IP Library Granted Patent US 8,863,739
Granted Patent B2
US 8,863,739 · App. 13/387,105 · Granted Oct 21, 2014

Structure for lifting and mounting heliostats and trolley for moving said heliostat

Inventors: Francisco Cerón García (Sevilla, ES); Emiliano Cornago Ramírez (Sevilla, ES); Joaquín De Río Martín (Sevilla, ES)
Assignee: Abengoa Solar New Technologies S.A.
B66C1/62B66C1/10F24J2/10F24J2/52F24J2002/5281
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 8,863,739
App. No.
13/387,105
Granted
Oct 21, 2014
Kind
B2
Abstract

It allows lifting the heliostat in the warehouse and placing it on the cart, and once it reaches the installation spot in the field, the lifting structure is used to lift the heliostat from the cart and place it on a previously installed pedestal. The structure formed by an upper arch and two lower bases, being the upper arch, comprised at the same time by a central, elongated and horizontal profile, which presents two lateral profiles on its ends, from which vertical plates start at the bottom, provided with a hole in the proximity of its lower ends, through which the upper arch ( 2 ) is linked to the lower bases through some fixing mechanism, having the lower bases a semicircular support adapted to receive one of the support arms of the heliostat.

Claims (32)

1. A heliostat lifting and assembling structure, intended for lifting and assembling a heliostat, the heliostat comprising:

a reflective surface composed of multiple flat and/or curved panels that are supported on a reticulated structure, and the reticulated structure is on tour supported on some straps holding two support arms comprised in the heliostat, and

a control mechanism provided with motors for the correct solar orientation, the assembling structure comprising:

two lower bases each one of the lower bases featuring a semicircular support adapted to receive one of the support arms of the heliostat,

an upper arch comprising a central, elongated and horizontal profile,

two lateral profiles on the ends of the upper arch and linked to the central profile at their mid-points,

vertical plates starting at the bottom of the lateral profiles and adapted to go through the heliostat through introduction in some spaces located among panels, and

a hole in the proximity of the lower ends of the vertical plates, through which the upper arch is linked with the lower bases by a fixing mechanism.

2. The assembling structure of claim 1 , wherein the central profile of the upper arch is provided in its upper face with a main ring, adapted to be hooked by a crane, for lifting the structure.

3. The assembling structure according to claim 2 , wherein the main ring additionally comprises some lateral brackets for a greater reinforcement and solidity of the upper arch.

4. The assembling structure of claim 1 , characterized in that the lateral profiles are provided with secondary rings.

5. The assembling structure of claim 4 , wherein the secondary rings are arranged in oblique direction, and located in the proximity of the ends of the lateral profiles.

6. The assembling structure of claim 1 , wherein the two lower bases have some flanges on their lateral ends, the flanges featuring a hole, for their attachment to the upper arch.

7. The assembling structure of claim 1 , wherein the semicircular supports have cylindrical bodies on their lateral faces.

8. The assembling structure of claim 1 , wherein the central profile, the two lateral profiles of the upper arch, and the lower bases show a configuration in an I-shape.

9. The assembling structure of claim 1 , characterized in that the fixing mechanism comprises washers, screws and nuts.

10. A heliostat assembling method comprising the steps of:

first lifting of the heliostat located in the interior of a warehouse, using a structure comprising:

two lower bases each one of the lower bases featuring a semicircular support adapted to receive one of the support arms of the heliostat,

an upper arch comprising a central, elongated and horizontal profile,

two lateral profiles located on the ends of the upper arch and linked to the central profile at their mid-points,

vertical plates starting at the bottom of the lateral profiles and adapted to go through the heliostat through introduction in some spaces located among panels, and

a hole provided in the proximity of the lower ends of said vertical plates, through which hole the upper arch is linked with the lower bases by a fixing mechanism;

arranging the heliostat on support plates located in some beams of a chassis of a transporting cart;

hooking the cart by a tractor or similar, through a trailer located in the front of the tractor or similar, for towing the cart towards the spot of installation in the field of the cart, and

final lifting of the heliostat from its position in the cart to a final position on a pedestal which has previously been installed in the proper spot in the field.

11. The method of claim 10 , wherein both the first lifting and the second lifting are carried through a crane adapted to hook some rings located on the upper arch of the structure.

12. The method of claim 10 , wherein the first lifting is carried out in the following way:

the crane is hooked to the upper arch of the structure through the hooks;

the vertical plates of the upper arch are inserted through some spaces located between some panels in the heliostat;

the upper arch and the lower bases are linked by means of a fixing mechanism; and

the structure is lifted by means of the crane, thereby lifting the heliostat, and the heliostat is arranged on the cart.

Assignments (1)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Nov 25, 2013
From: CERON GARCIA, FRANCISCO; CORNAGO RAMIREZ, EMILIANO; DE RIO MARTIN, JOAQUIN
To: ABENGOA SOLAR NEW TECHNOLOGIES S.A.
Reel/Frame 031670/0133 →
Priority Claims (1)
ES 200930523 · Jul 28, 2009 · national
Continuity (1)
Related Publication 20120176695A1 · Jul 12, 2012