP Library › Granted Patent US 11,028,832
Granted Patent B2
US 11,028,832 · App. 16/306,364 · Granted Jun 8, 2021

Floating wind turbine having a plurality of energy conversion units

Inventor: Sonke Siegfriedsen (Rendsburg, DE)
Assignee: Aerodyn Consulting Singapore PTE LTD
F03D13/25F03D1/02B63B2035/446F05B2240/2213F05B2240/93Y02E10/727
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 11,028,832
App. No.
16/306,364
Granted
Jun 8, 2021
Kind
B2
Abstract

The invention relates to a wind turbine comprising a floating base designed as a semi-submersible, a tower arranged on the floating base, at least two arms extending from the tower, a respective energy conversion unit arranged at the free end of each arm, and a cable system connecting the base to the energy conversion units and connecting the energy conversion units to one another in order to introduce the thrust forces acting on the tower, the arms and the energy conversion units into the base, wherein the cable system has a pre-tensioning, the value of which is greater than the loads to be expected during the operation of the wind turbine and acting against the pre-tensioning.

Claims (30)

1. A wind power plant having;

a floating foundation designed to be half-submerged, wherein the floating foundation is designed as a Y-shaped platform having a long arm and two short arms, each short arm being shorter than the long arm,

a tower arranged on the floating foundation, wherein the tower is arranged at a connection point of the arms and the long arm extends from the connection point to a free end of the long arm and the two short arms extend from the connection point to a respective free end of each short arm,

at least two cantilevers extending from the tower to a free end of each cantilever,

power converter units, wherein each power convertor unit is arranged on the free end of each cantilever, and

a cable system including at least two supports connecting the foundation to each of the power convertor units and at least one support connecting the power convertor units to each other for introducing the thrust acting upon the tower, the cantilevers and the power convertor units into the foundation, wherein the cable system has a pretensioning and each power convertor unit is arranged above the respective free end of each short arm.

2. The wind power plant according to claim 1 , wherein a force vector resulting from the pretensioning of the cable system during use of the wind power plant is located in the axis of one of the cantilevers.

3. The wind power plant according to claim 1 , wherein the wind power plant is designed having downwind turbines and the tower is inclined leeward.

4. The wind power plant according to claim 1 , wherein the cable system is connected by a flexible joint to the free end of the long arm and/or at free ends of the short arms.

5. The wind power plant according to claim 1 , wherein the cable system is connected by a flexible joint to the free end of the long arm and the power convertor units are connected via supports to free ends of the short arms.

6. The wind power plant according to claim 1 , wherein the floating foundation has a floater connected to each free end of the arms.

7. The wind power plant according to claim 6 , wherein the longitudinal axis of each floater is aligned in at least one plane with a power convertor unit.

8. The wind power plant according to claim 1 , comprising two power convertor units, each having a rotor having at least one rotor blade, wherein the directions of rotation of the two rotors are in opposite directions.

9. The wind power plant according to claim 1 , comprising two power convertor units, each having a rotor with at least one rotor blade, wherein the rotor blades are regulated during operation in a phase-shifted manner with respect to each other.

10. The wind power plant according to claim 1 , comprising two power convertor units, each having a rotor with at least one rotor blade, wherein the rotor blades in the farm position are aligned identically.

11. A wind power plant having;

a floating foundation designed to be half-submerged, wherein the floating foundation is designed as a Y-shaped platform having a long arm and two short arms, each short arm being shorter than the long arm,

a tower arranged on the floating foundation, wherein the tower is arranged at a connection point of the arms and the long arm extends from the connection point to a free end of the long arm and the two short arms extend from the connection point to a respective free end of each short arm,

at least two cantilevers extending from the tower to a free end of each cantilever,

power converter units, wherein each power convertor unit is arranged on the free end of each cantilever, and

a cable system including at least two guys connecting the foundation to each of the power convertor units and at least one guy connecting the power convertor units to each other for introducing the thrust acting upon the tower, the cantilevers and the power convertor units into the foundation, wherein the cable system has a pretensioning and at least one power convertor unit is arranged above the respective free end of each short arm.

12. The wind power plant according to claim 11 , wherein a force vector resulting from the pretensioning of the cable system during use of the wind power plant is located in the axis of one of the cantilevers.

13. A wind power plant having;

a floating foundation designed to be half-submerged, wherein the floating foundation is designed as a Y-shaped platform having a long arm and two short arms, each short arm being shorter than the long arm,

a tower arranged on the floating foundation, wherein the tower is arranged at a connection point of the arms and the long arm extends from the connection point to a free end of the long arm and the two short arms extend from the connection point to a respective free end of each short arm,

at least two cantilevers extending from the tower to a free end of each cantilever,

power converter units, wherein each power convertor unit is arranged on the free end of each cantilever, and

a cable system connecting the foundation to each of the power convertor units for introducing the thrust acting upon the tower, the cantilevers and the power convertor units into the foundation, wherein the cable system has at least three supports connected to each power converter unit, and at least one power convertor unit is arranged above the respective free end of each short arm.

14. The wind power plant according to claim 13 , wherein a force vector resulting from the pretensioning of the cable system during use of the wind power plant is located in the axis of one of the cantilevers.

15. The wind power plant according to claim 13 , wherein at least one of the supports is a guy.

Assignments (2)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Dec 12, 2018
From: SIEGFRIEDSEN, SONKE
To: AERODYN ENGINEERING GMBH
Reel/Frame 047755/0531 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Dec 12, 2018
From: AERODYN ENGINEERING GMBH
To: AERODYN CONSULTING SINGAPORE PTE LTD
Reel/Frame 047755/0863 →
Priority Claims (1)
DE 10 2016 110 290.3 · Jun 3, 2016 · national
Continuity (1)
Related Publication 20190211804A1 · Jul 11, 2019