IP Library › Granted Patent US 8,511,013
Granted Patent B2
US 8,511,013 · App. 12/553,395 · Granted Aug 20, 2013

Wind turbine tower and system and method for fabricating the same

Inventor: Stefan Voss (Salzbergen, DE)
Assignee: General Electric Company
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,511,013
App. No.
12/553,395
Granted
Aug 20, 2013
Kind
B2
Abstract

A system and method for fabricating a wind turbine tower is provided. The method includes providing at least one fiber reinforced plastic (“FRP”) strand, embedding a first portion of the FRP strand into a first concrete segment, and embedding a second portion of the FRP strand into a second concrete segment such that a third portion of the FRP strand extends from the first concrete segment to the second concrete segment. The method further includes displacing at least one of the first concrete segment and the second concrete segment relative to the other such that a tension is applied to the third portion of the FRP strand.

Claims (9)

1. A wind turbine tower including a plurality of tower sections, at least one of said tower sections comprising:

a first concrete flange;

a second concrete flange formed separately from said first concrete flange;

a concrete wall formed separately from said first concrete flange and said second concrete flange, said concrete wall positioned between said first concrete flange and said second concrete flange; and

a fiber reinforced plastic (“FRP”) strand comprising a first portion embedded in said first concrete flange and having a first tension, a second portion embedded in said second concrete flange and having a second tension, and a third portion embedded in said concrete wall and having a third tension such that said first concrete flange and said second concrete flange are coupled to said concrete wall via said FRP strand, wherein at least one of the following conditions is satisfied: said first portion is directly bonded to said first concrete flange, said second portion is directly bonded to said second concrete flange, and said third portion is directly bonded to said concrete wall.

2. The wind turbine tower in accordance with claim 1 , wherein the third tension is different than the first tension and the second tension.

3. The wind turbine tower in accordance with claim 2 , wherein the first tension is substantially the same as the second tension.

4. The wind turbine tower in accordance with claim 1 , wherein at least one of said first concrete flange and said second concrete flange is fabricated from an ultra-high performance concrete (“UHPC”).

5. The wind turbine tower in accordance with claim 4 , wherein said concrete wall is fabricated from a concrete material comprising a composition that is different than said UHPC.

Assignments (2)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jul 27, 2010
From: GE WIND ENGERY GMBH
To: GENERAL ELECTRIC COMPANY
Reel/Frame 024744/0361 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Sep 3, 2009
From: VOSS, STEFAN
To: GE WIND ENERGY GMBH
Reel/Frame 023189/0976 →
Continuity (1)
Related Publication 20100132282A1 · Jun 3, 2010