IP Library › Granted Patent US 11,650,553
Granted Patent B2
US 11,650,553 · App. 17/344,517 · Granted May 16, 2023

Machine control using real-time model

Inventors: Bhanu Kiran Reddy Palla (Bettendorf, IA); Nathan R. Vandike (Geneseo, IL); Federico Pardina-Malbran (Fort Collins, CO); Noel W. Anderson (Fargo, ND); Michael A. Waldo (Ankeny, IA)
Assignee: Deere & Company
G05B13/048A01D41/1271A01D41/141G05B13/041
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 11,650,553
App. No.
17/344,517
Granted
May 16, 2023
Kind
B2
Abstract

A priori geo-referenced vegetative index data is obtained for a worksite, along with field data that is collected by a sensor on a work machine that is performing an operation at the worksite. A predictive model is generated, while the machine is performing the operation, based on the geo-referenced vegetative index data and the field data. A model quality metric is generated for the predictive model and is used to determine whether the predictive model is a qualified predicative model. If so, a control system controls a subsystem of the work machine, using the qualified predictive model, and a position of the work machine, to perform the operation.

Claims (54)

1. A method of controlling a machine on a worksite to perform an operation comprising:

identifying geo-referenced soil characteristic data for the worksite that was generated prior to the machine performing the operation at the worksite;

collecting worksite data, with a sensor on the machine, as the machine is performing an operation at the worksite, the worksite data corresponding to a portion of the worksite;

generating a predictive model based on the geo-referenced soil characteristic data and the worksite data;

calculating an error value indicative of model error based on a comparison of model values from the generated predictive model to worksite values in the collected worksite data;

calculating a model quality metric, for the predictive model, indicative of model accuracy, based on the error value;

determining, while the machine is performing the operation at the worksite, whether the predictive model is a qualified predictive model based on the calculated model quality metric and

if so, controlling a subsystem of the machine, using the qualified predictive model, to perform the operation.

2. The method of claim 1 , wherein determining whether the predictive model is a qualified predictive model comprises:

determining whether the model quality metric meets a model quality threshold.

3. The method of claim 1 , and further comprising:

if the predictive model is determined not to be a qualified predictive model, then

identifying different geo-referenced soil characteristic data for generating a different predictive model;

generating the different predictive model;

determining, while the machine is performing the operation at the worksite, whether the different predictive model is a qualified model; and

if so, controlling a subsystem of the machine, using the different predictive model to perform the operation.

4. The method of claim 1 , wherein identifying geo-referenced soil characteristic data comprises:

obtaining a priori georeferenced soil characteristic data, from a remote system, corresponding to the worksite.

5. The method of claim 1 , wherein collecting worksite data comprises:

aggregating worksite data corresponding to a portion of the worksite, as the machine is performing an operation at the worksite.

6. The method of claim 1 , wherein the machine has a plurality of different subsystems and wherein controlling a subsystem comprises:

controlling the plurality of different subsystems on the machine.

7. The method of claim 6 , wherein generating a predictive model comprises:

generating a plurality of different predictive models, based on a priori data and the worksite data, for the different subsystems of the work machine.

8. The method of claim 7 , wherein calculating a model quality metric comprises:

calculating a plurality of different model quality metrics values for the different predictive models, wherein determining whether the predictive model is a qualified predictive model comprises determining whether each of the plurality of predictive models are qualified predictive models based on the calculated model quality metrics values.

9. The method of claim 8 , and further comprising:

if the plurality of different predictive models are qualified predictive models, then controlling each of the different subsystems of the work machine on the worksite, using a different one of the plurality of different predictive models.

10. The method of claim 1 , and further comprising:

iteratively repeating steps of collecting worksite data, updating the predictive model based on the worksite data, calculating a model quality metric for the updated predictive model and determining whether the predictive model is a qualified predicative model, while the machine is performing the operation.

11. A computing system on a work machine comprising:

a communication system configured to identify a priori, geo-referenced soil characteristic data for a worksite;

an in situ data collection system that collects worksite data, with a sensor on a machine, as the work machine is performing an operation at the worksite, the worksite data corresponding to a portion of the worksite;

a model generator system configured to receive the a priori, geo-referenced soil characteristic data and worksite data and generate a predictive model based on the a priori geo-referenced soil characteristic data and the worksite data, as the work machine is performing the operation at the worksite, using a model generation mechanism, the predictive model including predictive values of a characteristic of the worksite; and

a control system that, controls a subsystem of the machine using the predictive model.

12. The computing system of claim 11 , and further comprising:

a model evaluation system configured to calculate a model quality metric for the predictive model and determine whether the predictive model is a qualified predictive model; and

wherein the control system controls the subsystem using the predictive model if the predictive model is a qualified predictive model.

13. The computing system of claim 12 , wherein the model evaluation system comprises:

a model quality metric generator configured to calculate the model quality metric for the predictive model.

14. The computing system of claim 13 , wherein the model evaluation system comprises:

evaluation trigger logic configured to detect an evaluation trigger and, in response, generate a trigger output for the model evaluation system to evaluate an alternative predictive model.

15. The computer system of claim 14 , wherein the model generation system is configured to, in response to the trigger output, generate the alternative predictive model using alternative a priori soil characteristic data for the worksites.

16. The computer system of claim 14 , wherein the model generation system is configured to, in response to the trigger output, generate the alternative predictive model using an alternative model generation mechanism.

17. The computing system of claim 16 wherein the model generator system is configured to generate a plurality of predictive models each corresponding to a specific controllable subsystem, and wherein the control system uses each of the predictive models to control the corresponding specific controllable subsystem.

18. The computing system of claim 11 , wherein the a priori, geo-referenced soil characteristic data are generated prior to the work machine performing the operation at the worksite.

19. A work machine comprising:

a communication system configured to receive geo-referenced soil characteristic data for a worksite;

an in situ data collection system configured to collect worksite data, with a sensor on the work machine, as the work machine is performing an operation at the worksite, for a portion of the worksite;

a plurality of controllable subsystems;

a model generator system configured to generate a plurality of different predictive models, based on the geo-referenced soil characteristic data and the worksite data, each corresponding to a different controllable subsystem of the plurality of controllable subsystems of the work machine, the plurality of different predictive models including predictive values of an at least one characteristic of the worksite to be encountered by the work machine; and

a control system that generates control signals to control each of the controllable subsystems using a corresponding predictive model.

20. The work machine of claim 19 , and further comprising:

a model evaluation system configured to calculate a model quality metric for each of the predictive models and determine whether each of the predictive models is a qualified predictive model based on the model quality metrics, wherein the control system generates the control signals to control each of the controllable subsystems using a corresponding qualified predictive model.

Assignments (1)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jun 11, 2021
From: PALLA, BHANU KIRAN REDDY; VANDIKE, NATHAN R.; PARDINA-MALBRAN, FEDERICO; ANDERSON, NOEL W.; WALDO, MICHAEL A.
To: DEERE & COMPANY
Reel/Frame 056508/0741 →
Continuity (2)
Continuation 16380531 · Apr 10, 2019
Related Publication 20210302925A1 · Sep 30, 2021
Cited By (2)
US 12,550,807 US 12,635,678