Installation and industrial operation of an air supply system to dose given air flows to each individual cell of a set of electrolytic cells

Inventors: Víctor Vidaurre Heiremans (Santiago, CL); Edgardo Beltran Navarro (Santiago, CL); Victor Manuel Vidaurre Miller (Santiago, CL)
Assignee: ANCOR TECMIN, S.A.
C25C7/06B01F3/04269C25C1/12C25C7/00C25D5/08C25D21/10B01F2003/04319B01F2003/04361
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 9,169,574
App. No.
13/515,501
Granted
Oct 27, 2015
Kind
B2
Abstract

The invention refers to an air supply system ( 1 ) for a group of cells ( 4 ) arranged for dosing the individual air demand of each electrolytic cell ( 2 ) that must be fed to its electrolyte through a system of controlled air diffusion. It comprises a low pressure blower ( 5 ), a central feed pipe ( 6 ) and a plurality of feed branches ( 7 ); a flow meter ( 8 ) and a flow regulator ( 9 ) are associated to each feed branch. The assembly is connected to a bent hose ( 12 ) arranged on the walls of said electrolytic cell ( 2 ) to allow connection with an isobaric ring ( 3 ), so that the fed air can be diffused homogeneously and sustainedly in time to the electrolyte through selectively perforated hoses ( 16 ). The present invention also refers to the process of installation, calibration and operation of the air supply system.

Claims (18)

1. An air supply system ( 1 ) for a group of electrolytic cells ( 4 ) arranged for dosing the individual air demand of each electrolytic cell ( 2 ) that must be fed to its electrolyte through a system of controlled air diffusion, characterized in that it comprises:

at least one low pressure blower ( 5 );

at least one central feed pipe ( 6 ) connected to said at least one blower ( 5 ), wherein from said at least one central air feed pipe ( 6 ) emerge a plurality of feed hose branches ( 7 ), wherein each of said electrolytic cells having walls and each branch of said feed hose branches reaches up to a front wall of said walls;

selectively perforated hoses ( 16 ) formed by flexible anticorrosive material hoses ( 17 ) which have a selective distribution of perforations ( 18 ) parallel to the longitudinal axis of each of said selectively perforated hoses ( 16 );

a flow meter ( 8 ) arranged in each of said feed hose branches, the volume of air measured by said flow meter ( 8 ) being regulated by a flow regulator ( 9 ), and wherein said flow meter ( 8 ) is connected between a first feed hose ( 10 ) of said branch ( 7 ) and a second feed hose ( 11 ) of said branch ( 7 ), said first hose ( 10 ) being connected with flow regulator ( 9 ) and said second hose ( 11 ) being connected to a portion of bent hose ( 12 ) suitable to be affixed on the walls of said electrolytic cell ( 2 ) to allow a hose end ( 13 ) to be connected with an isobaric ring ( 3 ), so that the fed air can be diffused homogeneously and sustainedly in time to the electrolyte through said selectively perforated hoses ( 16 ), wherein besides flow regulator ( 9 ) a second flow regulator ( 21 ) is provided to enable deactivation of flow meter ( 8 ); and

a bypass ( 20 ) provided between each electrolytic cell ( 2 ) and the central feed pipe ( 6 ), wherein a first end of said bypass ( 20 ) is connected to the branch hose ( 7 ) and the second end of said bypass is connected to the second feed hose ( 11 ), and wherein said bypass ( 20 ) is provided with a cut off valve ( 22 ).

2. An air supply system ( 1 ) for a group of electrolytic cells ( 4 ) according to claim 1 , characterized in that flow regulator ( 9 ) is an adjustable squeeze clamp for the feed hose ( 7 ).

3. An air supply system ( 1 ) for a group of electrolytic cells ( 4 ) according to claim 1 , characterized in that the flow regulator ( 9 ) is a valve.

4. An air supply system ( 1 ) for a group of electrolytic cells ( 4 ) according to claim 1 , characterized in that said flow meter ( 8 ) comprises a translucent tube ( 14 ) in whose interior a sphere ( 15 ) is lodged, said translucent tube having a maximum limit ( 24 ) and a minimum limit ( 25 ) wherein sphere ( 15 ) statically floats in between according to the given flow of air of air required.

5. An air supply system ( 1 ) for a group of electrolytic cells ( 4 ) according to claim 4 , characterized in that said translucent tube has an inverted conical shape, wherein the lower portion of said tube is supplied with a seat ( 23 ) to lodge sphere ( 15 ) obstructing the passage of fluids and acting as an emergency retention valve, in the event that the hydraulic column pressure of the electrolyte inside the electrolytic cell ( 2 ) is greater than the pressure of the fed air flow, into electrolytic cell ( 2 ).

6. An air supply system ( 1 ) for a group of electrolytic cells ( 4 ) according to claim 5 , characterized in that in the lower portion of flow meter ( 8 ) a second sphere ( 30 ) is lodged and a corresponding occluding seat ( 29 ) is provided to allow to block passage to the electrolyte if its backpressure is greater than the pressure of the fed air flow into electrolytic cell ( 2 ).

7. An air supply system ( 1 ) for a group of cells ( 4 ) according to claim 5 , characterized in that in the lower portion of flow meter ( 8 ) a unidirectional valve is lodged that allows to shut off the passage of electrolyte if its backpressure is greater than the pressure of the fed air flow into electrolytic cell ( 2 ).

8. An air supply system ( 1 ) for a group of electrolytic cells ( 4 ) according to claim 5 , characterized in that said flow meter ( 8 ) has sensors ( 26 ) suitable for emitting alert signals to a monitoring means ( 28 ) enabling timely actions to be taken in the event of detection of anomalies or faults of air supply system ( 1 ) in any electrolytic cell ( 2 ).

9. An air supply system ( 1 ) for a group of electrolytic cells ( 4 ) according to claim 1 , characterized in that the perforations are equidistantly separated along the length of the hose.

10. An air supply system ( 1 ) for a group of electrolytic cells ( 4 ) according to claim 9 , characterized in that the angles of the perforations, seen in transversal cut, are within a range of −90° to +90°.

11. An air supply system ( 1 ) for a group of electrolytic cells ( 4 ) according to claim 10 , characterized in that said range is preferably of −30° to +30°.

12. An air supply system ( 1 ) for a group of electrolytic cells ( 4 ) according to claim 9 , characterized in that said perforations have a diameter ranging between 0.2 to 0.6 mm.

13. An air supply system ( 1 ) for a group of cells ( 4 ) according to claim 1 , characterized in that the perforations are arranged in groups, the groups of perforations being separated equidistantly.

Assignments (1)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jul 14, 2015
From: VIDAURRE HEIREMANS, VICTOR, MR.; BELTRAN NAVARRO, EDGARDO, MR.; VIDAURRE MILLER, VICTOR MANUEL, MR.
To: ANCOR TEMIN, S.A.
Reel/Frame 036088/0218 →
Priority Claims (1)
CL 023-2010 · Jan 13, 2010 · national
Continuity (1)
Related Publication 20130220831A1 · Aug 29, 2013