Method of constructing a reinforced compound concrete beam containing demolished concrete lumps

Inventors: Bo Wu (Guangdong, CN); Simin Jian (Guangdong, CN)
Assignee: SOUTH CHINA UNIVERSITY OF TECHNOLOGY
E04C3/293E04C3/06E04G21/00
View Patent ↗
Loading inventors, assignments & file history…
Monitor This Case
Get email alerts when status or documents change.
Order Certified Copies
Most orders are placed with the USPTO same day — all within 24 business hours.
Order via The Patent Place →
Pre-filled with this patent's details
Quick Facts
Patent No.
US 10,273,691
App. No.
16/056,384
Granted
Apr 30, 2019
Kind
B2
Abstract

A method of construction process of a reinforced compound concrete beam containing demolished concrete lumps comprising following steps. Form an I-shaped steel member with a discontinuous top flange by welding a bottom flange plate, a web and two steel plates. Set up a bottom die of the reinforced compound concrete beam. After hoisting the I-shaped steel member with the discontinuous top flange in position, bind longitudinal bars, waist bars and stirrups, and finally set up a side die. (2) Wet the demolished concrete lumps, pour the fresh concrete with a thickness of 20-30 mm inside a cavity formed by the bottom die and the side die, and then put a layer of the wet demolished concrete lumps in a gap between the two steel plates. The two steel plates are two rectangle steel plates or two trapezoid steel plates. Stir artificially so that the demolished concrete lumps are uniformly distributed inside the cavity formed by the bottom die and the side die. Pour a layer of fresh concrete into the cavity and vibrate the demolished concrete lumps and the fresh concrete in the cavity, so that the demolished concrete lumps are uniformly distributed in the fresh concrete. Repeatedly and alternately pour the fresh concrete and the demolished concrete lumps until the cavity is filled.

Claims (4)

1. A method of constructing a reinforced compound concrete beam containing demolished concrete lumps, the method comprising:

(1) forming an I-shaped steel member with a discontinuous top flange by welding one bottom flange plate and two steel plates to a web, preparing a bottom die portion of a die for casting the reinforced compound concrete beam, then hoisting the I-shaped steel member with the discontinuous top flange in position on the bottom die portion, and then binding together longitudinal bars, waist bars and stirrups, and finally setting up a side die portion of the die for casting the reinforced compound concrete beam;

(2) wetting the demolished concrete lumps, pouring the fresh concrete to a thickness of 20-30 mm inside a cavity formed by the bottom die and the side die, and then putting a layer of the wet demolished concrete lumps in a gap between the two steel plates, the two steel plates being two rectangle steel plates or two trapezoid steel plates, and stirring the wet demolished concrete lumps so that the wet demolished concrete lumps are uniformly distributed inside the cavity formed by the bottom die and the side die, then pouring a layer of fresh concrete into the cavity formed by the bottom die and the side die and vibrating the wet demolished concrete lumps and the fresh concrete in the cavity formed by the bottom die and the side die, so that the wet demolished concrete lumps are uniformly distributed in the fresh concrete;

repeatedly and alternately pouring the fresh concrete and the wet demolished concrete lumps until the cavity formed by the bottom die and the side die is filled.

Priority Claims (1)
CN 2014 1 0609233 · Oct 31, 2014 · national
Continuity (2)
Division 15522776
Related Publication 20180340334A1 · Nov 29, 2018