IP Library Granted Patent US 7,565,831
Granted Patent B2
US 7,565,831 · App. 11/589,893 · Granted Jul 28, 2009

Production method of indentation curve and hardness test method

Assignee: National Institute for Materials Science
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 7,565,831
App. No.
11/589,893
Granted
Jul 28, 2009
Kind
B2
Abstract

A production method of an indentation curve is given, in which when an indentation curve showing a relationship between indentation force and indentation depth in a process of indenting an indenter into a surface of a sample is produced, a measurement range using an (i−n)th (here, i and n are natural numbers) measurement value as a reference is provided, and the indentation depth or indentation force is temporarily measured when the indentation force or indentation depth is gradually changed, respectively, and when a temporarily measurement value obtained by the temporarily measurement is out of the determination range, indentation depth at the relevant indentation force or indentation force at the relevant indentation depth is measured and set as an ith measurement value, or the temporarily measurement value is used as the ith measurement value.

Claims (26)

1. A production method of an indentation curve, when an indentation curve showing a relationship between indentation force and indentation depth in a process of indenting an indenter into a surface of a sample is produced, which comprises:

setting a determination range based on an (i−n)th (here, i and n are natural numbers) measurement value as a reference,

temporarily measuring a indentation depth or indentation force when the indentation force or indentation depth is gradually changed respectively, and

measuring the indentation depth at the relevant indentation force or indentation force at the relevant indentation depth when a temporary measurement value obtained by the temporarily measurement is out of the determination range to set it as an ith measurement value.

2. The production method of the indentation curve according to claim 1 , which comprises:

setting the determination range based on an (i−1)th (here, i is an natural numbers) measurement value as a reference.

3. The production method of the indentation curve according to claim 2 , which comprises:

using a temporarily measurement value as an ith measurement value when the temporarily measurement value obtained by the temporarily measurement is out of the determination range.

4. The production method of the indentation curve according to claim 3 , wherein measurement speed is increased by decreasing the number of measurement times at one temporarily measurement point.

5. The production method of the indentation curve according to claim 4 , wherein conversion speed is increased in the temporarily measurement by reducing accuracy of A/D conversion of the temporarily measurement value from an analog signal to a digital signal.

6. The production method of the indentation curve according to claim 3 , wherein conversion speed is increased in the temporarily measurement by reducing accuracy of A/D conversion of the temporarily measurement value from an analog signal to a digital signal.

7. The production method of the indentation curve according to claim 2 , wherein measurement speed is increased by decreasing the number of measurement times at one temporarily measurement point.

8. The production method of the indentation curve according to claim 7 , wherein conversion speed is increased in the temporarily measurement by reducing accuracy of A/D conversion of the temporarily measurement value from an analog signal to a digital signal.

9. The production method of the indentation curve according to claim 2 , wherein conversion speed is increased in the temporarily measurement by reducing accuracy of A/D conversion of the temporarily measurement value from an analog signal to a digital signal.

10. The production method of the indentation curve according to claim 2 , wherein indentation depth when indentation force is gradually changed is temporarily measured in a range where a change level in indentation force is large, and indentation force when indentation depth is gradually changed is temporarily measured in a range where a change level of the indentation depth is large.

11. The production method of the indentation curve according to claim 1 , which comprises:

using a temporarily measurement value as an ith measurement value when the temporarily measurement value obtained by the temporarily measurement is out of the determination range.

12. The production method of the indentation curve according to claim 11 , wherein measurement speed is increased by decreasing the number of measurement times at one temporarily measurement point.

13. The production method of the indentation curve according to claim 12 , wherein conversion speed is increased in the temporarily measurement by reducing accuracy of A/D conversion of the temporarily measurement value from an analog signal to a digital signal.

14. The production method of the indentation curve according to claim 11 , wherein conversion speed is increased in the temporarily measurement by reducing accuracy of A/D conversion of the temporarily measurement value from an analog signal to a digital signal.

15. The production method of the indentation curve according to claim 1 , wherein measurement speed is increased by decreasing the number of measurement times at one temporarily measurement point.

16. The production method of the indentation curve according to claim 15 , wherein conversion speed is increased in the temporarily measurement by reducing accuracy of A/D conversion of the temporarily measurement value from an analog signal to a digital signal.

17. The production method of the indentation curve according to claim 1 , wherein conversion speed is increased in the temporarily measurement by reducing accuracy of A/D conversion of the temporarily measurement value from an analog signal to a digital signal.

18. The production method of the indentation curve according to claim 1 , wherein indentation depth when indentation force is gradually changed is temporarily measured in a range where a change level in indentation force is large, and indentation force when indentation depth is gradually changed is temporarily measured in a range where a change level of the indentation depth is large.

19. The production method of the indentation curve according to claim 1 , wherein the determination range is in a circular, elliptic, or rectangular shape using an (i−1)th measurement point as a center.

20. A hardness test method, which comprises: obtaining hardness of a micro area of a sample into which the indenter is indented from one of the indentation curves of claim.

Assignments (1)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jan 12, 2007
From: MIYAHARA, KENSUKE
To: NATIONAL INSTITUTE FOR MATERIALS SCIENCE
Reel/Frame 018788/0665 →
Priority Claims (1)
JP 2005-316059 · Oct 31, 2005 · national
Continuity (1)
Related Publication 20070113628A1 · May 24, 2007