IP Library › Granted Patent US 9,625,057
Granted Patent B2
US 9,625,057 · App. 14/651,758 · Granted Apr 18, 2017

Multi-activity pipe-laying vessel

Inventor: Yves Pierre Raymond Inbona (London, GB)
Assignee: Petrofac Ltd.
F16L1/12B63B35/03F16L1/18F16L1/19F16L1/205F16L1/207
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 9,625,057
App. No.
14/651,758
Granted
Apr 18, 2017
Kind
B2
Abstract

A pipe-laying vessel has a bow, a stern and a weather deck therebetween, with a moonpool passing through the weather deck. The vessel includes an S-lay pipe deployment facility located below the weather deck, having a main firing line extending along a centerline of the vessel and a pipe assembly factory for assembling single lengths of pipe to form pipe assemblies and introduce them into the firing line for deployment from the vessel. The vessel further includes a J-lay pipe deployment facility for deploying pipe through the moonpool, the J-lay pipe deployment facility including a tower located above the moon pool and pipe handling equipment for delivering pipe assemblies from the firing line to the tower. The moonpool is located to one side of the firing line. By virtue of this configuration a relatively compact structure can be achieved whereby minimal length and width dimensions for the vessel are achievable.

Claims (24)

1. A pipe-laying vessel having a bow, a stern and a weather deck therebetween, with a moonpool passing through the weather deck, the vessel comprising an S-lay pipe deployment facility located below the weather deck, having a main firing line extending along a centerline of the vessel extending from the bow to the stern of the vessel, and a pipe assembly factory for assembling single lengths of pipe to form pipe assemblies and introduce them into the firing line for deployment from the stern of the vessel, the vessel further comprising a J-lay pipe deployment facility for deploying pipe through the moonpool, the J-lay pipe deployment facility comprising a tower located above the moon pool and pipe handling equipment for delivering pipe assemblies from the firing line to the tower, wherein the moonpool is located to one side of the firing line.

2. The vessel according to claim 1 , wherein the moonpool is separated from the firing line by a cofferdam extending to the weather deck.

3. The vessel according to claim 1 , wherein the firing line comprises a weather protected area at its forward end and the moonpool extends to a position that is forward of a rearward limit of the weather protected area.

4. The vessel according to claim 1 , wherein the pipe assembly factory is arranged to assemble quad joints on the firing line.

5. The vessel according to claim 1 , wherein the pipe handling equipment comprises an elevator arranged to elevate quad joints from the firing line to the weather deck.

6. The vessel according to claim 5 , wherein the elevator is located rearward of the moonpool.

7. The vessel according to claim 1 , wherein the pipe handling equipment comprises a loader arm arranged to up-end quad joints from the weather deck for presentation to the tower.

8. The vessel according to claim 1 , wherein the pipe assembly factory extends from a position rearward of the moonpool to a position forward of the moonpool and further comprises conveyors for transporting pipe assemblies forwards past the moonpool on both sides thereof.

9. The vessel according to claim 1 , further comprising a longitudinal bulkhead that intersects the moonpool, the bulkhead being provided with a first breach rearward of the moonpool for passage of pipe segments from inboard to outboard and a second breach forward of the moonpool for passing doubles from outboard to inboard through the bulkhead.

10. The vessel according to claim 1 , wherein the tower is pivotally connected to the vessel, preferably at the weather deck, and can be tilted forwards from a vertical position to an inclined position of at least 45 degrees.

11. The vessel according to claim 1 , wherein the tower is arranged for performing operations through the moonpool simultaneously with operation of the S-lay pipe deployment facility to deploy the pipeline.

12. The vessel according to claim 1 , wherein the moonpool is generally rectangular, having a length at the hull parallel to the centreline of at least twice its width.

13. The vessel according to claim 1 , further comprising a heavy duty crane located at the stern of the vessel and having a capacity to lift at least 3000 tonnes through the moonpool.

14. The vessel according to claim 1 , further comprising portside and starboard loading cranes for loading of pipe segments from outboard of the vessel on both port and starboard sides and for delivering the pipe segments to pipe storage on the weather deck and/or to the factory deck.

15. A method of laying a pipeline from a pipe-laying vessel having an S-lay firing line and a J-lay tower located adjacent to a moonpool, the method comprising deploying pipe from the vessel in J-lay mode by:

fabricating doubles in a pipe factory below a weather deck of the vessel;

introducing the doubles into the firing line;

joining the doubles to form a quad joint on the firing line;

elevating the quad joint from the firing line to the weather deck and presenting it to the tower;

connecting the quad joint to the pipeline and lowering the pipeline through the moonpool.

16. The method of claim 15 , wherein the vessel has a bow, a stern and a weather deck therebetween, with a moonpool passing through the weather deck, the vessel comprising an S-lay pipe deployment facility located below the weather deck, having a main firing line extending along a centerline of the vessel and a pipe assembly factory for assembling single lengths of pipe to form pipe assemblies and introduce them into the firing line for deployment from the stern of the vessel, the vessel further comprising a J-lay pipe deployment facility for deploying pipe through the moonpool, the J-lay pipe deployment facility comprising a tower located above the moon pool and pipe handling equipment for delivering pipe assemblies from the firing line to the tower, wherein the moonpool is located to one side of the firing line.

17. The method according to claim 15 , further comprising subsequent or prior to deploying pipe in J-lay mode, abandoning and recovering the pipeline and performing S-lay deployment of pipe over a stern of the vessel.

18. The method according to claim 15 , further comprising performing auxiliary operations through the moonpool during S-lay deployment.

19. The method according to claim 15 , further comprising loading pipe segments onboard the vessel from both the port and starboard sides.

Assignments (2)
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Jan 23, 2019
From: PETROFAC LTD.
To: SHANGHAI ZHENHUA HEAVY INDUSTRIES CO., LTD.
Reel/Frame 048098/0977 →
ASSIGNMENT OF ASSIGNOR'S INTEREST Recorded Aug 27, 2015
From: INBONA, YVES PIERRE RAYMOND
To: PETROFAC LTD.
Reel/Frame 036436/0522 →
Priority Claims (1)
GB 1222495.2 · Dec 13, 2012 · national
Continuity (1)
Related Publication 20150316174A1 · Nov 5, 2015