Project management applications utilizing summary tasks for top-down project planning

Assignee: Microsoft Corporation
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,160,911
App. No.
12/468,663
Granted
Apr 17, 2012
Kind
B2
Abstract

Embodiments of the present invention are directed toward providing a method utilizing project management software for creating a project plan utilizing a top-down strategy allowing a user to describe high-level objectives before filling in details for the underlying tasks of which the high-level objectives are comprised. As an alternative to basing summary task dates and durations solely on subtask data, the present invention allows a user to enter dates and duration values into summary tasks regardless of when the corresponding subtasks occur. By utilizing a top-down project management approach, embodiments of the present invention promote utilizing summary tasks as a starting point of project planning. Users are able to input high-level objectives of a project when more specific details of subtasks are unknown. Because summary task data is not rolled-up from the subtask data, a user may specify details such as dates and durations of subtasks at a later time.

Claims (49)

1. A computer-implemented method for creating a top down project plan, the method comprising:

receiving information entered by a user associated with a summary task comprising subtasks;

determining by a processor executing code stored on a computer-readable medium whether a summary task's start date, finish date, or duration fields contain user-entered information;

when at least one, but no more than two of a summary task's start date, finish date, or duration fields contain user-entered information,

determining a schedule of planned dates for the summary task utilizing summary task information entered by the user in addition to calculated roll-up dates of the summary task's subtask information;

determining when a summary task's calculated roll-up dates contradict planned dates;

when a task's calculated roll-up dates contradict planned dates, preserving the user-entered planned dates; and

displaying the determined summary task schedule in the corresponding fields of the project plan;

wherein when all three of a summary task's start date, finish date, or duration fields contain user-entered information,

preserving the user-entered planned dates;

identifying differences between the planned dates and the roll-up dates of the summary task's subtasks when differences exist; and

displaying an indication of whether a task contains planned dates or when the task contains roll-up dates.

2. The computer-implemented method of claim 1 , wherein

when no user-entered information is contained in a summary task's start date, finish date, and duration fields,

determining a schedule for the summary task utilizing calculated roll-up dates of the summary task's subtask information; and

displaying the determined summary task schedule in the corresponding fields of the project plan.

3. The computer-implemented method of claim 1 , wherein identifying differences between the planned dates and the roll-up dates of the summary task includes providing a planned date Gantt bar and a calculated roll-up date Gantt bar displayed on a project plan Gantt chart.

4. The computer-implemented method of claim 1 , wherein identifying differences between the planned dates and the roll-up dates of the summary task includes providing a planned date field and a roll-up date field within a project plan table.

5. The computer-implemented method of claim 1 , wherein determining when a summary task's calculated roll-up dates contradict planned dates includes determining whether a summary task start date occurs before all of the start dates of the subtasks of the summary task.

6. The computer-implemented method of claim 1 , wherein determining when a summary task's calculated roll-up dates contradict planned dates includes determining whether a summary task start date occurs after all the finish dates of the subtasks of the summary task.

7. The computer-implemented method of claim 1 , wherein determining when a summary task's calculated roll-up dates contradict planned dates includes determining whether a summary task finish date occurs after all the finish dates of the subtasks of the summary task.

8. The computer-implemented method of claim 1 , wherein determining when a summary task's calculated roll-up dates contradict planned dates includes determining whether a summary task finish date occurs before all the finish dates of the subtasks of the summary task.

9. The computer-implemented method of claim 1 , wherein displaying an indication of whether a task contains planned dates or when the task contains roll-up dates includes displaying a push pin icon in association with information displayed for the task when the task contains only planned dates.

10. The computer-implemented method of claim 1 , wherein displaying an indication of whether a task contains planned dates or when the task contains roll-up dates includes displaying a push pin icon and a question mark in association with information displayed for the task when the task contains planned dates and roll-up dates.

11. The computer-implemented method of claim 1 , wherein displaying an indication of whether a task contains planned dates or when the task contains roll-up dates includes displaying an arrow icon in association with information displayed for the task when the task contains only roll-up dates.

12. A computer-readable storage medium containing computer-executable instructions which when executed by a computer perform a method for creating a top down project plan, the method comprising:

receiving information entered by a user associated with a summary task comprising one or more subtasks;

determining whether a summary task's start date, finish date, or duration fields contain user-entered information;

when at least one, but no more than two of a summary task's start date, finish date, or duration fields contain user-entered information,

determining a schedule of planned dates for the summary task utilizing summary task information entered by the user in addition to calculated roll-up dates of the summary task's subtask information;

determining when a summary task's calculated roll-up dates contradict planned dates; and

when a summary task's calculated roll-up dates contradict planned dates,

preserving the user-entered planned dates; and

identifying differences between the planned dates and the roll-up dates;

displaying the determined summary task schedule in the corresponding fields of the project plan;

but, when no user-entered information is contained in a summary task's start date, finish date, and duration fields,

determining a schedule for the summary task utilizing calculated roll-up dates of the summary task's subtask information; and

displaying the determined summary task schedule in the corresponding fields of the project plan;

wherein when all three of a summary task's start date, finish date, or duration fields contain user-entered information,

preserving the user-entered planned dates; and

identifying any differences between the planned dates and the roll-up dates of the summary tasks' subtasks; and

displaying an indication of whether a task contains planned dates or when the task contains roll-up dates.

13. The computer-readable medium of claim 12 ,

wherein identifying differences between the planned dates and the roll-up dates of the summary task includes providing a planned date Gantt bar and a calculated roll-up date Gantt bar displayed on a project plan Gantt chart; and

wherein identifying differences between the planned dates and the roll-up dates of the summary task includes providing a planned date field and a roll-up date field within a project plan table.

14. The computer-readable medium of claim 12 , wherein determining when a summary task's calculated roll-up dates contradict planned dates includes determining whether a summary task start date occurs before all of the start dates of the subtasks comprising the summary task.

15. The computer-readable medium of claim 12 , wherein determining when a summary task's calculated roll-up dates contradict planned dates includes determining whether a summary task start date occurs after all the finish dates of the subtasks of the summary task.

16. The computer-readable medium of claim 12 , wherein determining when a summary task's calculated roll-up dates contradict planned dates includes determining whether a summary task finish date occurs after all the finish dates of the subtasks of the summary task.

17. The computer-readable medium of claim 12 , wherein determining when a summary task's calculated roll-up dates contradict planned dates includes determining whether a summary task finish date occurs before all the finish dates of the subtasks of the summary task.

Assignments (2)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Dec 9, 2014
From: MICROSOFT CORPORATION
To: MICROSOFT TECHNOLOGY LICENSING, LLC
Reel/Frame 034564/0001 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Aug 10, 2009
From: LAU, BONNY P.; SHAHDAD, MOHAMMAD YAKOOB; DE VRIES, PETER; STEINGLASS, ALICE PRITIKIN
To: MICROSOFT CORPORATION
Reel/Frame 023076/0945 →
Continuity (1)
Related Publication 20100299171A1 · Nov 25, 2010