IP Library › Granted Patent US 11,530,832
Granted Patent B2
US 11,530,832 · App. 17/229,503 · Granted Dec 20, 2022

Peak demand response operation with improved sensible capacity

Inventors: Rakesh Goel (Irving, TX); Vijaykumar Sathyamurthi (Frisco, TX)
Assignee: Lennox Industries Inc.
F24F11/46F24F11/50F24F11/76F24F11/86
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 11,530,832
App. No.
17/229,503
Granted
Dec 20, 2022
Kind
B2
Abstract

An HVAC system includes a variable-speed compressor which compresses refrigerant flowing through the HVAC system, a blower which provides a flow of air through the HVAC system at a controllable flow rate, and a controller communicatively coupled to the variable-speed compressor and the blower. The controller receives a demand request which includes a command to reduce power consumption by the HVAC system. In response to receiving the demand request, a speed of the variable-speed compressor is decreased and the controllable flow rate of the flow of air provided by the blower is adjusted. Accordingly, a ratio of the first flow rate to the decreased tonnage of cooling is increased to a predefined value, and a power consumption of the HVAC system is decreased by at least a predefined percentage associated with the demand request.

Claims (37)

1. A heating, ventilation, and air conditioning (HVAC) system comprising:

a variable-speed compressor configured to compress refrigerant flowing through the HVAC system;

a blower configured to provide a flow of air through the HVAC system at a controllable flow rate; and

a controller communicatively coupled to the variable-speed compressor and the blower, the controller configured to:

receive a demand request, the demand request comprising a command to reduce power consumption by the HVAC system by a predefined percentage;

in response to receipt of the demand request:

decrease a speed of the variable-speed compressor by at least the predefined percentage of the command to reduce power consumption, thereby operating the HVAC system at a decreased tonnage of cooling corresponding to the decreased speed of the variable-speed compressor; and

adjust the controllable flow rate of the flow of air provided by the blower to a first flow rate, based on a predefined ratio of blower flow rate to tonnage of cooling;

wherein, following decreasing the speed of the variable-speed compressor and adjusting the controllable flow rate of the flow of air:

a ratio of the first flow rate to the decreased tonnage of cooling is increased to a predefined value, and

a power consumption of the HVAC system is decreased by at least the predefined percentage associated with the demand request.

2. The HVAC system of claim 1 , wherein the predefined value is greater than or equal to 500 cubic feet per minute per tonnage of cooling.

3. The HVAC system of claim 1 , wherein the controller is further configured to:

determine if a relative humidity of a space conditioned by the HVAC system is greater than a predefined maximum relative humidity value; and

in response to determining the relative humidity of the space is greater than the predefined maximum relative humidity value:

adjust one or both of the speed of the variable-speed compressor to a second speed and the controllable flow rate of the flow of air provided by the blower to a second flow rate, such that a ratio of the first flow rate to the tonnage of cooling is decreased to a second predefined value, wherein the second predefined value is less than the first predefined value.

4. The HVAC system of claim 1 , wherein:

the demand request comprises a start time associated with the command to reduce power consumption; and

the controller is further configured to, prior to decreasing the speed of the variable-speed compressor, cause a space conditioned by the HVAC system to be dehumidified before the start time is reached.

5. The HVAC system of claim 1 , wherein the demand request is received from a third party.

6. A method of operating a heating, ventilation, and air conditioning (HVAC) system, the method comprising:

compressing refrigerant flowing through the HVAC system;

providing a flow of air through the HVAC system at a controllable flow rate;

receiving a demand request, the demand request comprising a command to reduce power consumption of the HVAC system by a predefined percentage;

in response to receiving the demand request:

decreasing a speed of a variable-speed compressor of the HVAC system by at least the predefined percentage of the command to reduce power consumption, thereby operating the HVAC system at a decreased tonnage of cooling corresponding to the decreased speed of the variable-speed compressor; and

adjusting the controllable flow rate of the flow of air provided by a blower of the HVAC system to a first flow rate, based on a predefined ratio of blower flow rate to tonnage of cooling;

wherein, following decreasing the speed of the variable-speed compressor and adjusting the controllable flow rate of the flow of air:

a ratio of the first flow rate to the decreased tonnage of cooling is increased to a predefined value, and

a power consumption of the HVAC system is decreased by at least the predefined percentage associated with the demand request.

7. The method of claim 6 , wherein the predefined value is greater than or equal to 500 cubic feet per minute per tonnage of cooling.

8. The method of claim 6 , further comprising:

determining if a relative humidity of a space conditioned by the HVAC system is greater than a predefined maximum relative humidity value; and

in response to determining the relative humidity of the space is greater than the predefined maximum relative humidity value:

adjusting one or both of the speed of the variable-speed compressor to a second speed and the controllable flow rate of the flow of air provided by the blower to a second flow rate, such that a ratio of the first flow rate to the tonnage of cooling is decreased to a second predefined value, wherein the second predefined value is less than the first predefined value.

9. The method of claim 6 , wherein the demand request comprises a start time associated with the command to reduce power consumption, and the method further comprising, prior to decreasing the speed of the variable-speed compressor, causing a space conditioned by the HVAC system to be dehumidified before the start time is reached.

10. The method of claim 6 , wherein the demand request is received from a third party.

Assignments (1)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Apr 13, 2021
From: GOEL, RAKESH; SATHYAMURTHI, VIJAYKUMAR
To: LENNOX INDUSTRIES INC.
Reel/Frame 055906/0909 →
Continuity (2)
Division 16542861 · Aug 16, 2019
Related Publication 20210231333A1 · Jul 29, 2021