Offshore wind turbine installation

Inventors: Kok Seng Foo (Singapore, SG); Hock Chye Michael Chia (Singapore, SG); Asbjørn Mortensen (Singapore, SG); Cheng Choong Chan (Singapore, SG); Teng Kiat Lim (Singapore, SG); Toh Tung Wong (Singapore, SG); Tom Aksel Waitz Østvold (Singapore, SG); Rune Henriksen (Norway, NO)
Assignees: Keppel Offshore & Marine Technology Centre Pte Ltd; Offshore Technology Development Pte Ltd; Keppel Fels Ltd
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,640,340
App. No.
12/759,037
Granted
Feb 4, 2014
Kind
B2
Abstract

Installation vessels and methods for offshore wind turbine installation are disclosed. In one embodiment, a cantilever mast is used to transfer of wind turbine components from an installation vessel to an offshore installation site and guide the transfer to prevent undesired swinging movements of the wind turbine components. In another embodiment, a main crane is used in cooperation with a guide arm to transfer and guide wind turbine components from an installation vessel to an offshore installation site.

Claims (23)

1. An offshore wind turbine installation method, comprising:

disposing an installation vessel proximate to an offshore installation site, the installation vessel comprising:

a deck;

a cantilever mast mounted on the deck, the cantilever mast including:

a cantilever structure movably mounted on the deck; and a mast mounted on the cantilever structure, the mast including a lifting structure operable to secure to a wind turbine component, a first guide, and an intermediate platform;

transferring at least one wind turbine component from the installation vessel to the offshore installation site, including:

securing the at least one wind turbine component to the lifting structure;

while movably engaging the lifting structure to the mast using the first guide to prevent swinging of the at least one wind turbine component, moving the cantilever mast in a longitudinal direction and a transverse direction to position the at least one wind turbine component at the offshore installation site spaced apart from the installation vessel; and

performing blade installation on a nacelle and a hub supported on the intermediate platform at an intermediate height along the mast to form a nacelle and rotor assembly.

2. The method of claim 1 , wherein transferring at least one wind turbine component includes transferring the nacelle and rotor assembly, the method further comprising:

transferring a tower section from the installation vessel to the offshore installation site by using the main crane; and

at the same time, performing the blade installation.

3. The method of claim 1 , wherein transferring at least one wind turbine component includes transferring the nacelle and rotor assembly, the method further comprising:

transferring a tower section to a pick-up position for lifting by the mast;

transferring the tower section to the offshore installation site, including lifting the tower section using the mast, and

while movably engaging the tower section to the mast using a second guide to prevent swinging of the tower section, moving the cantilever mast in a longitudinal direction and a transverse direction to position the tower section at the offshore installation site; and

thereafter, performing the blade installation.

4. The method of claim 1 , wherein transferring at least one wind turbine component includes transferring the nacelle and rotor assembly, the method further comprising:

transferring the nacelle and rotor assembly from the installation vessel by moving the cantilever mast in a longitudinal direction and a transverse direction to lift the nacelle and rotor assembly from the intermediate platform; and

transferring the nacelle and rotor assembly from the intermediate platform to the offshore installation site by using the main crane.

5. The method of claim 1 , wherein transferring the at least one wind turbine component includes transferring the nacelle and rotor assembly to the offshore installation site, the method further comprising:

transferring a tower section and the nacelle and rotor assembly from the installation vessel to the offshore installation site using one of the main crane and the cantilever mast; and

transferring the blade from a blade magazine to an elevator movably installed along the mast.

Assignments (1)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded May 18, 2010
From: FOO, KOK SENG; CHIA, HOCK CHYE MICHAEL; MORTENSEN, ASBJORN; CHAN, CHENG CHOONG; LIM, TENG KIAT; WONG, TOH TUNG; OSTVOLD, TOM AKSEL WAITZ; HENRIKSEN, RUNE
To: KEPPEL OFFSHORE & MARINE TECHNOLOGY CENTRE PTE LTD; OFFSHORE TECHNOLOGY DEVELOPMENT PTE LTD; KEPPEL FELS LTD
Reel/Frame 024399/0237 →
Continuity (3)
Provisional Application 61180644 · May 22, 2009
Provisional Application 61220604 · Jun 26, 2009
Related Publication 20100293781A1 · Nov 25, 2010