Data center workload monitoring via a data center monitoring and management operation

Inventors: Vinay Sawal (Fremont, CA); Ching-Yun Chao (Austin, TX); Anil Varkhedi (San Jose, CA); Deepak Krishna (Newcastle, WA); Rajini Karthik (Austin, TX); Muzhar S. Khokhar (Shrewsbury, MA)
Assignee: Dell Products L.P.
H04L43/067H04L41/16H04L43/0817
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 12,224,922
App. No.
18/226,902
Granted
Feb 11, 2025
Kind
B1
Abstract

A system, method, and computer-readable medium for performing a data center monitoring and management operation. The data center monitoring and management operation includes: receiving data center asset workload data; capturing a set of the data center asset workload data at predefined time intervals; monitoring data center workload performance using the set of the data center asset workload data; and, predicting an anomaly associated with data center workload performance based upon the monitoring.

Claims (58)

1. A computer-implementable method for performing a data center monitoring and management operation, comprising:

receiving data center asset workload data associated with a workload executing on a data center asset;

capturing a set of the data center asset workload data at predefined time intervals, the set of the data center asset workload data representing a sequence of events occurring within a time window on the data center asset, the sequence of events comprising an iteratively captured sequence of image-based console data;

monitoring data center workload performance using the set of the data center asset workload data, the monitoring being performed at a particular point in a lifecycle of the workload executing on the data center asset; and,

predicting an anomaly associated with data center workload performance based upon the monitoring.

2. The method of claim 1 , further comprising:

analyzing a sliding window time slice of the set of data center asset workload data; and,

applying a learning model to the sliding window time slice of the set of data center asset workload data.

3. The method of claim 2 , wherein:

the learning model comprises one or more of a deep learning model and a bidirectional encoder representation from transformers (BERT) model.

4. The method of claim 1 , wherein:

the data center asset workload data comprises installation data.

5. The method of claim 4 , wherein:

the installation data comprises image data and text data.

6. The method of claim 5 , wherein:

the image data comprises an iteratively-captured set of K images; and,

the iteratively-captured set of K images are provided to a convolutional autoencoder, the convolutional autoencoder learning common occurrences of outcomes based upon the iteratively-captured set of K images.

7. A system comprising:

a processor;

a data bus coupled to the processor; and,

a non-transitory, computer-readable storage medium embodying computer program code, the non-transitory, computer-readable storage medium being coupled to the data bus, the computer program code interacting with a plurality of computer operations and comprising instructions executable by the processor and configured for:

receiving data center asset workload data associated with a workload executing on a data center asset;

capturing a set of the data center asset workload data at predefined time intervals, the set of the data center asset workload data representing a sequence of events occurring within a time window on the data center asset, the sequence of events comprising an iteratively captured sequence of image-based console data;

monitoring data center workload performance using the set of the data center asset workload data, the monitoring being performed at a particular point in a lifecycle of the workload executing on the data center asset; and,

predicting an anomaly associated with data center workload performance based upon the monitoring.

8. The system of claim 7 , wherein the instructions executable by the processor are further configured for:

analyzing a sliding window time slice of the set of data center asset workload data; and,

applying a learning model to the sliding window time slice of the set of data center asset workload data.

9. The system of claim 8 , wherein:

the learning model comprises one or more of a deep learning model and a bidirectional encoder representation from transformers (BERT) model.

10. The system of claim 7 , wherein:

the data center asset workload data comprises installation data.

11. The system of claim 10 , wherein:

the installation data comprises image data and text data.

12. The system of claim 11 , wherein:

the image data comprises an iteratively-captured set of K images; and,

the iteratively-captured set of K images are provided to a convolutional autoencoder, the convolutional autoencoder learning common occurrences of outcomes based upon the iteratively-captured set of K images.

13. A non-transitory, computer-readable storage medium embodying computer program code, the computer program code comprising computer executable instructions configured for:

receiving data center asset workload data associated with a workload executing on a data center asset;

capturing a set of the data center asset workload data at predefined time intervals, the set of the data center asset workload data representing a sequence of events occurring within a time window on the data center asset, the sequence of events comprising an iteratively captured sequence of image-based console data;

monitoring data center workload performance using the set of the data center asset workload data, the monitoring being performed at a particular point in a lifecycle of the workload executing on the data center asset; and,

predicting an anomaly associated with data center workload performance based upon the monitoring.

14. The non-transitory, computer-readable storage medium of claim 13 , wherein the computer executable instructions are further configured for:

analyzing a sliding window time slice of the set of data center asset workload data; and,

applying a learning model to the sliding window time slice of the set of data center asset workload data.

15. The non-transitory, computer-readable storage medium of claim 14 , wherein:

the learning model comprises one or more of a deep learning model and a bidirectional encoder representation from transformers (BERT) model.

16. The non-transitory, computer-readable storage medium of claim 13 , wherein:

the data center asset workload data comprises installation data.

17. The non-transitory, computer-readable storage medium of claim 16 , wherein:

the installation data comprises image data and text data.

18. The non-transitory, computer-readable storage medium of claim 17 , wherein:

the image data comprises an iteratively-captured set of K images; and,

the iteratively-captured set of K images are provided to a convolutional autoencoder, the convolutional autoencoder learning common occurrences of outcomes based upon the iteratively-captured set of K images.

19. The non-transitory, computer-readable storage medium of claim 13 , wherein:

the computer executable instructions are deployable to a client system from a server system at a remote location.

20. The non-transitory, computer-readable storage medium of claim 13 , wherein:

the computer executable instructions are provided by a service provider to a user on an on-demand basis.

Assignments (1)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jul 27, 2023
From: SAWAL, VINAY; CHAO, CHING-YUN; VARKHEDI, ANIL; KRISHNA, DEEPAK; KARTHIK, RAJINI; KHOKHAR, MUZHAR S.
To: DELL PRODUCTS L.P.
Reel/Frame 064401/0550 →
References Cited (20)
US 10613962B1 · Delange · 2020 [cited by examiner]
US 11294756B1 · Sadrieh · 2022 [cited by examiner]
US 11812285B1 · O'Mahony · 2023 [cited by examiner]
US 11831525B1 · Effern · 2023 [cited by examiner]
US 20110126275A1 · Anderson · 2011 [cited by examiner]
US 20160359683A1 · Bartfai-Walcott · 2016 [cited by examiner]
US 20180367607A1 · Gakhar · 2018 [cited by examiner]
US 20200099592A1 · Mahindru · 2020 [cited by examiner]
US 20200162342A1 · Fattu · 2020 [cited by examiner]
US 20200272909A1 · Parmentier · 2020 [cited by examiner]
US 20200351171A1 · Ozonat · 2020 [cited by examiner]
US 20210184916A1 · Ramanujan · 2021 [cited by examiner]
US 20210382631A1 · Singh · 2021 [cited by examiner]
US 20220012633A1 · Molahalli · 2022 [cited by examiner]
US 20220019461A1 · Balle · 2022 [cited by examiner]
US 20220027188A1 · Nagaraj · 2022 [cited by examiner]
US 20230065444A1 · Pyla · 2023 [cited by examiner]
US 20230188382A1 · Nath · 2023 [cited by examiner]
US 20230281069A1 · Goska · 2023 [cited by examiner]
US 20230421430A1 · Thakkar · 2023 [cited by examiner]