IP Library › Granted Patent US 11,586,169
Granted Patent B2
US 11,586,169 · App. 16/613,097 · Granted Feb 21, 2023

Production management device

Inventors: Takuji Hatakeyama (Iwata, JP); Yoshiki Okumura (Iwata, JP)
Assignee: YAMAHA HATSUDOKI KABUSHIKI KAISHA
G05B19/188H05K13/02H05K13/085G05B2219/45026
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 11,586,169
App. No.
16/613,097
Granted
Feb 21, 2023
Kind
B2
Abstract

A production management device, such as a production management computer, determines a production sequence of plural types of substrates in order to produce the substrates consecutively on a product type-by-type basis by using a component mounter including component supply devices. The production management device includes a main control unit for determining a production sequence of substrates such that, where a time from start to completion of off-line setup of all the component supply devices to be used for a single product type of substrate is defined as an off-line setup time, a sum of the off-line setup times for two product types of substrates to be consecutively produced is balanced over an entire period of consecutive production.

Claims (12)

1. A production management device that determines a production sequence of plural types of substrates in order to produce the substrates consecutively on a product type-by-type basis by using a component mounter including a plurality of component supply devices, the production management device comprising

a controller configured to determine a production sequence of substrates such that, where a time from start to completion of off-line setup of all the component supply devices to be used for a single product type of substrate is defined as an off-line setup time, a sum of the off-line setup times for two product types of substrates to be consecutively produced is balanced over an entire period of consecutive production, wherein

the plurality of the component supply devices are arranged side by side on a single attachment plate, and it is possible to attach a plurality of the attachment plates to the component mounter, and

the controller is configured to determine the production sequence of substrates such that a substrate of a product type with a larger number of the attachment plates needed simultaneously, and a substrate of a product type with a smaller number of the attachment plates needed simultaneously are alternately arrayed.

2. A production management device that determines a production sequence of plural types of substrates in order to produce the substrates consecutively on a product type-by-type basis by using a component mounter including a plurality of component supply devices, the production management device comprising

a controller configured to determine a production sequence of substrates such that, where a time from start to completion of off-line setup of all the component supply devices to be used for a single product type of substrate is defined as an off-line setup time, a sum of the off-line setup times for two product types of substrates to be consecutively produced is balanced over an entire period of consecutive production, wherein

the controller is configured to determine the production sequence of substrates such that, when a time from start to completion of production of a single product type of substrate is defined as a machine operating time, and when the machine operating time is constant for two product types of substrates to be consecutively produced, a substrate of a product type for which the off-line setup time is longer and a substrate of a product type for which the off-line setup time is shorter are alternately arrayed,

the plurality of the component supply devices are arranged side by side on a single attachment plate, and it is possible to attach a plurality of the attachment plates to the component mounter, and

the controller is configured to determine the production sequence of substrates such that a substrate of a product type with a larger number of the attachment plates needed simultaneously, and a substrate of a product type with a smaller number of the attachment plates needed simultaneously are alternately arrayed.

3. A production management device that determines a production sequence of a plurality of different product type substrates in order to produce the substrates consecutively on a product type-by-type basis by using a component mounter including a plurality of component supply devices, the production management device comprising

a controller configured to rearrange a consecutive production sequence for producing the plurality of different product type substrates by comparing respective off-line setup times for each of the product type substrates and respective machine operating times for each of the product type substrates, to determine a start time for each respective off-line setup and minimize a downtime across a sum of the machine operating times, wherein

the respective off-line setup time for each of the product type substrates is defined as a time from start to completion of off-line setup of all the component supply devices to be used for the respective product type substrate.

Assignments (1)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Nov 12, 2019
From: HATAKEYAMA, TAKUJI; OKUMURA, YOSHIKI
To: YAMAHA HATSUDOKI KABUSHIKI KAISHA
Reel/Frame 050986/0849 →
Continuity (1)
Related Publication 20200333760A1 · Oct 22, 2020