Construction method for girder in bridge, crane for pulling up girder, vehicle for carring girder, and girder used for the same

Assignee: Samsung Corporation
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,166,596
App. No.
12/133,974
Granted
May 1, 2012
Kind
B2
Abstract

A construction method for a girder in a bridge in which a plurality of piers are installed in an interval in a longitudinal direction of the bridge, a plurality of copings are installed on the piers, and a plurality of girders respectively installed between the piers are installed on the copings. The method comprises the steps of: installing at least one temporary girder on a front coping of the copings and a rear coping adjacent to the rear coping of the copings; installing a crane for pulling up a girder having a girder pulling up space therein guided by the temporary girder; and providing with a girder by a pre-cast method so as to install a girder on the front coping and the rear coping.

Claims (26)

1. A construction method for a girder in a bridge in which a plurality of piers are installed in an interval in a longitudinal direction of the bridge, and a plurality of copings are installed on the piers, the method comprising the steps of:

installing at least one temporary girder between a first coping and a second coping adjacent to the first coping;

installing a crane between the first and second copings, the crane including a girder pulling up space therein;

moving a vehicle loaded with a girder into the girder pulling up space of the crane, the vehicle moving on and along the temporary girder;

pulling up the girder by the crane;

drawing out the vehicle backward from the girder pulling up space;

moving the temporary girder to between the second coping and a third coping adjacent to the second coping; and

settling the girder onto the first and second copings,

wherein the steps of drawing out the vehicle, moving the temporary girder and settling the girder are performed in the described order.

2. The construction method for a girder in a bridge of claim 1 , further comprising the step of:

moving and installing the crane between the second and third copings, the crane being guided by the settled girded and the temporary girder, after the step of settling the girder.

3. A construction method for a girder in a bridge in which a plurality of piers are installed in an interval in a longitudinal direction of the bridge, and a plurality of copings are installed on the piers, the method comprising the steps of:

installing a pair of first and second temporary girders between a first coping and a second coping adjacent to the first coping;

installing a crane between the first and second copings, the crane including a girder pulling up space therein;

moving a vehicle loaded with a first girder into the girder pulling up space of the crane, the vehicle moving on and along the first and second temporary girders;

pulling up the first girder using the crane;

drawing out the vehicle backward from the girder pulling up space;

moving the first temporary girder to between the second coping and a third coping adjacent to the second coping;

settling the first girder onto the first and second copings using the crane, wherein the steps of drawing out the vehicle, moving the first temporary girder and settling the first girder are performed in the described order;

moving the vehicle loaded with a second girder into the girder pulling up space of the crane, the vehicle moving on and along the settled first girder and the second temporary girder;

pulling up the second girder using the crane;

drawing out the vehicle backward from the girder pulling up space;

moving the second temporary girder to between the second coping and the third coping; and

settling the second girder onto the first and second copings, wherein the steps of drawing out the vehicle, moving the second temporary girder and settling the second girder are performed in the described order.

4. The construction method for a girder in a bridge of claim 3 , further comprising the step of:

moving and installing the crane between the second and third copings, the crane being guided by the settled girders and the temporary girders, after the step of settling the girder.

Assignments (3)
CORRECTIVE ASSIGNMENT TO CORRECT THE RECEIVING PARTY ADDRESS PREVIOUSLY RECORDED AT REEL: 036675 FRAME: 0552. ASSIGNOR(S) HEREBY CONFIRMS THE MERGER AND CHANGE OF NAME Recorded Nov 9, 2015
From: SAMSUNG C&T CORPORATION; CHEIL INDUSTRIES INC.
To: SAMSUNG C&T CORPORATION
Reel/Frame 037072/0300 →
MERGER AND CHANGE OF NAME Recorded Sep 24, 2015
From: SAMSUNG C&T CORPORATION; CHEIL INDUSTRIES INC.
To: SAMSUNG C&T CORPORATION
Reel/Frame 036675/0552 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jun 5, 2008
From: KANG, DONG-OK; YOON, MAN-GEUN; SHIN, HYUN-YANG; KIM, YEONG-SEON
To: SAMSUNG CORPORATION
Reel/Frame 021055/0072 →
Priority Claims (1)
KR 10-2007-0054964 · Jun 5, 2007 · national
Continuity (1)
Related Publication 20080301889A1 · Dec 11, 2008