IP Library Granted Patent US 11,797,723
Granted Patent B2
US 11,797,723 · App. 17/140,527 · Granted Oct 24, 2023

Systems and methods for coordinating initiation, preparing, vetting, scheduling, constructing, and implementing a power plant implementation

Inventor: Lee Priest (Charlotte, NC)
Assignee: ETAK Systems, LLC
G06F30/13B64C39/024G06Q10/067G06Q10/06312G06Q10/06313G06Q10/103G06Q50/08G06T7/001G06T7/55B64U10/13B64U2101/30G06T2207/10032G06T2207/30108H04W16/18
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 11,797,723
App. No.
17/140,527
Granted
Oct 24, 2023
Kind
B2
Abstract

A method for scheduling construction of a power plant at a telecommunications site is disclosed. The method includes assessing the telecommunication site and the power plant. The method also includes obtaining data from the location utilizing one or more data capture techniques. The method also includes generating a model of the existing infrastructure and a model of the power plant and inserting the model of the power plant therein. The method further includes developing a draft schedule. The method also includes publishing the final schedule with the model of the power plant inserted into the model of the existing infrastructure.

Claims (31)

1. A method for scheduling construction of a power plant at a telecommunications site, the method comprising:

obtaining data utilizing one or more data capture techniques, the data including one or more of photos and videos of existing infrastructure at the telecommunications site selected to receive and interface with the power plant, wherein the one or more data capture techniques includes utilizing one or more of an Unmanned Aerial Vehicle (UAV), a satellite, a camera apparatus, and a telescoping apparatus for capturing the data;

generating a model of the existing infrastructure selected to receive and interface with the power plant;

generating a model of the power plant and inserting the model of the power plant into the model of the existing infrastructure;

developing a draft schedule comprising a matrix including an order of when each task for construction of the power plant is to be completed; and

publishing a final schedule with the model of the power plant inserted into the model of the existing infrastructure.

2. The method of claim 1 , wherein the data is associated with a location, and wherein the location is in at least one of a shelter, a cabinet housing, and supporting telecommunications equipment of the telecommunications site.

3. The method of claim 1 , wherein the revised schedule is based on schedule order conflicts and timing conflicts identified using the model.

4. The method of claim 1 , wherein the model of the power plant is generated based on construction documents of the power plant.

5. The method of claim 1 , further comprising:

vetting and testing the draft schedule for flow continuity and for viability of meeting deadlines outlined therein based on the model; and

generating a revised schedule from the draft schedule based on the vetting and testing of the draft schedule.

6. The method of claim 5 , wherein generating a revised schedule from the draft schedule based on vetting and testing of the draft schedule includes ensuring the revised schedule meets customer requirements.

7. The method of claim 5 , wherein one of the draft schedule and the revised schedule is provided to sub-contractors for further feedback and or testing.

8. The method of claim 5 , wherein the steps of vetting and testing the draft schedule for flow continuity and for viability of meeting deadlines outlined therein and generating the revised schedule from the draft schedule based on vetting and testing of the draft schedule are performed iteratively including receiving feedback from sub-contractors, ensuring the revised schedule meets customer requirements, revising the model, and testing the revised schedule against the revised model until a final schedule is determined.

9. A non-transitory computer-readable storage medium having computer readable code stored thereon for programming a computer for a power plant via steps comprising:

obtaining data utilizing one or more data capture techniques and utilizing the data for generating a model based thereon, the data including one or more of photos and videos of existing infrastructure at a telecommunications site selected to receive and interface with the power plant, wherein the one or more data capture techniques includes utilizing one or more of an Unmanned Aerial Vehicle (UAV), a satellite, a camera apparatus, and a telescoping apparatus for capturing the data;

generating a model of the existing infrastructure selected to receive and interface with the power plant;

generating a model of the power plant and inserting the model of the power plant into the model of the existing infrastructure;

developing a draft schedule comprising a matrix including an order of when each task for construction of the power plant is to be completed; and

publishing a final schedule with the model of the power plant inserted into the model of the existing infrastructure.

