IP Library Granted Patent US 10,742,019
Granted Patent B2
US 10,742,019 · App. 16/349,275 · Granted Aug 11, 2020

Monitoring tap changer switching

Inventor: Bengt-Olof Stenestam (Ludvika, SE)
Assignee: ABB Power Grids Switzerland AG
H02H7/055G01R31/62H01F29/02H01F29/04H01H9/0005H02H1/0007H01H2009/0061
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 10,742,019
App. No.
16/349,275
Granted
Aug 11, 2020
Kind
B2
Abstract

The present disclosure relates to a method of monitoring switching by an on-load tap changer (OLTC) 1 from a first contact 3 a to a second contact 3 b of a transformer winding 2 . The method includes measuring a voltage of the transformer. The method also includes measuring a temperature of the OLTC. The method also includes, based on the measured voltage and temperature, determining whether the switching from the first contact to the second contact has been successful.

Claims (35)

1. A method of monitoring switching by an on-load tap changer, OLTC, from a first contact to a second contact of a transformer winding during a switching time period, the method comprising:

measuring (M 1 ) a phase voltage of the transformer over time;

measuring (M 2 ) a temperature of the OLTC over time;

based on the measured voltage and temperature, determining (M 3 ) that the switching from the first contact to the second contact has not been successful;

wherein the determining (M 3 ) includes determining that the measured voltage has changed during the switching time period and that the change is above a predetermined threshold; and

wherein the determining (M 3 ) includes determining that the measured temperature continues to rise after the end of the switching time period.

2. The method of claim 1 , wherein the determining (M 3 ) includes determining that a quotient between the measured phase voltage and a measured current of the same phase has changed during the switching time period and that the change is above a predetermined threshold.

3. The method of claim 1 , wherein the method further includes tripping the transformer.

4. The method of claim 1 , wherein the measuring (M 1 ) of a voltage includes measuring a voltage at a bushing of the transformer.

5. The method of claim 1 , wherein the measuring (M 2 ) of a temperature includes measuring a temperature of insulation liquid, e.g., oil, in the OLTC by means of a temperature sensor located therein.

6. The method of claim 1 , wherein the measuring (M 1 ) of a voltage includes measuring a voltage for each phase of a three-phase transformer.

7. The method of claim 1 , wherein the OLTC includes a circuit breaker e.g., having a Vacuum Interrupter, VI.

8. The method of claim 1 , wherein the transformer has a voltage rating of at least 1 kV rms .

9. A computer program product comprising computer-executable components for causing a controller to perform a method of monitoring switching by an on-load tap changer, OLTC, from a first contact to a second contact of a transformer winding during a switching time period, the method including the steps of:

a method

measuring (M 1 ) a phase voltage of the transformer over time;

measuring (M 2 ) a temperature of the OLTC over time;

based on the measured voltage and temperature, determining (M 3 ) that the switching from the first contact to the second contact has not been successful;

wherein the determining (M 3 ) includes determining that the measured voltage has changed during the switching time period and that the change is above a predetermined threshold; and

wherein the determining (M 3 ) includes determining that the measured temperature continues to rise after the end of the switching time period.

10. A controller for monitoring switching by an online tap changer, OLTC, from a first contact to a second contact of a transformer winding during a switching time period, the controller comprising:

processing circuitry; and

storage storing instructions executable by said processing circuitry whereby said controller is operative to:

measure a phase voltage of a transformer over time;

measure a temperature of an OLTC of the transformer over time;

based on the measured voltage and temperature, determine that switching from a first contact to a second contact of a winding of the transformer has not been successful;

wherein the determining includes determining that the measured voltage has changed during the switching time period and that the change is above a predetermined threshold; and

wherein the determining includes determining that the measured temperature continues to rise after the end of the switching time period.

11. The method of claim 2 , wherein the method further includes tripping the transformer.

12. The method of claim 2 , wherein the measuring (M 1 ) of a voltage includes measuring a voltage at a bushing of the transformer.

13. The method of claim 2 , wherein the measuring (M 2 ) of a temperature includes measuring a temperature of insulation liquid, e.g., oil, in the OLTC by means of a temperature sensor located therein.

14. The method of claim 2 , wherein the measuring (M 1 ) of a voltage includes measuring a voltage for each phase of a three-phase transformer.

15. The method of claim 2 , wherein the OLTC includes a circuit breaker, e.g., having a Vacuum Interrupter, VI.

16. The method of claim 2 , wherein the transformer has a voltage rating of at least 1 kV rms .

17. The computer program product of claim 9 , including a processing circuit in the controller.

Assignments (5)
MERGER Recorded Nov 13, 2023
From: HITACHI ENERGY SWITZERLAND AG
To: HITACHI ENERGY LTD
Reel/Frame 065549/0576 →
CHANGE OF NAME Recorded Dec 31, 2021
From: ABB POWER GRIDS SWITZERLAND AG
To: HITACHI ENERGY SWITZERLAND AG
Reel/Frame 058666/0540 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jun 11, 2020
From: ABB SCHWEIZ AG
To: ABB POWER GRIDS SWITZERLAND AG
Reel/Frame 052905/0532 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Mar 6, 2020
From: ABB SCHWEIZ AG
To: ABB POWER GRIDS SWITZERLAND AG
Reel/Frame 052916/0001 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Aug 26, 2019
From: STENESTAM, BENGT-OLOF
To: ABB SCHWEIZ AG
Reel/Frame 050161/0072 →
Priority Claims (1)
EP 16200009 · Nov 22, 2016 · regional
Continuity (1)
Related Publication 20190288503A1 · Sep 19, 2019
Cited By (1)
US 12,469,653