IP Library Granted Patent US 11,624,480
Granted Patent B2
US 11,624,480 · App. 17/054,528 · Granted Apr 11, 2023

Petroleum production process system and method of operation

Inventors: Anders Lauvdal (Oslo, NO); Tylar Paul Bunger (Nittedal, NO)
Assignee: AKER SOLUTIONS AS
F17D3/10E21B43/01
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 11,624,480
App. No.
17/054,528
Granted
Apr 11, 2023
Kind
B2
Abstract

A process system includes a process module, an upstream pipe, a downstream pipe, an inlet pipe with an inlet isolation valve, an outlet pipe with a discharge isolation valve, a bypass with a bypass isolation valve, and a drainage line with a valve. The process module has an inlet, an outlet, and a drainage outlet. The inlet pipe fluidically connects the inlet of the process module to the upstream pipe. The outlet pipe fluidically connects the outlet of the process module to the downstream pipe. The bypass fluidly connects the upstream pipe and the downstream pipe via the bypass isolation valve. The drainage line fluidly connects the drainage outlet of the process module to the downstream pipe via the valve.

Claims (33)

1. A process system comprising:

a process module comprising an inlet, an outlet, and a drainage outlet;

an upstream pipe;

a downstream pipe;

an inlet pipe comprising an inlet isolation valve, the inlet pipe fluidically connecting the inlet of the process module to the upstream pipe;

an outlet pipe comprising a discharge isolation valve, the outlet pipe fluidically connecting the outlet of the process module to the downstream pipe;

a bypass comprising a bypass isolation valve, the bypass fluidly connecting the upstream pipe and the downstream pipe via the bypass isolation valve; and

a drainage line comprising a valve, the drainage line fluidly connecting the drainage outlet of the process module to the downstream pipe via the valve,

wherein,

the valve is a first valve,

the drainage line further comprises a second valve, and

the drainage line permits a fluid flow from the drainage outlet of the process module to the upstream pipe via the second valve via the drainage line being connected either,

directly to the upstream pipe, or

to the upstream pipe via a direct connection to the inlet pipe upstream of the inlet isolation valve, or

to the upstream pipe via a direct connection to the bypass upstream of the bypass isolation valve.

2. The process system as recited in claim 1 , wherein the bypass further comprises a flow restriction element.

3. The process system as recited in claim 2 , wherein the flow restriction element is a controllable flow restriction element operable to adjust a fluid flow rate therethrough.

4. The process system as recited in claim 1 , wherein the process system is arranged subsea.

5. The process system as recited in claim 1 , wherein the process system is arranged on an offshore platform.

6. The process system as recited in claim 1 , further comprising:

a conduit comprising a third valve for controlling a fluid flow through the conduit, the conduit fluidly connecting the downstream pipe with the inlet of the process module.

7. A method of draining the process module arranged in the process system as recited in to claim 6 , the method comprising simultaneously:

maintaining the bypass isolation valve, the inlet isolation valve, and the discharge isolation valve as closed;

flowing a gas from the downstream pipe to the inlet of the process module via the conduit; and

flowing a liquid from the drainage outlet of the process module to the upstream pipe via the drainage line.

8. A method of draining the process module arranged in the process system as recited in claim 1 , the method comprising simultaneously:

flowing a production fluid from the upstream pipe to the downstream pipe via the bypass;

flowing a gas from the upstream pipe to the inlet of the process module via the inlet pipe; and

flowing a liquid from the drainage outlet of the process module to the downstream pipe via the drainage line.

9. A method of draining the process module arranged in the process system as recited in claim 1 , the method comprising simultaneously:

maintaining the bypass isolation valve and the discharge isolation valve as closed;

flowing a gas from the upstream pipe to the inlet of the process module via the inlet pipe; and

flowing a liquid from the drainage outlet of the process module to the downstream pipe via the drainage line.

Assignments (2)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Dec 12, 2025
From: AKER SOLUTIONS AS
To: ONESUBSEA AS
Reel/Frame 073197/0623 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Nov 11, 2020
From: LAUVDAL, ANDERS, MR.; BUNGER, TYLAR PAUL, MR.
To: AKER SOLUTIONS AS
Reel/Frame 054329/0785 →
Priority Claims (1)
NO 20180680 · May 14, 2018 · national
Continuity (1)
Related Publication 20210116075A1 · Apr 22, 2021