10. The non-transitory computer-readable storage medium of claim 9 , wherein the data is associated with a location, and wherein the location is in at least one of a shelter, a cabinet housing, and supporting telecommunications equipment of the telecommunications site.

11. The non-transitory computer-readable storage medium of claim 9 , wherein the revised schedule is based on schedule order conflicts and timing conflicts identified using the model.

12. The non-transitory computer-readable storage medium of claim 9 , wherein the model of the power plant is generated based on construction documents of the power plant.

13. The non-transitory computer-readable storage medium of claim 9 , wherein the steps further comprise:

vetting and testing the draft schedule for flow continuity and for viability of meeting deadlines outlined therein based on the model; and

generating a revised schedule from the draft schedule based on the vetting and testing of the draft schedule.

14. The non-transitory computer-readable storage medium of claim 13 , wherein generating a revised schedule from the draft schedule based on vetting and testing of the draft schedule includes ensuring the revised schedule meets customer requirements.

15. The non-transitory computer-readable storage medium of claim 13 , wherein one of the draft schedule and the revised schedule is provided to sub-contractors for further feedback and or testing.

16. The non-transitory computer-readable storage medium of claim 13 , the steps of vetting and testing the draft schedule for flow continuity and for viability of meeting deadlines outlined therein and generating the revised schedule from the draft schedule based on vetting and testing of the draft schedule are performed iteratively including receiving feedback from sub-contractors, ensuring the revised schedule meets customer requirements, revising the model, and testing the revised schedule against the revised model until a final schedule is determined.

17. The method of claim 1 , wherein generating the model of the power plant and inserting the model of the power plant into the model of the existing infrastructure includes generating and inserting digital 3D models of non-existing equipment into the model of the existing infrastructure, wherein the model of the existing infrastructure is a digital 3D model.

Assignments (4)
RELEASE OF SECURITY INTEREST Recorded Mar 24, 2026
From: KEYBANK NATIONAL ASSOCIATION, AS AGENT
To: ETAK SYSTEMS, LLC
Reel/Frame 074818/0664 →
PATENT SECURITY AGREEMENT Recorded Mar 20, 2026
From: ETAK SYSTEMS, LLC
To: AQUARIAN CREDIT FUNDING LLC, AS ADMINISTRATIVE AGENT AND COLLATERAL AGENT
Reel/Frame 075246/0859 →
PATENT SECURITY AGREEMENT Recorded Apr 22, 2021
From: ETAK SYSTEMS, LLC
To: KEYBANK NATIONAL ASSOCIATION
Reel/Frame 056003/0641 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jan 4, 2021
From: PRIEST, LEE
To: ETAK SYSTEMS, LLC
Reel/Frame 054799/0750 →
Continuity (18)
Continuation In Part 16881623 · May 22, 2020
Continuation In Part 16881565 · May 22, 2020
Continuation In Part 16881510 · May 22, 2020
Continuation In Part 16861537 · Apr 29, 2020
Continuation In Part 16750301 · Jan 23, 2020
Continuation In Part 15968131 · May 1, 2018
Continuation In Part 15926533 · Mar 20, 2018
Continuation In Part 15898695 · Feb 19, 2018
Continuation In Part 15235686 · Aug 12, 2016
Continuation In Part 15877555 · Jan 23, 2018
Continuation In Part 15815786 · Nov 17, 2017
Continuation In Part 15675930 · Aug 14, 2017
Continuation In Part 15283699 · Oct 3, 2016
Continuation In Part 15241239 · Aug 19, 2016
Continuation In Part 15168503 · May 31, 2016
Continuation In Part 15160890 · May 20, 2016
Continuation In Part 14685720 · Apr 14, 2015
Related Publication 20210150098A1 · May 20, 2021