IP Library Granted Patent US 8,474,080
Granted Patent B2
US 8,474,080 · App. 13/059,933 · Granted Jul 2, 2013

Construction method of steel composition girder bridge

Inventors: Yong Joo Kim (Gwangju, KR); Jae Min Kim (Seoul, KR)
Assignees: Hyung Kyun Byun; Mi Young Lim; Yong Joo Kim
E01D21/06
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,474,080
App. No.
13/059,933
Granted
Jul 2, 2013
Kind
B2
Abstract

A construction method of a steel composite girder bridge includes installing steel girders on piers and forming shearing connectors on the steel girders at intervals of a predetermined distance, installing stagings and a first form for casting deck concrete in the steel girders, installing non-composite members in an upper flange of the steel girders to form each non-composite section of supporting points, installing a second form around each of the shearing connectors to form a shearing pocket, arranging sheath pipes in the supporting points and forming supporting point decks by casting and curing concrete, applying pre-stress to each section of the supporting point decks through the sheath pipes and performing a grouting process, forming span decks adjacent to the supporting point decks by casting and curing concrete in each span between the piers, and filling the shearing pockets with non-shrinkage mortar.

Claims (12)

1. A construction method of a steel composite girder bridge, the method comprising:

installing steel girders on piers and forming shearing connectors continuously on the steel girders at intervals of a predetermined distance;

installing stagings and a first form for casting deck concrete in the steel girders;

installing non-composite members in an upper flange of the steel girders to form each non-composite section of supporting points and installing a second form around each of the shearing connectors, wherein the second form forms a shearing pocket;

arranging sheath pipes in the supporting points and forming supporting point decks by casting and curing concrete;

applying pre-stress to each section of the supporting point decks through the sheath pipes and performing a grouting process;

forming span decks adjacent to the supporting point decks by casting and curing concrete in each span between the piers;

filling the shearing pockets with non-shrinkage mortar; and

forming a road after dismantling the stagings and the first and second forms, and forming protection walls.

2. The construction method according to claim 1 , wherein the non-composite members include adhesive sheet, vinyl, tape, fiber and grease.

3. The construction method according to claim 1 , wherein the pre-stress is applied when the concrete compressive strength of each section of the supporting point decks is equal to or greater than 28 Mpa.

4. The construction method according to claim 1 , wherein the steel composite girder bridge is an open-top girder type, a rectangular girder type, a plate girder type or a minor plate girder type.

Assignments (1)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded May 27, 2013
From: KIM, YONG JOO; KIM, JAE MIN
To: BYUN, HYUNG KYUN; LIM, MI YOUNG; KIM, YONG JOO
Reel/Frame 030489/0870 →
Priority Claims (1)
KR 10-2010-0008408 · Jan 29, 2010 · national
Continuity (1)
Related Publication 20120279000A1 · Nov 8, 2012