IP Library Granted Patent US 9,472,954
Granted Patent B2
US 9,472,954 · App. 14/028,620 · Granted Oct 18, 2016

Generator dispatching or load shedding control method and system for microgrid applications

Inventors: Damrongrit Piyabongkarn (Medina, MN); Edward F. Buck (Waldo, WI); Steven A. Dimino (Wauwatosa, WI)
Assignee: EATON CORPORATION
H02J3/38H02J3/04H02J3/32H02J3/381H02J3/382H02J3/46Y02E70/30Y10T307/305Y10T307/367Y10T307/718
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 9,472,954
App. No.
14/028,620
Granted
Oct 18, 2016
Kind
B2
Abstract

A microgrid power generation system includes a plurality of generators having a plurality of different rated capacities and a plurality of distribution nodes, at least some of the distribution nodes being powered by the generators. A grid is formed by the distribution nodes, the grid includes a system frequency. A plurality of loads are powered by the grid through the distribution nodes, the loads have a power demand. A processor includes a plurality of efficiency bands, each of the efficiency bands being for a corresponding one of the generators and including a plurality of generator switching points based upon droop of the system frequency and the power demand of the loads. The processor is structured to operate the generators and the loads under transient conditions based upon the efficiency bands.

Claims (34)

1. A generator dispatching control method for a microgrid, said method comprising:

employing a plurality of generators having a plurality of different rated capacities;

employing a plurality of distribution nodes;

powering at least some of said distribution nodes by said generators;

forming a grid by said distribution nodes, said grid including a system frequency;

powering a plurality of loads by said grid through said distribution nodes, said loads having a power demand;

operating by a processor said generators and said loads under transient conditions based upon a plurality of efficiency bands; and

employing each of said efficiency bands for a corresponding one of said generators, each of said efficiency bands including a plurality of generator switching points based upon droop of said system frequency and the power demand of said loads.

2. The generator dispatching control method of claim 1 further comprising:

powering at least some of said distribution nodes by an energy storage system.

3. The generator dispatching control method of claim 2 further comprising:

dynamically modifying said efficiency bands based on availability of said energy storage system.

4. The generator dispatching control method of claim 2 further comprising:

supporting by said energy storage system, based upon said efficiency bands, at least one of the different rated capacities of at least one of said generators; and

delaying starting of another one of said generators, when said loads exceed the at least one of the different rated capacities of said at least one of said generators.

5. The generator dispatching control method of claim 2 further comprising:

employing as said energy storage system an energy storage and a DC/AC inverter or battery interface module.

6. The generator dispatching control method of claim 2 further comprising:

employing an extended efficiency band operatively associated with said energy storage system; and

automatically adjusting thresholds of said extended efficiency band to depend on a state of charge of said energy storage system.

7. A microgrid power generation system comprising:

a plurality of generators having a plurality of different rated capacities;

a plurality of distribution nodes, at least some of said distribution nodes being powered by said generators;

a grid formed by said distribution nodes, said grid including a system frequency;

a plurality of loads powered by said grid through said distribution nodes, said loads having a power demand; and

a processor including a plurality of efficiency bands, each of said efficiency bands being for a corresponding one of said generators and including a plurality of generator switching points based upon droop of said system frequency and the power demand of said loads, said processor being structured to operate said generators and said loads under transient conditions based upon said efficiency bands.

8. The microgrid power generation system of claim 7 wherein at least one of said distribution nodes is powered by an energy storage system.

9. The microgrid power generation system of claim 8 wherein said processor is further structured to cause at least one of said generators to operate at or close to a corresponding at least one of the different rated capacities, thereby simultaneously supplying said loads and charging said energy storage system, followed by turning off said generators and supplying said loads from said energy storage system.

10. The microgrid power generation system of claim 7 wherein said processor is further structured to provide a predetermined response delay for said system frequency to settle at a corresponding operating point before turning on one of said generators.

11. The microgrid power generation system of claim 7 wherein said processor is further structured to shed a number of said loads if the system frequency droops at a rate exceeding a predetermined value, and to reconnect a number of said number of loads following recovery of said system frequency.

12. The microgrid power generation system of claim 7 wherein said processor is further structured to adjust said efficiency bands, a number of thresholds, a number of frequency droop slopes and a number of delays.

13. The microgrid power generation system of claim 8 wherein said processor is further structured to provide a first normal state for said loads and a second state for said loads, said second state requiring less power than said first normal state, a first transition from said first normal state to said second state, and a second transition from said second state to said first normal state.

14. The microgrid power generation system of claim 13 wherein said processor is further structured to provide a third state for said loads, said third state requiring greater power than said first normal state, and a fourth inverter state; and wherein when said processor turns off said generators, said energy storage system supplies power to said loads.

15. The microgrid power generation system of claim 7 wherein said generators include a first generator having a first rated capacity of said different rated capacities and a second generator having a second rated capacity of said different rated capacities, said second rated capacity being two times greater than said first rated capacity; wherein said processor is further structured, when said second generator is turned on, to turn on the first generator when the power demand of said loads is 100% of the second rated capacity of said second generator, to turn off the first generator when the power demand of said loads is less than 100% of the second rated capacity of said second generator; wherein said processor is further structured, when said second generator is turned on, to turn on the first generator when the power demand of said loads is less than the first rated capacity of said first generator and, after a predetermined time, to turn off the second generator; and wherein said processor is further structured, when said second generator is turned off, to turn on the second generator when the power demand of said loads increases to the first rated capacity of said first generator.

Assignments (3)
CONFIRMATORY LICENSE Recorded May 13, 2020
From: EATON CORPORATION
To: UNITED STATES OF AMERICA AS REPRESENTED BY THE SECRETARY OF THE ARMY
Reel/Frame 052644/0866 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Apr 11, 2019
From: EATON CORPORATION
To: EATON INTELLIGENT POWER LIMITED
Reel/Frame 048855/0626 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Sep 17, 2013
From: PIYABONGKARN, DAMRONGRIT; BUCK, EDWARD F.; DIMINO, STEVEN A.
To: EATON CORPORATION
Reel/Frame 031219/0632 →
Continuity (2)
Provisional Application 61710905 · Oct 8, 2012
Related Publication 20140097683A1 · Apr 10, 2014