Construction method and arrangement for carrying out a construction project

Inventor: Thomas Bauer (Schrobenhausen, DE)
Assignee: BAUER Spezialtiefbau GmbH
G06Q50/08E02D7/00E02D13/06E02D2600/10
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 12,700,049
App. No.
18/260,535
Filed
Jul 6, 2023
Granted
Aug 4, 2026
Kind
B2
Art Unit
2119
USPC
700/95
Abstract

The invention relates to a construction method and an arrangement for carrying out a construction project involving the production of several foundation elements on a construction site by means of at least one construction apparatus, wherein based on information on starting conditions, in particular on the ground composition, and the at least one construction apparatus as well as specifications for the construction project with the foundation elements to be produced a method sequence with determination of manufacturing parameters for each foundation element to be produced is defined in a computer unit, on the basis of the defined method sequence with the defined manufacturing parameters the production of at least one foundation element is started, during the method sequence actual data are recorded when producing the foundation elements and supplied to the computer unit, the computer unit compares the recorded actual data with target data for the defined method sequence and in the case of a relevant deviation of the actual data from the target data a changed method sequence with changed manufacturing parameters and/or new target data for the foundation elements still to be produced is ascertained by the computer unit and forwarded to the at least one construction apparatus.

Claims (16)

1 . A construction method for carrying out a construction project involving construction of foundation elements on a construction site by means of at least one construction apparatus, the construction method comprising:

storing in a memory specifications for the foundation elements of the construction project, manufacturing parameters of the at least one construction apparatus for constructing each foundation element among the foundation elements, and a construction schedule for constructing the foundation elements;

determining a deviation between actual data of a construction time of a foundation element among the foundation elements by the at least one construction apparatus according to a specification of the foundation element under the manufacturing parameters with target data for the construction time of the foundation element; and

determining new manufacturing parameters for the at least one construction apparatus to construct all foundation elements still to be constructed based on the deviation and the construction schedule,

wherein the at least one construction apparatus includes a drilling apparatus, the manufacturing parameters include a drilling speed of the drilling apparatus, a torque of the drilling apparatus, a feed force of the drilling apparatus, and a feed speed of the drilling apparatus, and

the new manufacturing parameters include a new drilling speed of the drilling apparatus, a new torque of the drilling apparatus, a new feed force of the drilling apparatus, and a new feed speed of the drilling apparatus.

2 . The construction method according to claim 1 , wherein

constructing each foundation element includes drilling with the drilling apparatus and cutting with a diaphragm wall cutter.

3 . The construction method according to claim 1 , further comprising recording the actual data by at least one sensor means on the at least one construction apparatus and/or by at least one stand-alone sensor means which is independent from a construction apparatus.

4 . The construction method according to claim 1 , wherein

the foundation elements include piles, diaphragm wall segments, retaining and cut-off walls, dams, sealing bases, compacted ground regions, ground anchors and/or sheet piles.

5 . The construction method according to claim 1 , wherein

the at least one construction apparatus includes diaphragm wall grabs, vibrators and/or mechanical impact devices including diesel hammers and hydraulic hammers.

6 . The construction method according to claim 1 , further comprising:

determining an actual ground composition of the construction site; and

determining the new manufacturing parameters based on the actual ground composition.

Assignments (1)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jul 19, 2023
From: BAUER, THOMAS
To: BAUER SPEZIALTIEFBAU GMBH
Reel/Frame 064312/0766 →
Priority Claims (1)
EP 21164873 · Mar 25, 2021 · regional
Continuity (1)
Related Publication 20240054577A1 · Feb 15, 2024
References Cited (16)
US 7429148B2 · Verstraeten · 2008 [cited by examiner]
US 8684108B2 · Turner · 2014 [cited by examiner]
US 10872302B2 · Selvaraj · 2020 [cited by examiner]
US 11280173B1 · Buerger · 2022 [cited by examiner]
US 11466420B2 · Stengl · 2022 [cited by examiner]
US 20130155058A1 · Golparvar-Fard · 2013 [cited by examiner]
US 20140219730A1 · Coupland · 2014 [cited by examiner]
US 20180012125A1 · Ladha · 2018 [cited by examiner]
US 20190325089A1 · Golparvar-Fard · 2019 [cited by examiner]
EP 3296467A1 · 2018 [cited by applicant]
EP 3299523A1 · 2018 [cited by applicant]
EP 3569769A1 · 2019 [cited by applicant]
EP 3613903A1 · 2020 [cited by applicant]
EP 3533932B1 · 2020 [cited by examiner]
International Preliminary Report on Patentability (Chapter II) issued in PCT/EP2022/056492; completed Nov. 15, 2022. [cited by applicant]
International Search Report issued in PCT/EP2022/056492; mailed Jun. 21, 2022. [cited by applicant]