Water heater demand side management system

Inventors: Benjamin F. Harbin, III (Athens, AL); Cecil Ray Holland, Jr. (Ardmore, TN); Robert J. Toth (Huntsville, AL); Adrian O'Neil (Madison, AL); Michael Scott Sansom (Huntsville, AL); R. Michael Browder (Bristol, TN); Brook Marin (Huntsville, AL)
Assignees: Carina Technology, Inc.; Bristol Tech Essential Services
F24H9/2021F24D19/1051F24H1/0018F24H9/2014G05B13/026G05B15/02G05D23/1923G05F1/66H02J3/14H02J3/28H02J13/0006H02J13/0062H02J13/0075H02J2003/143Y02B30/762Y02B70/3225Y02B70/3275Y02B90/222Y02B90/2638Y02B90/2653Y04S20/12Y04S20/222Y04S20/244Y04S40/124Y04S40/126
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 10,168,073
App. No.
14/875,470
Granted
Jan 1, 2019
Kind
B2
Abstract

A system for shifting energy demand from on-peak time windows to off-peak time windows by using hot water heater load shifting, while providing the end user with the level of service (i.e., availability of hot water) according to the user's customary use described by service quality criteria. The shift is accomplished by a controller located at the end user establishment and in communication with a central control server. The controller monitors local water heater temperature and controls heating elements in accordance with a demand shift process commanded by the central control server. The controller may determine usage and remaining capacity for reporting back to the central control server. A volumetric capacity and usage determination is disclosed. The control server may select water heaters according to use and/or capacity. Further embodiments may regulate load dependent properties of the power including voltage, phase and/or frequency.

Claims (18)

1. A method for controlling a plurality of water heaters to vary a loading profile of a load on a power grid to affect a load dependent property of power on said power grid comprising:

a water heater control server receiving remaining volume capacity information and reserve volume capacity information from a plurality of water heaters connected to said power grid at separate customer locations;

generating historical usage pattern information for each water heater of said plurality of water heaters based on said remaining volume capacity information and said reserve volume capacity information, said reserve volume capacity information relating to a capability to deliver a reserve volume of hot water on immediate demand;

generating predicted usage pattern information based on said historical usage pattern information;

receiving present load demand information relating to a present load demand and desired load demand information by said water heater control server based on a power grid monitoring system monitoring said power grid, and a relationship between a load on said power grid and said load dependent property of said power;

said water heater control server communicating a control strategy to each said water heater of said plurality of water heaters, said control strategy comprising a temperature limit over time for each said water heater of said plurality of water heaters, said temperature limit over time based on said remaining volume capacity information, said reserve capacity information, said present load demand information, said predicted load demand information and said predicted usage pattern information; said control strategy allowing recovery when said remaining volume capacity is less than said reserve volume capacity.

2. The method in accordance with claim 1 , wherein said load dependent property is voltage.

3. The method in accordance with claim 1 , wherein said load dependent property is phase.

4. The method in accordance with claim 1 , wherein said load dependent property is frequency.

5. The method in accordance with claim 1 , wherein each said water heater of said plurality of water heaters is controlled in accordance with a hot water delivery quality criteria applied to said predicted usage pattern information specific to each said water heater.

6. The method in accordance with claim 1 , wherein said remaining volume capacity information and said reserve volume capacity information are based on a temperature measurement of an upper volume of water and a temperature measurement of a lower volume of water in each said water heater.

7. The method in accordance with claim 1 , further including said water heater control server sending a real time override of said control strategy in response to an immediate need for regulation of said present load demand.

8. The method in accordance with claim 1 , further including said water heater control server communicating a real time command to at least one water heater of said plurality of water heaters to override said control strategy and immediately connect or disconnect said at least one water heater to adjust said present load demand.

9. The method in accordance with claim 8 , wherein said command to override said control strategy comprises a command to override a requirement for controlling a temperature of a lower volume of said plurality of water heaters when said remaining capacity exceeds said reserve capacity, and to lower a temperature of said water heater regardless of the remaining capacity.

10. The method in accordance with claim 1 , further including: grouping said plurality of water heaters into a plurality of groups based on said historical usage pattern information and controlling said plurality of water heaters based on group control strategies for each said group of said plurality of groups based on said historical usage pattern information.

11. The method in accordance with claim 1 , wherein said control strategy comprises shifting said load from a peak demand interval to an off peak demand interval.

12. The method in accordance with claim 11 , wherein said control strategy comprises shifting said load to a minimum demand interval.

13. The method in accordance with claim 1 , wherein said control strategy is based on a total remaining energy available to command from said plurality of water heaters, said remaining energy available to command based on a difference between said remaining volume capacity and said reserve volume capacity.

Assignments (2)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded May 1, 2018
From: BROWDER, R. MICHAEL
To: BRISTOL TENNESSEE ESSENTIAL SERVICES
Reel/Frame 045682/0499 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Apr 25, 2018
From: HARBIN, BENJAMIN F., III; HOLLAND, CECIL RAY, JR.; TOTH, ROBERT J.; O'NEIL, ADRIAN; SANSOM, MICHAEL SCOTT; MARIN, BROOK
To: CARINA TECHNOLOGY, INC.
Reel/Frame 045631/0558 →
Continuity (5)
Continuation In Part 14320604 · Jun 30, 2014
Continuation 13526497 · Jun 18, 2012
Continuation 12493086 · Jun 26, 2009
Provisional Application 61077235 · Jul 1, 2008
Related Publication 20160216007A1 · Jul 28, 2016