Bolt tightening robot for wind turbines

Inventors: Kenneth Johst (Frederiksberg C, DK); Lars Jagd (Malmö, SE); Jonas Bovin (Virum, DK); Gerald Marinitsch (Kalsdorf, AT)
F03D1/001B25J9/1633F03D11/04F05B2230/50F05B2240/912F05B2260/301Y02E10/728
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 9,212,651
App. No.
14/365,928
Granted
Dec 15, 2015
Kind
B2
Abstract

A robot to bolt down a series of nut bolts in a joint circular flange connection of a wind turbine, which robot comprises at least two wheels and a drive to transport the robot along the series of nut bolts and a tool to bolt down a nut bolt with a predefined torque and a position sensor to position the tool above the nut bolt to be bolted down and a robot control system to control the tightening process and document parameters relevant for the stability of each bolted down nut bolt.

Claims (15)

1. A robot to bolt down a series of nut bolts in a joint circular flange connection of a wind turbine, the robot comprising:

a drive to transport the robot along the series of nut bolts; and

a tool to bolt down a nut bolt with a predefined torque; and

a position sensor to position the tool above the nut bolt to be bolted down; and

a robot control system to control the tightening process and to store parameters to document the bolted down nut bolts.

2. The robot according to claim 1 , wherein the robot control system stores parameters that document whether or not each bolted down nut bolt has been mounted according to a specification.

3. The robot according to claim 1 , wherein the robot control system controls the robot to bolt down the nut bolts in the joint circular flange connection in a predefined sequence.

4. The robot according claim 1 , wherein the drive of the robot comprises wheels that are angled to each other in order to move the robot around the series of nut bolts in the circle of the joint circular flange connection.

5. The robot according to claim 1 , wherein the drive of the robot comprises a belt drive with magnets attached to the belt which magnets temporarily connect to the metal wall of the joint circular flange connection of the wind turbine to transport the robot.

6. The robot according to claim 5 , wherein the belt drive comprises adjustable rollers for the belt to ensure that the magnets temporarily connect the circular metal wall.

7. The robot according to claim 1 , wherein the tool to bolt down the nut bolts with a predefined torque uses either a bolt stretch method or is realized by a torque wrench and a clamp system.

8. A method to bolt down a series of nut bolts in a joint circular flange connection of a wind turbine, the method comprising:

positioning a nut bolt on each bolt of the joint circular flange connection;

positioning a robot according to claim 1 on the joint circular flange connection and initiating the robot control system to tighten the nut bolts in a predefined sequence and/or with a predefined torque and to store parameters to document the bolted down nut bolts.

9. The method according to claim 8 , wherein the robot control system stores parameters that document whether or not each bolted down nut bolt has been mounted according to a specification.

Assignments (2)
LICENSE Recorded Oct 13, 2020
From: ADMEDE AB
To: VESTAS WIND SYSTEMS A/S
Reel/Frame 054043/0203 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jun 26, 2017
From: JOHST, KENNETH; JAGD, LARS; BOVIN, JONAS; MARINITSCH, GERALD
To: ADMEDE AB
Reel/Frame 042813/0185 →
Priority Claims (1)
EP 11194856 · Dec 21, 2011 · regional
Continuity (1)
Related Publication 20140350724A1 · Nov 27, 2014