Dry mix and concrete composition containing bed ash and related methods
Embodiments of a dry mix for producing a concrete composition are provided. The dry mix includes aggregate, cement, and bed ash. The bed ash contains the combustion product of a fluidized bed coal combustion reaction. Additionally, embodiments of a method of preparing the dry mix and embodiments of a method of preparing a concrete composition are provided. The dry mix is also suitable for repairing soil slips, and embodiments of a method of repairing a soil slip are also provided.
1. A method of repairing a soil slip on a slope, the method comprising the steps of:
excavating earth from the soil slip to a depth below a slip plane of the soil slip;
mixing the earth with a dry mix to create an augmented soil, the dry mix comprising bed ash and cement;
replacing the augmented soil in the soil slip; and
compacting the augmented soil.
2. The method of claim 1 , wherein the weight ratio of bed ash to cement in the dry mix is from 3:1 to 5:1.
3. The method of claim 2 , wherein the weight ratio of bed ash to cement in the dry mix is about 4:1.
4. The method of claim 1 , wherein the dry mix comprises 18% to 20% by weight of the cement.
5. The method of claim 1 , wherein the dry mix further comprises aggregate.
6. The method of claim 5 , wherein the dry mix comprises substantially equal volumes of aggregate and of bed ash and cement.
7. The method of claim 5 , wherein the aggregate is 2″×3″ crushed stone.
8. The method of claim 1 , wherein the step of excavating further comprises forming one or more keyways in the slope.
9. The method of claim 1 , wherein the augmented soil comprises 5% to 40% by weight of the dry mix.
10. The method of claim 9 , wherein the augmented soil comprises from 10% to 15% by weight of the dry mix.
11. The method of claim 1 , wherein the step of replacing the augmented soil in the soil slip further comprises filling the soil slip in lifts of no more than 24″.
12. The method of claim 11 , wherein the compacting step is performed after each lift.
13. The method of claim 1 , further comprising the step of forming at least one horizontal catchment on the slope.
14. The method of claim 13 , wherein a horizontal catchment of the at least one horizontal catchment is located at a base of the slope between the slop and a roadway.
15. The method of claim 1 , wherein the method does not comprise a step of adding water to the augmented soil.