IP Library › Granted Patent US 8,511,258
Granted Patent B2
US 8,511,258 · App. 12/019,451 · Granted Aug 20, 2013

Coal boiler and coal boiler combustion method

Inventors: Kenji Yamamoto (Hitachinaka, JP); Masato Handa (Mito, JP); Teruyuki Okazaki (Hitachiohta, JP); Kazumi Yasuda (Hitachi, JP); Osamu Ito (Hitachiohta, JP)
Assignee: Hitachi, Ltd.
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,511,258
App. No.
12/019,451
Granted
Aug 20, 2013
Kind
B2
Abstract

Disclosed is a coal boiler that makes it possible to reduce the height of the boiler and shorten the period of construction. The coal boiler includes a first furnace in which a combustion gas generated by burning coal and air ascends; a second furnace in which the combustion gas supplied from the first furnace flows downward; and a heat recovery area in which the combustion gas supplied from the second furnace flows upward.

Claims (38)

1. A coal boiler comprising:

a first furnace in which a combustion gas generated by burning coal and air ascends;

a second furnace in which the combustion gas supplied from the first furnace flows downward, the second furnace including a staged combustion after-air port; and

a heat recovery area in which the combustion gas supplied from the second furnace flows upward.

2. The coal boiler according to claim 1 , wherein a heat exchanger mounted in the heat recovery area is made of tubes; and wherein the spacing interval between the tubes constituting the heat exchanger is longer on the upstream side than on the downstream side.

3. The coal boiler according to claim 2 , further comprising:

a partition for dividing a combustion gas flow path in the heat recovery area into two.

4. The coal boiler according to claim 1 , further comprising:

a superheater that is provided for a roof wall of the second furnace.

5. The coal boiler according to claim 1 , further comprising:

a joint lower beam that is positioned between a rear wall of the first furnace and a front wall of the second furnace; and

an iron frame to which the joint lower beam is connected.

6. The coal boiler according to claim 1 , further comprising:

a water/steam flow path that allows steam or water flowing in a water wall tube constituting the first furnace to flow in a water wall tube constituting the second furnace, pass through a water-steam separator, and flow in a cage wall tube constituting the heat recovery area.

7. The coal boiler according to claim 6 , further comprising:

a water/steam flow path that supplies steam discharged from the cage wall tube to a roof wall tube constituting the first furnace.

8. The coal boiler according to claim 1 , further comprising:

a water/steam flow path that allows steam or water flowing in a water wall tube constituting the first furnace to flow in a cage wall tube constituting the heat recovery area, pass through a water-steam separator, and flow in a water wall tube constituting the second furnace.

9. The coal boiler according to claim 8 , further comprising:

a water/steam flow path that supplies steam discharged from the cage wall tube to a roof wall constituting the first furnace.

10. The coal boiler according to claim 1 , further comprising:

a water/steam flow path that supplies water to a water wall tube constituting the first furnace and a water wall tube constituting the second furnace, and allows the water to pass through a water-steam separator and flow in a cage wall tube provided for the heat recovery area.

11. The coal boiler according to claim 1 , wherein the same member is used as a part of the second furnace and as a part of a cage wall of the heat recovery area.

12. The coal boiler according to claim 1 , wherein the second furnace includes an ammonia or urea ejection port.

13. The coal boiler according to claim 1 , further comprising:

a screen tube that is provided for a furnace joint connecting the first furnace to the second furnace;

wherein steam, air, or water is injected into the screen tube to remove ash.

14. The coal boiler according to claim 1 , wherein a pendant structure is employed for the furnaces; wherein a ground-supported, free-standing structure is employed for a cage wall of the heat recovery area; and wherein a member for absorbing the thermal expansion of the cage wall is used to connect to the second furnace.

15. The coal boiler according to claim 1 , wherein the gas temperature in the second furnace is high enough for fuel combustion but not high enough for thermal NOx generation.

16. The coal boiler according to claim 1 , further comprising:

a flow path for supplying a flue gas to the second furnace from the downstream side of a heat exchanger provided for the heat recovery area.

17. The coal boiler according to claim 1 , further comprising:

a structure for hanging a furnace joint provided between the first furnace and the second furnace.

18. A coal boiler combustion method comprising the steps of:

generating a combustion gas by burning coal and air ejected from a burner and allowing the generated combustion gas to ascend in a first furnace;

allowing the combustion gas supplied from the first furnace to descend in a second furnace;

supplying air to the second furnace through a staged combustion after-air port in the second furnace; and

allowing the combustion gas supplied from the second furnace to ascend in a heat recovery area.

Assignments (1)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Mar 24, 2008
From: YAMAMOTO, KENJI; HANDA, MASATO; OKAZAKI, TERUYUKI; YASUDA, KAZUMI; ITO, OSAMU
To: HITACHI, LTD.
Reel/Frame 020689/0429 →
Priority Claims (1)
JP 2007-124063 · May 9, 2007 · national
Continuity (1)
Related Publication 20080276844A1 · Nov 13, 2008