IP Library Granted Patent US 7,178,351
Granted Patent B2
US 7,178,351 · App. 10/658,277 · Granted Feb 20, 2007

Heat exchanger optimization process and apparatus

View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 7,178,351
App. No.
10/658,277
Granted
Feb 20, 2007
Kind
B2
Abstract

An electronic HEMD determines the optimum balance between gas cooling and heat exchanger pressure loss, for any given operating condition, and adjusts the gas flow rate through the exchanger accordingly, to yield the maximum net power savings (and thereby energy savings) afforded by the exchanger. Maintaining the optimum balance between cooling and exchanger pressure loss reduces the amount of energy required to transport a given volume of gas through a pipeline and thereby increases the transmission efficiency of the gas pipeline system. A method of operating a heat exchanger on a natural gas transmission pipeline using a control algorithm that in turn controls the position of a heat exchanger bypass valve. The current operating conditions of the upstream compressor and gas cooling system are continually monitored for any changes and the control algorithm determines, the optimum flow through the heat exchanger and initiates a command signal to the exchanger bypass valve operator to move the bypass valve and thereby increase or decrease the gas flow rate through the exchanger, as required, until the optimum balance between gas cooling and heat exchanger pressure loss has been achieved.

Claims (30)

1. A method for controlling gas cooling in a gas pipeline having a heat exchanger at a compressor station, the method comprising the steps of:

A) obtaining observations of parameters that are characteristic of gas flow through the compressor station under a set of operating conditions having a corresponding energy cost, the observations comprising gas temperature at the inlet of the heat exchanger, gas temperature at the outlet of the heat exchanger, ambient air temperature and pressure, gas pressure at the inlet of the heat exchanger, gas pressure loss across the heat exchanger, estimated gas flow rate through the heat exchanger and periodic estimated gas flow through the heat exchanger bypass valve, and compressor station;

B) from the observations of step A, determining a balance between gas cooling and heat exchanger gas pressure loss that results in an improvement of energy savings by comparison with the energy cost of the set of operating conditions; and C) operating a bypass valve on the gas pipeline to divert an amount of gas into the heat exchanger that achieves the balance determined in step B.

2. The method of claim 1 further comprising the steps of:

finding the expected pressure differential across the heat exchanger at a level of gas flow rate;

finding the actual pressure differential across the heat exchanger at a level of gas flow rate;

finding a relationship between the actual pressure differential and expected pressure differential across the heat exchanger at the level of gas flow rate; and

finding the degree of internal fouling of the heat exchanger from the relationship found in the preceding step.

3. The method of claim 2 further comprising the step of:

adjusting the determination of step B for the gas flow rate through the heat exchanger.

4. The method of claim 2 further comprising the step of:

recording the increase in pressure differential across the heat exchanger tubes for future maintenance action.

5. The method of claim 2 further comprising the steps of:

finding a relationship between the original fouling resistance and actual current fouling resistance for the heat exchanger at level of cooling and gas flow rate; and

finding the degree of internal and/or external fouling of the heat exchanger from the relationship found in the preceding step.

6. The method of claim 5 further comprising the step of:

adjusting the determination of step B for the gas flow rate through the heat exchanger.

7. The method of claim 5 further comprising the step of:

recording the increase in internal and/or external fouling of the heat exchanger tubes for future maintenance action.

8. The method of claim 1 further comprising the steps of:

finding the original dirty overall heat transfer coefficient for the heat exchanger at a level of cooling and gas flow rate;

finding the original clean overall heat transfer coefficient for the heat exchanger at a level of cooling and gas flow rate;

finding a relationship between the original dirty and clean overall heat transfer coefficient at the level of cooling and gas flow rate; and

finding the original fouling resistance for the heat exchanger from the relationship found in the preceding step.

9. The method of claim 1 further comprising the steps of:

finding the actual current dirty overall heat transfer coefficient for the heat exchanger at a level of cooling and gas flow rate;

finding the actual current clean overall heat transfer coefficient for the heat exchanger at a level of cooling and gas flow rate;

finding a relationship between the actual current dirty and clean overall heat transfer coefficient at a level of cooling and gas flow rate; and

finding the actual current fouling resistance for the heat exchanger from the relationship found in the preceding step.

10. The method of claim 1 in which the determination of step B takes into account compression power requirements in the pipeline downstream of the compressor.

Continuity (1)
Related Publication 20050034467A1 · Feb 17, 2005