Construction method for prestressed concrete girder bridges

Assignees: BNG Consultant Co., Ltd.; Daewoo E&C., Ltd.; Korea Infrastructure Safety & Technology Corporation
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 7,373,683
App. No.
10/555,927
Granted
May 20, 2008
Kind
B2
Abstract

A construction method for simple bridges or continuous bridges using prestressed concrete girder (PSC girder) and precast slabs (PSC slabs) where prestress is applied to the lower portion of the center of the girder. bridges of low clearance and long span are constructed by preventing a loss of prestress due to load of the slabs and relieving excessive compression force generated on the upper edge portion of the center of the girder during the construction of the bridge.

Claims (12)

1. A construction method for prestressed concrete (PSC) girder bridges comprising the steps of:

providing a PSC girder with at least first and second tendons;

tensing the first tendon and locating the PSC girder spanning between bridge seating devices;

gradually tensing the second tendon while arranging precast slabs at regular intervals on a top surface of the PSC girder;

compounding the precast slabs and PSC girder using a filler material; and

installing additional dead load on the precast slabs.

2. A construction method according to claim 1 , including locating the second tendon in the PSC girder after locating the PSC girder between the bridge seating devices.

3. A construction method according to claim 1 or 2 , including a sheath in the PSC girder, wherein the second tendon is located in the sheath.

4. A construction method according to claim 3 , including providing a plurality of adjacent PSC girders having a space therebetween on bridge seating devices and locating the second tendon in the adjacent PSC girders.

5. A construction method according to claim 4 , including pouring a concrete connection part in the space between the adjacent PSC girders.

6. The construction method for PSC continuous girder bridges according to claim 5 , wherein when the concrete for the connection parts is poured, the compounding for slabs is simultaneously poured adjacent to continuous spot portions, wherein compression stress is applied to the slabs adjacent to the continuous spot portion during the second tensing of the second tendon.

7. The construction method for PSC continuous girder bridges according to claim 5 , wherein at least some of the first tensing of the first tendon is applied to portions of the PSC girder where static moment is applied wherein excessive compression stress is prevented from being generated on a lower edge portion of the PSC girder adjacent to a continuous spot portion when load is applied to the girder.

Assignments (1)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Nov 8, 2005
From: MOON, SUNGHEE
To: BNG CONSULTANT, CO., LTD. (33.33%); DAEWOO E&C CO., LTD. (33.33%); KOREA INFRASTRUCTURE SAFETY & TECHNOLOGY CORPORATION (33.33%)
Reel/Frame 017901/0326 →
Priority Claims (1)
KR 10-2003-0031356 · May 16, 2003 · national
Continuity (1)
Related Publication 20070056123A1 · Mar 15, 2007