IP Library › Granted Patent US 12,258,868
Granted Patent B2
US 12,258,868 · App. 18/190,672 · Granted Mar 25, 2025

System and method for an in-conduit hydroturbine

Inventors: Michael Connor, Jr. (Saint Clair, MI); Thomas Beales (Houston, TX); Gregory T. Semler (Belvedere, CA)
Assignee: INPIPE ENERGY, INC.
F01D15/10F01D17/08F01D21/14F02B37/183F05D2220/76F05D2270/02F05D2270/3013F05D2270/44F05D2270/54
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 12,258,868
App. No.
18/190,672
Granted
Mar 25, 2025
Kind
B2
Abstract

System and methods for an electric power generating system are described. In one example, the electric power generating system includes a controller that adjusts a speed of a turbine that is located along a bypass conduit via a regenerative drive in response to a downstream pressure. The electric power generating system also includes a bypass valve that is located along the bypass conduit to control a system pressure when the turbine is not adjusted responsive to the downstream pressure.

Claims (29)

1. An electrical power generating system, comprising:

a bypass conduit including a bypass control valve and a turbine;

a primary conduit including a primary control valve; and

a controller including executable instructions stored in non-transitory memory that causes the controller to:

responsive to a fluid flow rate through the primary conduit being greater than a minimum threshold flow rate, adjust a speed of the turbine in response to a downstream pressure while the bypass control valve is fully open,

where the downstream pressure is a pressure in the primary conduit downstream of the primary control valve.

2. The electrical power generating system of claim 1 , where the adjusting the speed of the turbine includes decreasing the speed of the turbine when a downstream pressure is not greater than a desired downstream pressure minus a first offset pressure.

3. The electrical power generating system of claim 2 , where the adjusting the speed of the turbine includes increasing the speed of the turbine when the downstream pressure is greater than the desired downstream pressure plus a second offset pressure.

4. The electrical power generating system of claim 3 , where the adjusting the speed of the turbine includes maintaining the speed of the turbine when the downstream pressure is greater than the desired downstream pressure minus the first offset pressure and not greater than the desired downstream pressure plus the second offset pressure.

5. The electrical power generating system of claim 1 , where the controller adjusts the speed of the turbine via commanding a regenerative drive.

6. The electrical power generating system of claim 5 , where the regenerative drive includes a rectifier and an inverter.

7. The electrical power generating system of claim 1 , further comprising additional executable instructions that cause the controller to:

responsive to a fluid flow rate through the primary conduit being less than the minimum threshold flow rate, adjust the bypass control valve in response to the downstream pressure while maintaining the speed of the turbine at zero or a minimum non-zero speed.

8. A method for an electrical power generating system, comprising:

responsive to a flow rate through a primary conduit being greater than a minimum threshold flow rate, via a controller, fully opening a bypass control valve and adjusting a speed of a turbine in a bypass conduit in response to a downstream pressure in a fluid distribution system, the downstream pressure being a pressure in the primary conduit downstream of a primary control valve, the bypass conduit parallel with the primary conduit, the bypass control valve positioned in the bypass conduit.

9. The method of claim 8 , where the minimum threshold flow rate based on pipe size or historical water demand.

10. The method of claim 9 , further comprising adjusting a position of the bypass control valve in response to the flow rate through the primary conduit being less than the minimum threshold flow rate.

11. The method of claim 10 , where the bypass control valve is adjusted in response to the downstream pressure in the fluid distribution system.

12. The method of claim 11 , where the bypass control valve is incrementally opened in response to the downstream pressure not being greater than a desired downstream pressure minus a first offset pressure.

13. The method of claim 12 , where the bypass control valve is incrementally closed in response to the downstream pressure being greater than the desired downstream pressure plus a second offset pressure.

14. The method of claim 13 , where the controller commands a regenerative drive to adjust the speed of the turbine.

15. An electrical power generating system, comprising:

a bypass conduit including a bypass control valve and a turbine;

a primary conduit including a primary control valve; and

a controller including executable instructions stored in non-transitory memory that causes the controller to operate the electrical power generating system in a plurality of operating states including a fourth operating state where the bypass control valve is fully open, and a speed of the turbine is adjusted in response to a downstream pressure when a fluid flow rate through the primary conduit is greater than a minimum threshold flow rate, where the downstream pressure is a pressure in the primary conduit downstream of the primary control valve.

16. The electrical power generating system of claim 15 , where the plurality of operating states includes a first operating state where the speed of the turbine is zero and the bypass control valve is fully closed.

17. The electrical power generating system of claim 16 , where the plurality of operating states includes a second operating state where the speed of the turbine is zero and the bypass control valve is partially opened responsive to a flow rate through the primary conduit being below a starting threshold flow rate, the minimum threshold flow rate greater than the starting threshold flow rate.

18. The electrical power generating system of claim 17 , where the plurality of operating states includes a third operating state where the speed of the turbine is a minimum non-zero speed and the bypass control valve is partially opened responsive to a flow rate through the primary conduit being above the starting threshold flow rate and below the minimum threshold flow rate.

19. The electrical power generating system of claim 18 , where the plurality of operating states includes a fifth operating state where the speed of the turbine is maintained and the bypass control valve is fully opened responsive to a flow rate through the primary conduit being above a maximum threshold flow rate, the maximum threshold flow rate greater than the minimum threshold flow rate.

Assignments (1)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Mar 28, 2023
From: CONNOR, MICHAEL, JR.; BEALES, THOMAS; SEMLER, GREGORY T.
To: INPIPE ENERGY, INC.
Reel/Frame 063130/0976 →
Continuity (1)
Related Publication 20240328326A1 · Oct 3, 2024
References Cited (23)
US 3808794A · Wood · 1974 [cited by examiner]
US 4496845A · Ensign et al. · 1985 [cited by applicant]
US 4654537A · Gaspard · 1987 [cited by examiner]
US 4658587A · Ecomard · 1987 [cited by examiner]
US 4809510A · Gaspard · 1989 [cited by examiner]
US 8680704B1 · Rooney · 2014 [cited by examiner]
US 9611627B2 · Schreiner · 2017 [cited by examiner]
US 10247100B2 · Leamy · 2019 [cited by examiner]
US 10947953B2 · Burns · 2021 [cited by examiner]
US 11041476B2 · Abe · 2021 [cited by examiner]
US 11946604B2 · Semler · 2024 [cited by examiner]
US 20120261921A1 · Kaiser · 2012 [cited by applicant]
US 20130092126A1 · Leone et al. · 2013 [cited by applicant]
US 20140158242A1 · Schreiner · 2014 [cited by examiner]
US 20140265328A1 · Van Blerk · 2014 [cited by examiner]
US 20150260151A1 · Kang · 2015 [cited by examiner]
US 20210310221A1 · Semler · 2021 [cited by examiner]
US 20220128044A1 · Semler · 2022 [cited by examiner]
US 20240142064A1 · Semler · 2024 [cited by examiner]
GB 2191248A · 1987 [cited by examiner]
JP 2009138633A · 2009 [cited by applicant]
KR 101555433B1 · 2015 [cited by applicant]
ISA Korean Intellectual Property Office, International Search Report and Written Opinion Issued in Application No. PCT/US2024/012979, May 31, 2024, WIPO, 10 pages. [cited by applicant]
Cited By (1)
US 12,345,229