IP Library Granted Patent US 8,191,721
Granted Patent B2
US 8,191,721 · App. 11/986,035 · Granted Jun 5, 2012

Method and device for mounting of wind turbine blades

Assignee: Siemens Aktiengesellschaft
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,191,721
App. No.
11/986,035
Granted
Jun 5, 2012
Kind
B2
Abstract

A method for mounting a wind turbine blade to a wind turbine hub by use of a crane boom is provided. The orientation of the blade is kept substantially horizontal when the blade is lifted off the ground and mounted to the rotor hub. Control wires which connect the blade via the crane boom to a winch arrangement are used for keeping the blade orientation substantially horizontal in addition to at least one bearing wire for bearing the blade weight.

Claims (11)

1. A wind turbine blade lifting system, comprising:

a lifting device with a frame, wherein a wind turbine blade is connectable to the lifting device, and wherein the frame has two ends and a central area;

a crane boom;

a winch arrangement; and

control wires for controlling a blade orientation, wherein the control wires run from the lifting device via the crane boom to the winch arrangement,

wherein the control wires are connected to the ends of the frame and allow for controlling the blade orientation to be substantially horizontal when a wind turbine blade has been lifted of the ground.

2. The wind turbine blade lifting system as claimed in claim 1 , wherein the winch arrangement is located at the crane boom's bottom end.

3. The wind turbine blade lifting system as claimed in claim 1 , wherein the control wires run from the lifting device to pulleys at the crane boom and from the pulleys to the winch arrangement.

4. The wind turbine blade lifting system as claimed in claim 3 , wherein the pulleys are movable with respect to the crane boom.

5. The wind turbine blade lifting system as claimed in claim 4 , wherein the winch arrangement comprises at least two independently controllable winches for at least two control wires.

6. The wind turbine blade lifting system as claimed in claim 1 , wherein the winch arrangement comprises at least two independently controllable winches for at least two control wires.

Assignments (3)
CHANGE OF NAME Recorded Jul 28, 2021
From: SIEMENS WIND POWER A/S
To: SIEMENS GAMESA RENEWABLE ENERGY A/S
Reel/Frame 057434/0737 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Dec 2, 2016
From: SIEMENS AKTIENGESELLSCHAFT
To: SIEMENS WIND POWER A/S
Reel/Frame 040492/0102 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Feb 21, 2008
From: HANSEN, HENRIK LYNDERUP; MOELLER, JESPER
To: SIEMENS AKTIENGESELLSCHAFT
Reel/Frame 020551/0527 →
Priority Claims (3)
EP 06024336 · Nov 23, 2006 · regional
EP 06024337 · Nov 23, 2006 · regional
EP 07013724 · Jul 12, 2007 · regional
Continuity (1)
Related Publication 20080216301A1 · Sep 11, 2008