Method of controlling machines at a worksite

Inventors: Liqun Chi (Peoria, IL); Sanat A. Talmaki (Peoria, IL); Paul T. Corcoran (Washington, IL); Scott A. Leman (Eureka, IL); Brad L. Holsapple (Metamora, IL); Mark W. Whiting (Peur, IL); Allen J. DeClerk (Princeton, IL)
Assignee: Caterpillar Inc.
E02F9/2054E02F9/262G05B15/02G06F3/0484G06F17/30477
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 9,822,509
App. No.
15/143,985
Granted
Nov 21, 2017
Kind
B1
Abstract

A method of controlling machines for performing operations at a worksite is disclosed. The method includes receiving pre-construction terrain data, design terrain data, and resource data and then defining a plurality of constraints based on the data. Operations of the machines are simulated based on the data. The method includes estimating process variables associated with the operations and defining and scheduling tasks to be performed by the machines. The method includes collecting real time data from the worksite and updating the estimated process variables and the scheduled tasks of the machines based on the collected real time data. Instructions are then provided to the machines for executing the tasks.

Claims (39)

1. A method of controlling machines for performing operations at a worksite, the method comprising:

receiving, by a control system, pre-construction terrain data associated with the worksite;

receiving, by the control system, design terrain data associated with the worksite;

receiving, by the control system, resource data associated with the machines;

defining a plurality of constraints associated with the operations based on the pre-construction terrain data, the design terrain data, and the resource data;

simulating the operations of the machines at the worksite based on the pre-construction terrain data, the design terrain data, and the resource data;

estimating process variables associated with the operations based on the simulation of the operations and the plurality of constraints;

collecting real time data associated with the operations performed at the worksite using a communication medium, wherein the real time data is one of an amount of material transferred at the worksite, performance details of each of the machines deployed at the worksite, and data obtained from a worksite survey;

updating the estimated process variables associated with the operations of the machines based on the collected real time data; and

providing, via a communication medium, instructions to the machines to execute scheduled tasks.

2. The method of claim 1 , wherein the process variables include tasks, task schedule, and required resources.

3. The method of claim 1 , wherein the constraints include one of a project budget, a project schedule, and available resources.

4. The method of claim 1 , wherein the constraints are received from a user interface module.

5. The method of claim 1 , wherein the constraints are weighted constraints.

6. The method of claim 1 , wherein updated process variables are received from a user interface module.

7. The method of claim 1 , wherein updated process variables are provided to a user interface module for assessment.

8. The method of claim 1 , wherein additional tasks are received from a user interface module.

9. The method of claim 1 , wherein the real time data is subject to data preparation before the estimated tasks and schedule are updated.

10. The method of claim 1 , wherein the simulation is further based on a volume of material to be moved.

11. A system for controlling machines for performing operations at a worksite, the system comprising:

a control system configured to:

receive said pre-construction terrain data from a database;

receive said design terrain data from a database;

receive resource data from a database;

define a plurality of constraints associated with the operations based on the pre-construction terrain data, the design terrain data, and the resource data;

simulate the operations of the machines at the worksite based on the pre-construction terrain data , the design terrain data, and the resource data;

estimate process variables associated with the operations based on the simulation of the operations and the plurality of constraints;

collect real time data associated with the operations performed at the worksite using a communication medium, wherein the real time data is one of an amount of material transferred at the worksite, performance details of each of the machines deployed at the worksite, and data obtained from a worksite survey;

update the estimated process variables associated with the operations of the machines based on the collected real time data; and

provide instructions, via a communication medium, to the machines to execute scheduled tasks.

12. The system of claim 11 , wherein the process variables include tasks, task schedule, and required resources.

13. The system of claim 11 , wherein the constraints include one of a project budget, a project schedule, and available resources.

14. The system of claim 11 , wherein the constraints are received from a user interface module.

15. The system of claim 11 , wherein the constraints are weighted constraints.

16. The system of claim 11 , wherein updated process variables are received from a user interface module.

17. The system of claim 11 , wherein updated process variables are provided to a user interface module for assessment.

18. The system of claim 11 , wherein additional tasks are received from a user interface module.

19. The system of claim 11 , wherein the real time data is subject to data preparation before the estimated tasks and schedule are updated.

20. The system of claim 11 , wherein the simulation is further based on a volume of material to be moved.

Assignments (2)
CORRECTIVE ASSIGNMENT TO ADD INVENTOR'S JAMES: MARK W. WHITING AND ALLEN J. DECLERK DATA PREVIOUSLY RECORDED ON REEL 038435 FRAME 0766. ASSIGNOR(S) HEREBY CONFIRMS THE ASSIGNMENT. Recorded Aug 7, 2017
From: CHI, LIQUN; TALMAKI, SANAT A.; CORCORAN, PAUL T.; LEMAN, SCOTT A; HOLSAPPLE, BRAD L.; WHITING, MARK W.; DECLERK, ALLEN J.
To: CATERPILLAR INC.
Reel/Frame 043458/0320 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded May 2, 2016
From: CHI, LIQUN; TALMAKI, SANAT A.; CORCORAN, PAUL T.; LEMAN, SCOTT A.; HOLSAPPLE, BRAD L.
To: CATERPILLAR INC.
Reel/Frame 038435/0766 →