IP Library Granted Patent US 7,651,294
Granted Patent B2
US 7,651,294 · App. 11/732,388 · Granted Jan 26, 2010

Soil stabilization method

Assignee: Team Laboratory Chemical Corporation
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 7,651,294
App. No.
11/732,388
Granted
Jan 26, 2010
Kind
B2
Abstract

A method of use of a composition for soil stabilization is disclosed. The composition comprises a solution of soluble sodium silicate applied at the disclosed application rate to improve the load bearing capacity for a roadway. The method of the invention addresses the application of the disclosed composition to maximize stabilization of road beds.

Claims (41)

1. A method of soil stabilization for a road bed comprising:

providing soil stabilizer comprising 28-30 percent silicon dioxide by weight and 8.5-9.5 percent sodium oxide by weight in an aqueous solution;

applying the soil stabilizer to the road in three steps, the steps comprising:

(i) a first step of applying the soil stabilizer to the road bed at a rate of one gallon of the soil stabilizer per every 420-880 square yards of road surface;

(ii) a second step of applying a mixture of road bed material and the soil stabilizer to the road bed at a rate of one gallon of the soil stabilizer per every 50-80 square yards of road surface; and

(iii) a third step of applying the soil stabilizer to the road bed at a rate of one gallon of the soil stabilizer per every 360-700 square yards of road surface.

2. The method of claim 1 wherein the road bed is compacted after each of the steps of applying the soil stabilizer.

3. The method of claim 2 wherein the road bed is leveled before the first step of applying the soil stabilizer.

4. The method of claim 3 wherein the grade and slope of the road bed is finished before the third step of applying the soil stabilizer.

5. The method of claim 2 wherein the grade and slope of the road bed is finished before the third step of applying the soil stabilizer.

6. The method of claim 5 wherein the road bed is compacted after the third step of applying the soil stabilizer until the surface of the road bed is dry.

7. The method of claim 6 wherein the second step comprises applying the mixture of road bed material and the soil stabilizer in lifts of one to two inches in thickness and compacting the road bed after each application of the mixture.

8. The method of claim 7 wherein the soil stabilizer is diluted in a ratio of about one 55-gallon drum of the soil stabilizer per 5,000 gallons of water before the three application steps.

9. The method of claim 1 wherein the second step comprises applying the mixture of road bed material and the soil stabilizer in lifts of one to two inches in thickness and compacting the road bed after each application of the mixture.

10. The method of claim 1 wherein the providing step comprises providing a soil stabilizer comprising about 28.4 percent silicon dioxide by weight and about 8.7 percent sodium oxide by weight in an aqueous solution.

11. A method of soil stabilization for a road bed comprising:

providing a soil stabilizer comprising 28-30 percent silicon dioxide by weight and 8.5-9.5 percent sodium oxide by weight in an aqueous solution; and

applying the soil stabilizer to the road bed at a rate of 0.018-0.027 gallons of the soil stabilizer per square yard of road bed.

12. The method of claim 11 wherein the soil stabilizer is diluted in a ratio of about one 55-gallon drum of the soil stabilizer per 5,000 gallons of water before the steps.

13. The method of claim 12 wherein the step comprises applying the mixture of road bed material and the soil stabilizer in lifts of one to two inches in thickness and compacting the road bed after each application of the mixture.

14. The method of claim 13 wherein the providing step comprises providing a soil stabilizer comprising about 28.4 percent silicon dioxide by weight and about 8.7 percent sodium oxide by weight in an aqueous solution.

15. A method of soil stabilization for a road bed comprising:

providing a soil stabilizer comprising silicon dioxide and sodium oxide wherein the average weight ratio of silicon dioxide to sodium oxide is between 3.2 and 3.3;

applying the soil stabilizer to the road bed in three steps, the steps comprising:

(i) a first step of applying the soil stabilizer to the road bed at a rate of one pound of the soil stabilizer per every 95-210 square yards of road surface;

(ii) a second step of applying a mixture of road bed material and the soil stabilizer to the road bed at a rate of one pound of the soil stabilizer per every 12-20 square yards of road surface; and

(iii) a third step of applying the soil stabilizer to the road bed at a rate of one pound of the soil stabilizer per every 80-170 square yards of road surface.

16. The method of claim 15 wherein the soil stabilizer is diluted in water before the steps of applying the soil stabilizer.

17. The method of claim 15 wherein the second step comprises applying the mixture of road bed material and the soil stabilizer in lifts of one to two inches in thickness and compacting the road bed after each application of the mixture.

18. The method of claim 16 wherein the road bed is compacted after each of the steps of applying the soil stabilizer.

19. The method of claim 17 wherein the road bed is leveled before the first step of applying the soil stabilizer.

20. The method of claim 18 wherein the grade and slope of the road bed is finished before the third step of applying the soil stabilizer.

21. A kit for soil stabilization of a road bed comprising:

a soil stabilizer comprising 28-30 percent silicon dioxide by weight and 8.5-9.5 percent sodium oxide by weight in an aqueous solution; and

instructions for a method of application of the soil stabilizer to the road bed, the method comprising:

(i) a first step of applying the soil stabilizer to the road bed at a rate of one gallon of the soil stabilizer per every 420-880 square yards of road surface;

(ii) a second step of applying a mixture of road bed material and the soil stabilizer to the road bed at a rate of one gallon of the soil stabilizer per every 50-80 square yards of road surface; and

(iii) a third step of applying the soil stabilizer to the road bed at a rate of one gallon of the soil stabilizer per every 360-700 square yards of road surface.

22. A method of soil stabilization for a road bed comprising:

providing a soil stabilizer comprising 28-30 percent silicon dioxide by weight and 8.5-9.5 percent sodium oxide by weight in an aqueous solution; and

applying the soil stabilizer to the road bed at a rate of about 0.005 gallons of the soil stabilizer per square yard per inch thickness of road bed.

Assignments (5)
CORRECTIVE ASSIGNMENT TO CORRECT THE CORRECT THE ASSIGNEE NAME PREVIOUSLY RECORDED AT REEL: 019226 FRAME: 0642. ASSIGNOR(S) HEREBY CONFIRMS THE ASSIGNMENT. Recorded Dec 19, 2019
From: MAIER, TERRY L.
To: LAKER CHEMICAL, INC.
Reel/Frame 052002/0729 →
SECURITY INTEREST Recorded Oct 2, 2019
From: TEAM LABORATORY CHEMICAL, LLC
To: SUNFLOWER BANK, N.A.
Reel/Frame 050601/0358 →
INTELLECTUAL PROPERTY SECURITY AGREEMENT Recorded Oct 2, 2019
From: TEAM LABORATORY CHEMICAL, LLC
To: PLEXUS FUND IV-A, L.P., AS ADMINISTRATIVE AGENT
Reel/Frame 050611/0639 →
NUNC PRO TUNC ASSIGNMENT Recorded Sep 30, 2019
From: LAKER CHEMICAL, INC. (D/B/A "TEAM LABORATORY CHEMICAL CORPORATION", "TEAM LABORATORY CHEMICAL CORP." AND "TEAM LAB")
To: TEAM LABORATORY CHEMICAL, LLC
Reel/Frame 050562/0790 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Apr 30, 2007
From: MAIER, TERRY L.
To: TEAM LABORATORY CHEMICAL CORPORATION
Reel/Frame 019226/0642 →
Continuity (2)
Provisional Application 6078964000 · Apr 6, 2006
Related Publication 20070258768A1 · Nov 8, 2007