IP Library Granted Patent US 8,433,547
Granted Patent B2
US 8,433,547 · App. 12/630,035 · Granted Apr 30, 2013

System and method for analyzing nonstandard facility operations within a data center

Inventors: Mikkel Dalgas (Hejls, DK); Anders Thorbjoern Jensen (Jelling, DK)
Assignee: Schneider Electric IT Corporation
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,433,547
App. No.
12/630,035
Granted
Apr 30, 2013
Kind
B2
Abstract

A computer implemented method and a data center management appliance for simulating nonstandard operation of an element of a data center is provided. The method includes acts of determining a one data center resource affected by a data center element, selecting a simulator from a plurality of simulators based on the data center resource and the data center element and generating a impact analysis of the nonstandard operation of the data center element using the simulator. The data center management appliance includes a network interface, a memory and a controller coupled to the network interface and the memory. The controller is configured to determine a data center resource affected by a data center element, select a simulator from a plurality of simulators based on the data center resource and the data center element and generate a impact analysis of nonstandard operation of the data center element using the first simulator.

Claims (44)

1. A method for simulating, using a computer system including memory and at least one processor coupled to the memory, nonstandard operation of an element of a data center, the method comprising:

determining, by the computer system, at least first one data center resource affected by at least one first data center element;

selecting, by the computer system, at least one first simulator from a plurality of different simulators based at least in part on the at least one first data center resource and the at least one first data center element; and

generating, by the computer system, a first impact analysis of the nonstandard operation of the at least one first data center element using the at least one first simulator, wherein generating the analysis includes identifying at least one second data center element affected by the nonstandard operation of the at least one first data center element.

2. The method according to claim 1 , wherein determining the at least one first data center resource includes receiving configuration management information from a database of benchmarks calculated at least in part on modeled information and at least in part on measurements taken during operation of the data center.

3. The method according to claim 1 , wherein selecting the at least one first simulator includes selecting at least two simulators and generating the impact analysis includes generating an impact analysis that spans at least two data center resources.

4. The method according to claim 1 , wherein selecting the at least one first simulator from the plurality of simulators includes selecting the at least one first simulator from a plurality of simulators including at least one of a cooling simulator and a power simulator.

5. The method according to claim 1 , wherein generating the first impact analysis includes:

generating a list of critically impacted data center elements; and

generating a list of data center elements with affected redundancy.

6. The method according to claim 5 , further comprising:

determining at least one second data center resource affected by at least one third data center element identified in the list of critically impacted data center elements;

selecting at least one second simulator from the plurality of simulators based at least in part on the at least one second data center resource and the at least one third data center element; and

generating a second impact analysis of nonstandard operation of the at least one third data center element using the at least one second simulator.

7. The method according to claim 1 , further comprising providing the impact analysis to an external entity.

8. The method according to claim 7 , wherein providing the impact analysis to the external entity includes providing the impact analysis to an external system via a system interface.

9. The method according to claim 7 , wherein providing the impact analysis to the external entity includes providing the impact analysis to a user via a user interface.

10. A data center management appliance comprising:

a network interface;

a memory; and

a controller coupled to the network interface and the memory and configured to:

determine at least one first data center resource affected by at least one first data center element;

select at least one first simulator from a plurality of different simulators based at least in part on the at least one first data center resource and the at least one first data center element; and

generate a first impact analysis of nonstandard operation of the at least one first data center element using the at least one first simulator, the first impact analysis identifying at least one second data center element affected by the nonstandard operation of the at least one first data center element.

11. The data center management appliance according to claim 10 , wherein the controller configured to determine the at least one first data center resource is further configured to receive configuration management information from a database of benchmarks calculated at least in part on modeled information and at least in part on measurements taken during operation of the data center.

12. The data center management appliance according to claim 10 , wherein the controller configured to select the at least one first simulator and generate the impact analysis is further configured to select at least two simulators and generate an impact analysis that spans at least two data center resources.

13. The data center management appliance according to claim 10 , wherein the controller configured to select the at least one first simulator from the plurality of simulators is further configured to select the at least one first simulator from a plurality of simulators including at least one of a cooling simulator and a power simulator.

14. The data center management appliance according to claim 10 , wherein the controller configured to generate the first impact analysis is further configured to:

generate a list of critically impacted data center elements; and

generate a list of data center elements with affected redundancy.

15. The data center management appliance according to claim 14 , wherein the controller is further configured to:

determine at least one second data center resource affected by at least one third data center element identified in the list of critically impacted data center elements;

select at least one second simulator from the plurality of simulators based at least in part on the at least one second data center resource and the at least one third data center element; and

generate a second impact analysis using the at least one second simulator.

16. The data center management appliance according to claim 10 , wherein the controller is further configured to provide the impact analysis to an external entity.

17. The data center management appliance according to claim 16 , wherein the controller configured to provide the impact analysis to the external entity is further configured to provide the impact analysis to an external system via a system interface.

18. The data center management appliance according to claim 16 , wherein the controller configured to provide the impact analysis to the external entity is further configured to provide the impact analysis to a user via a user interface.

19. A data center management appliance comprising:

a network interface;

a memory; and

means for analyzing, for a plurality of data center resources, an impact of nonstandard operation of at least one first data center element, the means for analyzing including:

means for identifying at least one second data center element affected by the nonstandard operation of the at least one first data center element; and

means for selecting at least one first simulator from a plurality of different simulators based at least in part on the at least one first data center element and at least one first data center resource affected by the at least one first data center element.

20. The data center management appliance according to claim 19 , wherein the means for analyzing includes a means for analyzing at least one of cooling and power.

Assignments (2)
CHANGE OF NAME Recorded Mar 21, 2013
From: AMERICAN POWER CONVERSION CORPORATION
To: SCHNEIDER ELECTRIC IT CORPORATION
Reel/Frame 030062/0766 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Feb 5, 2010
From: DALGAS, MIKKEL; JENSEN, ANDERS THORBJOERN
To: AMERICAN POWER CONVERSION CORPORATION
Reel/Frame 023903/0904 →
Continuity (1)
Related Publication 20110137713A1 · Jun 9, 2011